was adopted by the Board of Supervisors on June 15, 2021.
Approved
Public Works, Facilities and Parks
43.
a. Award a contract to Granite Rock Company, the lowest responsible bidder for the Salinas Road
and Pajaro Project, Project No. 1175 (Project), in the total amount of $735,253;
b. Approve the Performance and Payment Bonds executed and provided by Granite Rock Company;
c. Authorize a contingency, not to exceed 10% of the contract amount or $73,525 to provide funding
for approved contract change orders;
d. Authorize the Director of Public Works, Facilities and Parks to execute the contract subject to the
provisions of the Public Contract Code and Board Policies as applicable, approve change orders to the
contract that do not exceed 10% of the original contract amount or $73,525 do not significantly change
the scope of work, and not to exceed the maximum contract amount of $808,778; and
e. Authorize the Director of Public Works, Facilities and Parks to execute a Certificate of Completion
and record a Notice of Completion with the County Recorder when the Director determines that the
contract is complete in all respects in accordance with the Plans and Special Provisions for the
construction of the Salinas Road and Pajaro Project, Project No. 1175.
California Environmental Quality Act (CEQA) Action: A Notice of Exemption was filed on
March 19, 2025, pursuant to CEQA Guidelines, California Code of Regulations (CCR) Section 15301
Existing Facilities. The Project has been determined to be categorically exempt (Class 1) because the
Project is to perform repair and maintenance of existing streets and similar facilities which involve no
expansion of an existing use (See CEQA Guidelines, California Code of Regulations (CCR) Section
15301 Existing Facilities).
Approved
44.
a. Approve submittal of a subapplication under the California Office of Emergency Services (Cal
OES) to the Federal Emergency Management Agency’s Hazard Mitigation Grant Program (HMGP),
to request funding for the Scenic Road Protection Structure Project;
b. Authorize the Director of Public Works, Facilities and Parks or his/her designee, to act as the agent
for the County in processing all documentation to secure these funds; and
c. Direct PWFP to return to the Board for approval prior to acceptance of grant award.
Approved
45.
a. Approve Professional Services Agreement with Wallace Group, a California Corporation to
provide professional engineering services for the Chualar Wastewater Consolidation Project, Project
No. C-06-8676-110, Request for Proposals #10951, for an initial term of three years from August 26,
2025 to August 25, 2028, with the option to extend the Agreement for two additional years, for an
amount not to exceed $571,942 and
b. Authorize the Contracts & Purchasing Officer or their designee to execute the Professional Services
Agreement and future amendments to the Agreement where the amendments do not significantly alter
the scope of work or increase the amount by more than 10% ($57,194) of the original approved
Agreement amount of $571,942 bringing the potential overall aggregate not to exceed amount to
$629,136 subject to review and approval as to form by the Office of the County Counsel and as to
fiscal provisions by the Auditor-Controller’s Office.