File #: WRAG 20-254    Name: Salinas Pump Amendment No. 3
Type: WR General Agenda Status: Agenda Ready
File created: 6/5/2020 In control: Water Resources Agency Board of Directors
On agenda: 6/15/2020 Final action:
Title: Approve Amendment No. 3 to the Agreement with Salinas Pump Company to extend the Agreement period through June 30, 2022 to provide well and pump maintenance, repair services and well logging services for the Castroville Seawater Intrusion Project (CSIP); and authorize the General Manager to execute Amendment No. 3
Attachments: 1. Board Report, 2. Amendment No.pdf, 3. Amendment No. 2, 4. Amendment No. 1, 5. Salinas Pump Company Agreement, 6. Board Order
Date Action ByActionResultAction DetailsSearchable Meeting DetailsVideo
No records to display.
Title
Approve Amendment No. 3 to the Agreement with Salinas Pump Company to extend the Agreement period through June 30, 2022 to provide well and pump maintenance, repair services and well logging services for the Castroville Seawater Intrusion Project (CSIP); and authorize the General Manager to execute Amendment No. 3
Report
RECOMMENDATION:
It is recommended that the Monterey County Water Resources Agency Board of Directors:

Approve Amendment No. 3 to the Agreement with Salinas Pump Company to extend the Agreement period through June 30, 2022 to provide well and pump maintenance, repair services and well logging services for the Castroville Seawater Intrusion Project (CSIP); and authorize the General Manager to execute Amendment No. 3

SUMMARY/DISCUSSION:
On August 24, 2015, the Board of Directors approved a three-year Professional Services Agreement with Salinas Pump Company in the amount of $156,000 to provide maintenance, repair and well logging services for the CSIP supplemental wells and pumps on an as-needed basis.

On December 6, 2016, the Board of Directors approved Amendment No. 1 to the Agreement with Salinas Pump Company in the amount of $150,000 to provide maintenance, repair and well logging services for the CSIP supplemental wells and pumps on an as-needed basis, and to extend the Agreement term to June 30, 2020. Amendment No. 2 increased the amount payable by $300,000 to provide rehabilitation and maintenance work on CSIP supplemental wells.

The purpose of Amendment No. 3 is to allow access to as-needed well logging services, maintenance and repair of CSIP wells and pumps through June 30, 2022. The Scope of Work for Amendment No. 3 remains the same as described in Exhibit A of the Agreement.

OTHER AGENCY INVOLVEMENT:
None.

FINANCING:
Funds are available in Fund 131 - CSIP Operations and Maintenance.

Prepared by: Manuel Saavedra, Associate Water Resources Engineer, (831) 755-4860

Approved by: Brent Buche, General...