File #: 18-1176    Name: East Garrison Subdivision Phase 2 Infrastructure Improvements
Type: General Agenda Item Status: Consent Agenda
File created: 11/30/2018 In control: Board of Supervisors
On agenda: 12/11/2018 Final action:
Title: a. Accept as complete a portion of the East Garrison Subdivision Phase 3 Infrastructure Improvements, including road, drainage, and infrastructure improvements; and b. Accept the completed road improvements on Watkins Gate Road, Watkins Gate Road/Reservation Road Intersection and Reservation Road paving, traffic improvements, and signalization into the County's maintained road system; and c. Approve the release of Phase 3 On-site and Off-site infrastructure improvements Performance Bond in the amount of $4,674,000 and Labor and Materials Bond in the amount of $2,336,800, Bond Number SUR0043482, related to said improvements in accordance with Government Code section 66499.7; and d. Approve the release of Phase 3 Performance Bond for Grading and Erosion Control in the amount of $658,000 and Labor and Materials Bond for Grading and Erosion Control in the amount of $329,000, Bond Number SUR0043481, related to said improvements in accordance with Government Code section 66499.7; and e. Appr...
Attachments: 1. Board Report, 2. Attachment A -Location Map, 3. Attachment B - Bond Summary, 4. Attachment C - Final Map, 5. Attachment D - East Garrison Phase Three, 6. Attachment E - MCWD Resolution No. 2018-53, 7. Attachment F - Faithful Performance Security Bond, 8. Attachment G - Laborers & Materialmen Security Bond (SUR-481), 9. Attachment H - Grading & Erosion Control Security Bond, 10. Attachment I - Laborers & Materialmen Security Bond (SUR-482), 11. Attachment J - Monumentaition Security Bond, 12. Attachment K - Maintenance Security Bond, 13. Attachment L - Subdivision Improvement Agreement, 14. Attachment M - Urban Services Agreement, 15. Attachment N - Amendment to Urban Services Agmt., 16. Attachment O - Temporary Maintenance Agreement, 17. Attachment P - Operation and Maintenance Plan, 18. Attachment Q - Whitson Engineers Letter of Completion, 19. 49. Completed Board Order
Date Action ByActionResultAction DetailsSearchable Meeting DetailsVideo
No records to display.
Title
a. Accept as complete a portion of the East Garrison Subdivision Phase 3 Infrastructure Improvements, including road, drainage, and infrastructure improvements; and
b. Accept the completed road improvements on Watkins Gate Road, Watkins Gate Road/Reservation Road Intersection and Reservation Road paving, traffic improvements, and signalization into the County's maintained road system; and
c. Approve the release of Phase 3 On-site and Off-site infrastructure improvements Performance Bond in the amount of $4,674,000 and Labor and Materials Bond in the amount of $2,336,800, Bond Number SUR0043482, related to said improvements in accordance with Government Code section 66499.7; and
d. Approve the release of Phase 3 Performance Bond for Grading and Erosion Control in the amount of $658,000 and Labor and Materials Bond for Grading and Erosion Control in the amount of $329,000, Bond Number SUR0043481, related to said improvements in accordance with Government Code section 66499.7; and
e. Approve the release of Phase 3 Monumentation Bond in the amount of $75,000, Bond Number SUR0043484, related to said improvements in accordance with Government Code section 66499.7; and
f. Approve the acceptance of Phase 3 Maintenance Bond in the amount of $934,720.
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors:
a. Accept as complete a portion of the East Garrison Subdivision Phase 3 Infrastructure Improvements, including road, drainage, and infrastructure improvements; and
b. Accept the completed road improvements on Watkins Gate Road, Watkins Gate Road/Reservation Road Intersection and Reservation Road paving, traffic improvements, and signalization into the County's maintained road system; and
c. Approve the release of Phase 3 On-site and Off-site infrastructure improvements Performance Bond in the amount of $4,674,000 and Laborer and Materials Bond in the amount of $2,336,800, Bond Number SUR0043482, related to said improvements in accordance with Gove...

Click here for full text