File #: 22-444    Name: Reconstruction of Cooper and Murphy Roads
Type: General Agenda Item Status: RMA Public Works - Consent
File created: 5/10/2022 In control: Board of Supervisors
On agenda: 5/24/2022 Final action: 5/24/2022
Title: a. Adopt Plans and Special Provisions for the Cooper Road Reconstruction, Project No. 1152 to reconstruct and resurface Cooper Road from Blanco Road to State Route 183, approximately 2.9 miles; b. Adopt Plans and Special Provisions for the Murphy Road Reconstruction, Project No. 1169 to reconstruct Murphy Road from San Juan Road to Santa Cruz County Line, approximately 0.6 mile; and c. Authorize the Director of Public Works, Facilities, and Parks to advertise the projects' "Notice to Bidders" in the Monterey County Weekly.
Attachments: 1. Board Report, 2. Attachment A - Location Map, 3. Attachment B - Project Budget, 4. Attachment C - Book 1 Cooper Road Reconstruction, Project No. 1152, 5. Attachment D - Book 2 Cooper Road Reconstruction, Project No. 1152, 6. Attachment E - Book 1 Murphy Road Reconstruction, Project No. 1169, 7. Attachment F - Book 2 Murphy Road Reconstruction, Project No. 1169, 8. Completed Board Order Item No. 46
Title
a. Adopt Plans and Special Provisions for the Cooper Road Reconstruction, Project No. 1152 to reconstruct and resurface Cooper Road from Blanco Road to State Route 183, approximately 2.9 miles;
b. Adopt Plans and Special Provisions for the Murphy Road Reconstruction, Project No. 1169 to reconstruct Murphy Road from San Juan Road to Santa Cruz County Line, approximately 0.6 mile; and
c. Authorize the Director of Public Works, Facilities, and Parks to advertise the projects' "Notice to Bidders" in the Monterey County Weekly.
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors:
a. Adopt Plans and Special Provisions for the Cooper Road Reconstruction, Project No. 1152 to reconstruct and resurface Cooper Road from Blanco Road to State Route 183, approximately 2.9 miles;
b. Adopt Plans and Special Provisions for the Murphy Road Reconstruction, Project No. 1169 to reconstruct Murphy Road from San Juan Road to Santa Cruz County Line, approximately 0.6 mile; and
c. Authorize the Director of Public Works, Facilities, and Parks to advertise the projects'
"Notice to Bidders" in the Monterey County Weekly.

SUMMARY/DISCUSSION:
Each project, in general, consists of reconstructing the existing asphalt roadway by grinding the existing pavement and reutilizing it as road base, overlaying hot mix asphalt (HMA) concrete, clearing and grubbing, installing pavement traffic stripes and performing traffic control. The Cooper Road project will reconstruct Cooper Road from Blanco Road to State Route 183, approximately 2.9 miles. The Murphy Road project will reconstruct Murphy Road from San Juan Road to the Santa Cruz County Line, approximately six tenths (0.6) of a mile. Both projects were identified as priority projects in the Capital Improvement Plan.

The bid openings for these projects are set for June 24, 2022, at 2:00 p.m., in the Board Chambers, County of Monterey, Administration Building, Government Center, 168 West Alisal Street, Salinas, Californ...