Title
Consider:
a. Authorizing preliminary actions to prepare a project description and perform other engineering and design work to commence environmental review for the Interlake Tunnel Project;
b. Requesting the Monterey County Board of Supervisors to authorize proceeding with negotiation and execution of a funding agreement between Monterey County and the Monterey County Water Resources Agency for an amount not to exceed $2.5 million to perform the necessary work to commence environmental review of the Interlake Tunnel Project, said funds to be reimbursed to Monterey County if the Project is approved and financed; and
c. Authorizing the General Manager of the Monterey County Water Resources Agency to enter into the necessary agreements to prepare for and commence environmental review of the Project in an initial amount not to exceed $500,000 provided funding is approved by Monterey County.
Report
RECOMMENDATION:
It is recommended that the Monterey County Water Resources Agency Board of Supervisors:
a) Authorize preliminary actions to prepare a project description and perform other engineering and design work to commence environmental review for the Interlake Tunnel Project; b) Request the Monterey County Board of Supervisors to authorize proceeding with negotiation and execution of a funding agreement between Monterey County and the Monterey County Water Resources Agency for an amount not to exceed $2.5 million to perform the necessary work to commence environmental review of the Interlake Tunnel Project, said funds to be reimbursed to Monterey County if the Project is approved and financed; c) Authorize the General Manager of the Monterey County Water Resources Agency to enter into the necessary agreements to prepare for and commence environmental review of the Project in an initial amount not to exceed $500,000 provided funding is approved by Monterey County.
SUMMARY/DISCUSSION:
The Interlake Tunnel Project ("Project") was included in the...