File #: 22-907    Name: Receive Status Report on Laguna Seca Start-Finish Bridge and Track Overlay Project, Project 8498
Type: General Agenda Item Status: Agenda Ready
File created: 9/19/2022 In control: Capital Improvement Committee
On agenda: 10/10/2022 Final action:
Title: Receive a status report on the Laguna Seca Start-Finish Bridge and Track Overlay Project, Project 8498.
Attachments: 1. CIC Report, 2. Attachment A-Board Resolution 22-313
Title
Receive a status report on the Laguna Seca Start-Finish Bridge and Track Overlay Project, Project 8498.
Report
RECOMMENDATION:
It is recommended that the Capital Improvement Committee receive a status report on the Laguna Seca Start-Finish Bridge and Track Overlay Project, Project 8498.

SUMMARY/DISCUSSION:
This report reflects the Laguna Seca Start-Finish Bridge and Track Overlay Project, Project 8498 (Project), status at the time of writing. Subsequent updates will track progress for outstanding items (completed items will be removed). Staff will also provide the Committee with a verbal update on any developments following the submittal of this report.

This Project replaces the deteriorated Start-Finish Bridge and Track Overlay at WeatherTech Raceway at Laguna Seca (WRLS), located in the Laguna Seca Recreation Area (LSRA) at 1021 Monterey Salinas Highway, Salinas, CA. The Project is being constructed in a Single Phase. On August 11, 2022, the Notice to Proceed (NTP) was issued for the Project. The NTP authorized Contractor Granite Construction Company, the lowest responsive bidder, to commence work on Pre-Construction documents and procure/produce the necessary shop drawings. Demolition and site work is scheduled to begin on November 1, 2022, with Project completion anticipated by June 14, 2023.

The County has entered into an agreement with MNS Engineers Inc. (MNS) to act as the Construction Manager to oversee the Project and track its progress. Currently, the Project is on schedule.

Project Schedule
Notice to Proceed Issued: August 11, 2022
Pre-Construction Complete: November 1, 2022
Construction Mobilization Begins: November 1, 2022
Construction Complete/Demobilization: June 14, 2023

Project Budget
Budget Approved by BOS 7/26/22 $ 14,902,198





Project Costs
- Environmental/Engineering: $ 500,000
- Construc...