File #: 20-162    Name: Jail Housing Addition, Project 8819
Type: General Agenda Item Status: Agenda Ready
File created: 2/28/2020 In control: Capital Improvement Committee
On agenda: 3/9/2020 Final action:
Title: Receive a Status Report on the Jail Housing Addition, Project 8819.
Attachments: 1. CIC Report, 2. Attachment A - Project Summary and Critical Issues, 3. Attachment B - Project Budget, 4. Attachment C - Change Order History
Title
Receive a Status Report on the Jail Housing Addition, Project 8819.
Report
It is recommended that the Capital Improvement Committee receive a Status Report on the Jail Housing Addition, Project 8819.

SUMMARY/DISCUSSION:
The Jail Housing Addition (Project) provides 576 new beds in eight (8) housing units distributed on two floors, program spaces for inmates, administration and staff support spaces, and a public entrance with video visitation.

The majority (95%) of construction is complete. Remaining tasks include flooring finishes, furniture, mechanical, electrical and plumbing finishing, commissioning and punch list items. Many of these tasks cannot be completed until additional California State Fire Marshall (CSFM) inspector requirements, noted below, are addressed.

The original completion date was scheduled as July 31, 2019. The project team negotiated and agreed to extend the completion date to December 31, 2019 of which 89 days were identified as compensable (excusable) and 64 as non-compensable. Based on the Contractor's construction schedule, the completion date is now estimated as March 31, 2020. However, critical time impact issues related to field changes from the CSFM may extend the Project schedule into Summer 2020. Project delays after the construction contract end date of December 31, 2019 may be subject to a time delay claim by the contractor, which includes a daily rate payable by the County. All time delay claims are subject to review and negotiation by the County. Claim review includes determining any concurrent delays by multiple stakeholders which may offset any contractor monetary claims against the County.

Additional CSFM requirements include extensive reconstruction to create fire rated penetrations in the floors and added Underwriters Laborites (UL) listings not included in the approved plans for wall joints, mechanical duct shafts, and other previously approved construction that are items. Addressing the requirement for fire ra...

Click here for full text