PLN250071 - CASTLEMAN MICHAEL S JR & CAROL K ET AL
Public hearing to consider demolition of a 1,870 square foot single-family dwelling and construction of a 4,705 square foot two-story single-family dwelling with attached garage, and associated site improvements.
Project Location: 1012 San Carlos Road, Pebble Beach
Proposed CEQA Action: Find the project categorically exempt pursuant to Section 15302 of the California Environmental Quality Act Guidelines.
Body
RECOMMENDATIONS
It is recommended that the Zoning Administrator adopt a resolution:
1) Find that the project qualifies as a Class 2 Categorical Exemption pursuant to Section 15302 of the CEQA Guidelines and there are no exceptions pursuant to Section 15300.2; and
2) Approve a Design Approval to allow demolition of a 1,870 square foot single-family dwelling and construction of a 4,705 square foot two-story single-family dwelling with attached garage, and associated site improvements.
The attached draft resolution includes findings and evidence for consideration (Exhibit A). Staff recommends approval subject to 7 conditions of approval.
PROJECT INFORMATION
Property Owner: Michael Castleman
Agent: John Moore
APNs: 007-282-004-000
Zoning: Medium Density Residential, with Building Site - 6, Design Control, and Recreational Equipment Storage zoning overlays (“MDR/B-6-D-RES”)
Plan Area: Greater Monterey Peninsula Area Plan
Flagged and Staked: Yes
SUMMARY
Staff is recommending approval of a Design Approval subject to the findings and evidence in the attached Resolution (see Exhibit A), and subject to the conditions of approval attached to the Resolution. Please read these carefully and contact the planner if you have any questions. Unless otherwise noted in the conditions, the applicant will be required to satisfy all permit conditions prior to the issuance of a building/grading permits and/or commencement of the approved use. The decision on this project is appealable to the Planning Commission.
The project was referred to the Del Monte Forest Land Use Advisory Committee for review on August 21, 2025. The LUAC meeting minutes were not available at the time of this staff report; however, the LUAC approved unanimously.
OTHER AGENCY INVOLVEMENT
The following County agencies have reviewed this project, have comments, and/or have recommended conditions:
HCD-Engineering Services
HCD-Environmental Services
Environmental Health Bureau
Pebble Beach Community Services District (Fire)
Prepared and Reviewed by: Fionna Jensen, Principal Planner
Approved by: Jacquelyn Nickerson, Principal Planner
The following attachments are on file with HCD:
Exhibit A - Draft Resolution, including;
• Conditions of Approval
• Site Plan, Floor Plans, Elevations, and Colors and Materials
Exhibit B - Vicinity Map
cc: Front Counter Copy; Pebble Beach Community Services District (Fire); Environmental Health Bureau; HCD-Engineering Services; HCD-Environmental Services; Anna Ginette Quenga, AICP, Principal Planner; Craig Spencer, HCD Chief of Planning; Fionna Jensen, Project Planner; Kel Seliger, Owner; John Moore, Agent; The Open Monterey Project (Molly Erickson); LandWatch (Executive Director); Christina McGinnis, Keep Big Sur Wild; Planning File PLN250071.