File #: 17-0139    Name: Deltawrx 2017
Type: General Agenda Item Status: Passed
File created: 2/3/2017 In control: Board of Supervisors
On agenda: 3/7/2017 Final action: 3/7/2017
Title: Approve and authorize the Contracts Purchasing Officer, or Contracts Purchasing Supervisor, to sign a County of Monterey Standard Agreement with DELTAWRX, LLC for project management and related services for the Monterey County Next Generation Radio System Project (NGEN), in an amount not to exceed $120,000.00 for the period of January 15, 2017 through June 30, 2017.
Attachments: 1. Board Report, 2. CONTRACT 5 DWX Monterey County PM Agreement 2017-01-30, 3. Completed Board Order
Title
Approve and authorize the Contracts Purchasing Officer, or Contracts Purchasing Supervisor, to sign a County of Monterey Standard Agreement with DELTAWRX, LLC for project management and related services for the Monterey County Next Generation Radio System Project (NGEN), in an amount not to exceed $120,000.00 for the period of January 15, 2017 through June 30, 2017.
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors:
a. Approve and authorize the Contracts Purchasing Officer, or Contracts Purchasing Supervisor, to sign a County of Monterey Standard Agreement with DELTAWRX, LLC for project management and related services for the Monterey County Next Generation Radio System Project (NGEN), in an amount not to exceed $120,000.00 for the period of January 15, 2017 through June 30, 2017.
SUMMARY/DISCUSSION:
In December, 2010, the Board of Supervisors approved the contract with DELTAWRX, LLC to provide Project Management and associated services for the design and implementation of the Monterey County Next Generation (NGEN) Public Safety Radio System. Since that Agreement, DELTAWRX has proven to be a valuable partner in the development of functional requirements, telecommunication radio site development, radio frequency acquisition, and coordination between the prime NGEN contractor, Harris Corporation, and multiple departments within the County of Monterey.
The NGEN Project was scheduled for completion in December 2016. Unexpected issues surrounding the functionality of the radio system have been identified during the course of the Delivered Audio Quality (DAQ) test causing the project to be extended through the close of the fiscal year. This contract will allow DELTAWRX to continue with project management activities and responsibilities through the estimated NGEN system completion date and debrief period.
OTHER AGENCY INVOLVEMENT:
The agreement has been reviewed by County Counsel as to legal form.
FINANCING:
The costs in the Agreement wit...