PLN210094 - PAJARO SUNNY MESA COMMUNITY SERVICES DISTRICT
(VARIOUS OWNERS)
6.
Public hearing to consider improvements to the Pajaro Sunny Mesa Community Services Springfield
water distribution system including resuming water service to 73 properties between Springfield Road
and Struve Road and adding a new connection at the Moss Landing Mobile Home Park (105
connections) replacing the existing water system for the mobile home park. Water system
improvements include: conversion of a test well to a production well; new water storage tanks, a new
booster pump station; new distribution piping and installation of new individual service laterals and
meters. Improvements will be located within 100 feet of ESHA.
Project Location: The property is located northeast of the intersection of Highway 1 and Springfield
Road, Royal Oaks [74 associated parcels under various owners] (Assessor’s Parcel Number
413-014-001-000), North County Land Use Plan, Coastal Zone
CEQA Action: Consider the environmental effects of the project described in the Mitigated Negative
Declaration for the Springfield Water System Improvement Project (State Clearinghouse No.
2020080200) adopted by the Board of Directors of the Pajaro Sunny Mesa Community Services
District (Resolution No. 10-01-20).
Kayla Nelson, Assistant Planner, presented this item.
Applicant Representative: Denise Duffy and Nick Panofsky
Public Comment:
Margie Kay, Kelli Hutten, Ignacio Garcia
It was moved by Commissioner Mendoza, seconded by Commissioner Diehl
and passed by the following vote to Considering the environmental effects of
the project described in the Mitigated Negative Declaration for the Springfield
Water System Improvement Project adopted by the Board of Directors of the
Pajaro Sunny Mesa Community Services District and approve the Combined
Development Permit.
AYES:
Daniels, Diehl, Getzelman, Gonzalez, Work, Monsalve, Mendoza,
Roberts
NOES: None
ABSENT:
None
ABSTAIN: None
Commissioner Daniels excused herself from the Commission at 3:00 p.m.