title
Support a recommendation to the Board of Supervisors to add Parks Roof Replacement and Repair Project to the RMA Fiscal Year 2019-20 Capital Work Program, pending consideration by the Budget Committee regarding funding.
report
RECOMMENDATION:
It is recommended that the Capital Improvement Committee support a recommendation to the Board of Supervisors to add Parks Roof Replacement and Repair Project (Project) to the RMA Fiscal Year 2019-20 Capital Work Program, pending consideration by the Budget Committee regarding funding.
SUMMARY/DISCUSSION:
Over the years, the roofs at various Parks facilities have deteriorated to the point where they no longer perform as designed. In some cases, especially at San Lorenzo Park, there are multiple leaks in multiple roofs. In one facility, daylight is visible through the roof overhead. Attachment A identifies several Parks facilities roofs in immediate need of replacement or repair to prevent further damage to the facility and resolve potential safety concerns. RMA-Parks has procured estimates from its JOC program, which is prepared to complete these projects prior to the rainy season. Delay of these roof repairs will lead to further deterioration of the Parks facilities and result in higher repair costs.
RMA proposes utilizing its Job Order Contracting services to complete the roof replacements and repairs to the listed facilities at a total estimated cost of $225,757. This Project, and associated costs, was not included in the FY 2020-24 Five-Year CIP, so it was not considered for a funding allocation by the Board of Supervisors.
RMA recommends that the Capital Improvement Committee support its recommendation to the Board of Supervisors to add the Roof Replacement and Repair Project for County Parks Facilities to the RMA FY 2019-20 Capital Work Program, pending consideration by the Budget Committee regarding funding.
OTHER AGENCY INVOLVEMENT:
None. Due to late submission of this Board Report, the CAO Budget a...
Click here for full text