File #: 23-186    Name: Key Capital Projects Update
Type: General Agenda Item Status: Agenda Ready
File created: 2/21/2023 In control: Capital Improvement Committee
On agenda: 3/6/2023 Final action:
Title: Receive a report on Key Capital Projects managed by the Public Works, Facilities and Parks Department (PWFP) for the period from July 1, 2022 through December 31, 2022 (Fiscal Year 2022-23, Quarters One and Two).
Attachments: 1. CIC Report, 2. Attachment A - FY22-23 Q1-Q2 CIP Status Report. xlsx
Title
Receive a report on Key Capital Projects managed by the Public Works, Facilities and Parks Department (PWFP) for the period from July 1, 2022 through December 31, 2022 (Fiscal Year 2022-23, Quarters One and Two).
Report
RECOMMENDATION:
It is recommended that the Capital Improvement Committee:
Receive a report on Key Capital Projects managed by the Public Works, Facilities and Parks Department (PWFP) for the period from July 1, 2022 through December 31, 2022 (Fiscal Year 2022-23, Quarters One and Two).

SUMMARY
This report provides a status update on key capital improvement projects managed by PWFP for the first and second quarters of Fiscal Year (FY) 2022-23. During this period, there were 49 active capital projects totaling $135.8 million in costs-to-date: 24 Public Works (Road and Bridge) projects at $57.0 million and 25 Facilities projects at $78.8 million. This report includes project estimates, costs to date, and status. Five Facilities and six Public Works projects were completed during this reporting period. Three Public Works projects were substantially completed, where construction was completed, and project closeout activities were underway (e.g., submitting documentation to regulatory agencies to close out permits).

DISCUSSION:
Capital projects are non-recurring, exceed $100,000 cost, and have an estimated useful life of at least five years to provide long-term assets to the County. All the active capital improvement projects being managed by PWFP are summarized in Attachment A. Additional detail is provided below for selected completed projects and those with significant activity during the first quarter (Q1) and second quarter (Q2) of FY 2022-23.

Completed Projects - Facilities

1590 Moffett St-ITD Facility-HVAC Upgrade
The project involved installing HVAC units in a large imaging room and in a telecom room. Neither space had dedicated cooling for the sensitive equipment. The project budget was $200,000. The project general contrac...

Click here for full text