SIGNED BOARD REPORT"�|E�X�MONTEREY COUNTY BOARD OF SUPERVISORS
MEETING: June 14,2011 Consent AGENDA NO.: s-2
SUBJECT: a. Award a contract to MCM Construction, Inc., the lowest responsible base
bidder, for the Lonoak Road Bridge at Lewis Creek Replacement Project,
Bridge No. 402, Federal Aid Project No. BRLOZB-5944 035), Project
No. 11-220565; in the total amount of $1,499,999;
b. Approve the Performance and Payment Bonds executed and provided by
MCM Construction, Inc.;
c. Authorize a contingency not to exceed 10% of the Contract amount) to
provide funding for approved contract change orders; and
d. Authorize the Director of Public Works to execute the contract and subject
to the terms of the Public Contract Code, approve change orders to the
contract that do not exceed 10% of the original contract amount and do not
significantly change the scope of work.
DEPARTMENT: RMA Public Works
RECOMMENDATIONS:
It is recommended that the Board of Supervisors:
a. Award a contract to MCM Construction, Inc., the lowest responsible base bidder, for the
Lonoak Road Bridge at Lewis Creek Replacement Project, Bridge No. 402, Federal Aid
Project No. BRLOZB-5944(035), Project No. 11-220565; in the total amount of
$1,499,999;
b. Approve the Performance and Payment Bonds executed and provided by MCM
Construction, Inc.;
c. Authorize a contingency not to exceed 10% of the Contract amount) to provide funding for
approved contract change orders; and
d. Authorize the Director of Public Works to execute the contract and subject to the terms of
the Public Contract Code, approve change orders to the contract that do not exceed 10% of
the original contract amount and do not significantly change the scope of work.
SUMMARY/DISCUSSION:
The Board approved the Plans and Special Provisions for the Lonoak Road Bridge at Lewis
Creek Replacement Project, Bridge No. 402, Federal Aid Project No. BRLOZB-5944 035),
Project No. 11-220565, on March 15, 2011. The project was subsequently advertised and bids
were solicited. The bids were opened on April 14, 2011, and the lowest responsible base bidder
was MCM Construction, Inc. in the amount of $1,499,999. The Engineer's Estimate is
$2,000,000 for the project.
The Lonoak Road Bridge at Lewis Creek Replacement Project consists of construction of a new
two lane bridge on the existing alignment, a detour constructed adjacent to the existing bridge,
associated approach embankment grading and paving, removal of the existing bridge, and
associated improvements on Lewis Creek and Lonoak Road.
BIB]
40723-U01
SIGNED-U02
BOARD-U02
REPORT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103566-U03
C10-U03
BOARD-U03
REPORTS-U03
6/28/2011-U04
HANCOCKD-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
SIGNED BOARD REPORT"�|E�X�Award MCM Construction, Inc. contract for Lonoak Road Bridge at Lewis Creek Project
June 14, 2011
Page 2
OTHER AGENCY INVOLVEMENT:
County Counsel and Contracts/Purchasing attended the bid opening and reviewed the low bid for
conformance with applicable regulations. County Counsel and Risk Management approved the
Contract and Bonds as to form, and insurance provisions, respectively.
FINANCING:
There is no financial impact to the General Fund for FY 2010/11 or FY 2011/12. The estimated
total cost of the project, including engineering, environmental, right-of-way and construction, is
$3,227,675. The project is funded by Federal Highway Administration FHWA) and Highway
Bridge Replacement and Rehabilitation Program HBRR) funds, State Seismic Retrofit Funds
and Road Funds.
Prepared by: Approved by:
fA Arturo A. Adlawan, P.E. 831) 755-4823 azdan T. Emrani, M.S., P.E.
Senior Civil Engineer Director of Public Works
Dated: June 6, 2011
Attachments: Board Order; Project Budget; Bid Summary; Contract; Bonds on file with the
Clerk of the Board); Location Map
BIB]
40723-U01
SIGNED-U02
BOARD-U02
REPORT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103566-U03
C10-U03
BOARD-U03
REPORTS-U03
6/28/2011-U04
HANCOCKD-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm�57
Before the Board of Supervisors in and for the
County of Monterey, State of California
Agreement No. A-12007; Construction No. 2011-005
a. Award a contract to MCM Construction, Inc., the
lowest responsible base bidder, for the Lonoak Road
Bridge at Lewis Creek Replacement Project, Bridge
No. 402, Federal Aid Project No. BRLOZB-5944
035), Project No. 11-220565; in the total amount of
$1,499,999;
b. Approve the Performance and Payment Bonds
executed and provided by MCM Construction, Inc.;
c. Authorize a contingency not to exceed 10% of the
Contract amount) to provide funding for approved
contract change orders; and
d. Authorize the Director of Public Works to execute
the contract and subject to the terms of the Public
Contract Code, approve change orders to the
contract that do not exceed 10% of the original
contract amount and do not significantly change the
scope of work...
Upon motion of Supervisor Salinas, seconded by Supervisor Armenta, and carried by
those members present, the Board hereby;
a. Awarded a contract to MCM Construction, Inc., the lowest responsible base
bidder, for the Lonoak Road Bridge at Lewis Creek Replacement Project, Bridge
No. 402, Federal Aid Project No. BRLOZB-5944 035), Project No. 11-220565;
in the total amount of $1,499,999;
b. Approved the Performance and Payment Bonds executed and provided by MCM
Construction, Inc.;
c. Authorized a contingency not to exceed 10% of the Contract amount) to provide
funding for approved contract change orders; and
d. Authorized the Director of Public Works to execute the contract and subject to the
terms of the Public Contract Code, approve change orders to the contract that do
not exceed 10% of the original contract amount and do not significantly change
the scope of work.
PASSED AND ADOPTED on this 14th day of June, 2011, by the following vote, to wit:
AYES: Supervisors Armenta, Calcagno, Salinas, Parker, and Potter
NOES: None
ABSENT: None
I, Gail T. Borkowski, Clerk of the Board of Supervisors of the County of Monterey, State of California, hereby
certify that the foregoing is a true copy of an original order of said Board of Supervisors duly made and entered
in the minutes thereof of Minute Book 75 for the meeting on June 14, 2011.
Dated: June 20, 2011 Gail T. Borkowski, Clerk of the Board of Supervisors
Revised: July 7, 2011 County of Monterey, State of California
By
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm�CONTRACT FOR PUBLIC WORK
COUNTY OF MONTEREY
STATE OF CALIFORNIA
CONTRACT NO. 11-220565
THIS AGREEMENT, made in triplicate by and between the COUNTY OF MONTEREY, a
political subdivision of the State of California, hereinafter called the County," and
MCM CONSTRUCTION, INC., hereinafter called the Contractor,"
WITNESSETH:
1) THE WORK
The Contractor shall do all the work and furnish all the materials, except such as
are mentioned in any of the contract documents to be furnished by the County, necessary to
construct and complete in a good, workmanlike and substantial manner and to the satisfaction of
the County, the following public work:
LONOAK ROAD BRIDGE
AT LEWIS CREEK
COUNTY BRIDGE NO. 402, STATE BRIDGE NO. 44C-0158
PROJECT NO. 11-220565
STATE PROJECT NO. NO. EA 05-927094L
FEDERAL AID PROJECT NO. BRLOZB-5944 035)
in accordance with this agreement and with all of the following additional contract documents
which are incorporated into and made a part of this agreement:
a) The Standard Specifications, dated July 2002 and the Standard Specifications
dated May 2006 with Amendments issue date 11-30-10 were referenced; and
the Standard Plans, dated July 2002 and May 2006 of the State of California,
Department of Transportation.
b) A set of plans and cross sections when applicable) entitled:
LONOAK ROAD BRIDGE AT LEWIS CREEK,
STATE BRIDGE NO. 44C-0158) 44C-0179, COUNTY BR. NO. 402
FEDERAL-AID PROJECT NO. BRLOZB-5944 035)
PROJECT NO. 11-220565
c) The Special Provisions for the work.
d) The Notice to Bidders calling for bids.
e) The Payment and Performance bonds required.
LONOAK ROAD BRIDGE 1
CONTRACT NO. 11-220565
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm�f)
Local Agency Bidder DBE information, Exhibit 15-G(2)
g) Certificate of Insurance.
h) The accepted bid/proposal including the following:
1) List of Subcontractors
2) Equal Employment Opportunity Certification
3) Public Contract Code
Section 10285.1 Statement
Section 10162 Questionnaire
Section 10232 Statement
4) Non-Collusion Affidavit
5) Debarment and Suspension Certification
6) Non-Lobbying Certification for Federal Aid Contracts
7) Disclosure of Lobbying Activities
8) Statement Concerning Employment of Undocumented Aliens
9) Contractor's Certificate as to Worker's Compensation
10) List of Satisfied Public Agencies
11) Bidder's Bond
12) Bidder's List
13) Local Agency Bidder UDBE Commitment, Exhibit 15-G(1)
14) UDBE Information Good Faith Efforts, Exhibit 15-H
All contract documents are intended to cooperate, so that any work called for in one and
not mentioned in another is to be executed the same as if mentioned in all. However, should
there be any conflict between the terms of this instrument and the Contractor's bid or proposal,
then this instrument shall control.
2. WORKERS' COMPENSATION
In accordance with the provisions of Section 3700 of the Labor Code, the Contractor
and every Subcontractor will be required to secure the payment of compensation to his
employees.
3. CONTRACT PRICE
The County shall pay the Contractor the following prices for the performance of this
contract:
ITEM ITEM CODE ITEM DESCRIPTION UNIT OF ESTIMATE UNIT PRICE ITEM TOTAL
NO MEASURE QUANTITY In Figures) In Figures)
1 066072 Maintain Detour LS 1 $5,000.00 $5,000.00
LONOAK ROAD BRIDGE
AT LEWIS CREEK
COUNTY BRIDGE NO. 402, STATE BRIDGE NO. 44C-0158
PROJECT NO. 11-220565
STATE PROJECT NO. EA 05-927094L
FEDERAL AID PROJECT NO. BRLOZB-5944 035)
LONOAK ROAD BRIDGE 2
CONTRACT NO. 11-220565
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm�ITEM ITEM CODE ITEM DESCRIPTION UNIT OF ESTIMATE UNIT PRICE ITEM TOTAL
NO MEASURE QUANTITY In Figures) In Figures)
2 066105 Resident Engineer's Office LS 1 $35,000.00 $35,000.00
Project Schedule
3 070010 Critical Path Method) LS 1 $5,000.00 $5,000.00
Temporary Fence
4 071302 Type BW) m 200 $25.00 $5,000.00
Temporary Fence
5 071325 Type ESA) m 75 $20.00 $1,500.00
6 073031 900 mm Temporary Culvert m 100 $100.00 $10,000.00
900 mm Temporary
7 073031A Flared End Section EA 8 $400.00 $3,200.00
Prepare Storm Water Pollution
8 074019 Prevention Program S) LS 1 $1,200.00 $1,200.00
9 074020 Water Pollution Control LS 1 $10,000.00 $10,000.00
10 120090 Construction Area Signs LS 1 $3,000.00 $3,000.00
11 120100 Traffic Control System LS 1 $12,000.00 $12,000.00
12 129000 Temporary Railing Type K) m 50 $150.00 $7,500.00
13 129100 Temporary Crash Cushion
Module EA 22 $350.00 $7,700.00
14 150605 Remove Fence m 325 $8.00 $2,600.00
15 151554 Install Salvaged) Gate with
Posts EA 3 $1,4 00.00 $4,200.00
16 152386 Relocate Roadside
Sign One Post EA 2 $250.00 $500.00
17 152423 Adjust Monument to Grade
EA 2 $600.00 $1,200.00
18 153103 Cold Plane AC Pavement
60 mm) m2 15 $250.00 $3,750.00
19 157550 Bridge Removal
LS 1 $45,000.00 $45,000.00
20 160101 Clearing and Grubbing
LS 1 $10,000.00 $10,000.00
21 170101 Develop Water Supply
LS 1 $10,000.00 $10,000.00
22 190101 Roadway Excavation F)
m3 850 $25.00 $21,250.00
23 190136 Roadway Excavation
Detour) F) m3 315 $85.00 $26,775.00
24 192003 Structure Excavation
m3
207
Bridge) F) $50.00 $10,350.00
25 192020 Structure Excavation
Type D) F) m3 7 $120.00 $840.00
26 193003 Structure Backfill
Bridge) F) m3 115 $125.00 $14,375.00
27 198001 I mport Borrow Detour)
m3 440 $85.00 $37,400.00
LONOAK ROAD BRIDGE 3
CONTRACT NO. 11-220565
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm�ITEM ITEM CODE ITEM DESCRIPTION UNIT OF ESTIMATE UNIT PRICE ITEM TOTAL
NO MEASURE QUANTITY In Figures) In Figures)
28 203016A Erosion Control
Type D-Seed Mix #1) S) m2 700 $3.00 $2,100.00
29 203016B Erosion Control
Type D-Seed Mix #2) S) m2 3,300 $3.00 $9,900.00
30 208252A 38 mm Plastic Pipe
PR 200) Supply Line) m 30 $120.00 $3,6 00.00
31 208751A 102 mm Galvanized Steel
Pipe Conduit m 15 $150.00 $2,250.00
32 220101 Finish Roadway
LS 1 $5,000.00 $5,000.00
33 260200A Detour Baserock
m3 460 $85.00 $39,100.00
34 260201 Aggregate Base Class 2)
m3 910 $70.00 $63,700.00
35 390102 Hot Mix Asphalt Type A)
to 610 $140.00 $85,400.00
36 393001 Pavement Reinforcing
Fabric m2 13 $25.00 $325.00
37 490663 1.5 m Cast-In-Drilled Hole
Concrete Piling S) m 30 $4,900.00 $147,000.00
38 490696 Furnish Piling Class
900) P) m 360 $165.00 $59,400.00
39 490697 Drive Pile Class 900)
EA 24 $2,200.00 $52,800.00
40 500001 Prestressing Cast-In-Place
Concrete S) LS 1 $25,000.00 $25,000.00
41 510051 Structural Concrete,
Bridge Footing m3 26 $430.00 $11,180.00
42 510053 Structural Concrete,
Bridge m3 280 $1,167.00 $326,760.00
43 519129A Joint Seal Assembly
Type B MR=50 mm) m 21 $250.00 $5,250.00
44 520102 Bar Reinforcing Steel
Bridge) P)(S) kg 63,000 $1.80 $113,400.00
45 566011 Roadside Sign-One Post
EA 8 $400.00 $3,200.00
46 721007 RSP 220 kg 1/4 Ton)
Method B) m3 125 $93.00 $11,625.00
47 729010 Rock Slope Protection
Fabric m2 250 $2.00 $500.00
48 731507 Minor Concrete
Gutter Depression) m3 1.6 $2,200.00 $3,520.00
49 750501 Miscellaneous Metal
Bridge) kg 66 $20.00 $1,320.00
50 800002 Fence Type BW, Wood
Post) m 270 $33.00 $8,910.00
51 800701 Reconstruct Pipe Fence
m 20 $330.00 $6,600.00
52 810110 Survey Monument
EA 2 $1,400.00 $2,800.00
53 820118 Guard Railing Delineator
EA 4 $140.00 $560.00
LONOAK ROAD BRIDGE 4
CONTRACT NO. 11-220565
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm�ITEM
ITEM CODE
ITEM DESCRIPTION UNIT OF ESTIMATE UNIT PRICE ITEM TOTAL
NO MEASURE QUANTITY In Figures) In Figures)
54 820152 Object Marker
Type L-2 CA) EA 4 $130.00 $520.00
55 832003 Metal Beam Guard Railing
Wood Post) S) m 31 $75.00 $2,325.00
56 839565 Terminal System
Type SRT) S) EA 4 $2,400.00 $9,600.00
57 839720 Concrete Barrier Type 732)
m 112 $340.00 $38,080.00
58 840561 100 mm Thermoplastic
Traffic Stripe S) m 1,414 $2.00 $2,828.00
59 840656 Paint Traffic Stripe 2-Coat)
m 186 $4.00 $744.00
60 850111 Pavement Marker
Retroreflective) S) EA 110 $6.00 $660.00
61 860791A 4) 102 mm Direct Buried
Utility Conduit at&t) m 50 $85.00 $4,250.00
62 860792A 102 mm Utility Conduit in
bridge at&t) m 47 $100.00 $4,700.00
63 994629 Relocate Building Barn) LS 1
$1,000.00 $1,000.00
64 999990 Mobilization 10%)
LS 1 $149,752.00 $149,752.00
P) Denotes Partial Pay Item
F) Denotes Final Pay Item TOTAL BID $1,499,999.00
S) Denotes Specialty Item
LONOAK ROAD BRIDGE 5
CONTRACT NO. 1 1 220565
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm�IN WITNESS WHEREOF, the parties hereto have executed this Agreement as of the
dates appearing below their respective signatures.
CONTRACTOR:
By:
Name:
MCM CONSTRUCTION, INC.
EDMUNDO A. PUCHI
Title: TREASURER
Date: APRIT. 28, 2011
COUNTY OF MONTEREY:
By:
Name: Yazdan T. Emrani, P.E.
Title: Director of Public Works
Date:
By:
APPROVE AS TO FORM
Name: Cynthia L. Hasson
Title: Deputy County Counsel
Date:
APPROVE AS TO INDEMNITY/
R1%jrx bW c Vi~I UAGE
COUNTY OF MONTEREY
By: APPROVED
Name:i N SL&PAl`1i'Q94AN G UAG E
LONOAK ROAD BRIDGE
6
CONTRACT NO. 11-220565
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm�CERTIFICATE OF AUTHORITY
I, EDMUNDO A. PUCHI, Treasurer, General Counsel and Assistant Secretary of MCM
Construction, Inc. hereby certify that the company is a corporation duly organized pursuant to
and under the laws of the State of California. The Company was first incorporated in 1973 and
is in good standing in this State.
I further attest that the following persons are officers of the Corporation:
James A. Carter President
Harry D. McGovern Vice President, General Manager and Secretary
Edmundo A. Puchi Treasurer, General Counsel and Assistant Secretary
James R. Coppini Assistant Secretary
I further attest that the President, Vice President and Treasurer of the Corporation,
are authorized to execute all documents necessary to bind the Corporation to any bid,
contract or similar offer or obligation.
I certify under penalty of perjury that the above statements are true and correct as
reflected in the Corporation's records of Corporate acts and resolutions.
Executed this date of May 27, 2011 at North Highlands, California.
EDMUNDO A. PUCHI
Treasurer, General Counsel and Assistant Secretary
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm �COUNTY OF MONTEREY
PERFORMANCE BOND
WHEREAS, the County of Monterey has awarded to Principal, M M. C M
as Contractor, a contract for the following project:
Construction, Inc.
LONOAK ROAD BRIDGE
AT LEWIS CREEK
COUNTY BRIDGE NO. 402, STATE BRIDGE NO.44C-0158
PROJECT NO. 11-220565
STATE PROJECT NO. EA 05-927094L
FEDERAL AID PROJECT NO. BRLOZB-5944 035)
BOND #105471528
Premium: $6,750.00
WHEREAS, Principal, as Contractor, is required to furnish a bond in connection with said
contract, to secure the faithful performance of said contract.
NOW, THEREFORE, we M.C.M. Construction, Inc. as Principal,
and Travelers Casualty and Surety Company of America
as Surety, are held and firmly
bound unto the County of Monterey, a political subdivision of the State of California hereinafter
called Count lri the penal Sum Of
O payme1 aNl 4 payment of which sum in lawful money of the United States, well and truly to be made, we bind
ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally,
firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT:
If the Principal, as Contractor, or Principal's heirs, executors, administrators, successors,
or assigns, 1) shall in all things stand to and abide by and well and truly keep and perform the
covenants, conditions, and agreements in said contract and any alteration thereof made as therein
provided, on Principal's part to be kept and performed, at the time and in the manner therein
specified and in all respects according to their true intent and meaning, and 2) shall defend,
indemnify and save harmless the County, the members of its board of supervisors, and its
officers, agents and employees as therein stipulated, then this obligation shall become null and
void; otherwise, it shall be and remain in full force and virtue.
Surety hereby stipulates and agrees that no change, extension of time, alteration, or addition
to the terms of the contract or the call for bids, or to the work to be performed thereunder, or the
specifications accompanying the same, shall in any way affect its obligation under this bond, and
it does hereby waive notice of any such change, extension of time, alteration or addition to the
terms of said contract or the call for bids, or to the work, or to the specifications.
Whenever the Principal, as Contractor, is in default, and is declared in default, under the
contract by the County of Monterey, the County of Monterey having performed its obligation
under the contract, Surety may promptly remedy the default, or shall promptly:
1) Complete the contract in accordance with its terms or conditions, or
LONOAK ROAD BRIDGE 3
CONTRACT NO. 11-220565
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm
�2) Obtain a bid or bids for submission to County of Monterey for completing the
contract in accordance with its terms or conditions, and upon determination by
County of Monterey and Surety of the lowest responsible and responsive bidder,
arrange for a contract between such bidder and County of Monterey, and make
available as work progresses even though there should be a default or a
succession of defaults under the contract or contracts of completion arranged
under this paragraph) sufficient funds to pay the cost of completion less the
balance of contract price.
If suit is brought upon this bond by the County and judgment is recovered, the Surety shall
pay all litigation expenses incurred by the County in such suit, including attorney's fees, court
costs, expert witness fees and investigation expenses.
IN WITNESS WHEREOF, the above-bounden parties have executed this instrument under
their several seals this 27th day of AFril 20 11 the name and
corporate seal of each corporate party being hereto affixed and these presents duly signed by its
undersigned representative, pursuant to authority of its governing body.
Corporate Seal)
Corporate Seal)
M.C.M. Construction, Inc.
Name and Title EDMUNDO A. PUCHI, TREASURER
Surety
Travelers Casualty and Surety Company of America
Attorney-in-Fact
Attach notary acknowledgment for all signatures and attorney-in-fact certificate for signature by surety's
representative)
LONOAK ROAD BRIDGE 4
CONTRACT NO. 11-220565
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm
�ACKNOWLEDGMENT
State of California
County of Santa Clara
On April 27, 2011 before me, Erin Bautista, Notary Public
insert name and title of the officer)
personally appeared Jean L. Neu
who proved to me on the basis of satisfactory evidence to be the person(a) whose name(&) is/aizx
subscribed to the within instrument and acknowledged to me that kshel!t e* executed the same in
JQis/her/t thE authorized capacity and that by Wher/ t signature(s) on the instrument the
person( R), or the entity upon behalf of which the person(x) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal.
Signature
ERIN BAUTISTA F
Commission # 1884542
Notary Public California
Z
z Santa Clara County
Seal) My Comm. Expires Apr 25, 2014
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm
�WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
TRAVELERS J
POWER OF ATTORNEY
Farmington Casualty Company St. Paul Mercury Insurance Company
Fidelity and Guaranty Insurance Company Travelers Casualty and Surety Company
Fidelity and Guaranty Insurance Underwriters, Inc. Travelers Casualty and Surety Company of America
St. Paul Fire and Marine Insurance Company United States Fidelity and Guaranty Company
St. Paul Guardian Insurance Company
Attorney-In Fact No. 223488
Certificate No. 004157516
KNOW ALL MEN BY THESE PRESENTS: That St. Paul Fire and Marine Insurance Company, St. Paul Guardian Insurance Company and St. Paul Mercury Insurance
Company are corporations duly organized under the laws of the State of Minnesota, that Farmington Casualty Company, Travelers Casualty and Surety Company, and
Travelers Casualty and Surety Company of America are corporations duly organized under the laws of the State of Connecticut, that United States Fidelity and Guaranty
Company is a corporation duly organized under the laws of the State of Maryland, that Fidelity and Guaranty Insurance Company is a corporation duly organized under
the laws of the State of Iowa, and that Fidelity and Guaranty Insurance Underwriters, Inc., is a corporation duly organized under the laws of the State of Wisconsin
herein collectively called the Companies"), and that the Companies do hereby make, constitute and appoint
Bryan D. Martin, Bradley N. Wright, Jean L. Neu, Erin Bautista, and Frances Murphy
of the City of San Jose State of California their true and lawful Attorney(s)-in-Fact,
each in their separate capacity if more than one is named above, to sign, execute, seal and acknowledge any and all bonds, recognizances, conditional undertakings and
other writings obligatory in the nature thereof on behalf of the Companies in their business of guaranteeing the fidelity of persons, guaranteeing the performance of
contracts and executing or guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by law.
11th
IN WITNESS WHEREOF, the Companies have caused this instrument to be signed arid their corporate seals to be hereto affixed, this
day of April 2011
Farmington Casualty Company
Fidelity and Guaranty Insurance Company
Fidelity and Guaranty Insurance Underwriters, Inc.
St. Paul Fire and Marine Insurance Company
St. Paul Guardian Insurance Company
State of Connecticut
City of Hartford ss.
By:
St. Paul Mercury Insurance Company
Travelers Casualty and Surety Company
Travelers Casualty and Surety Company of America
United States Fidelity and Guaranty Company
On this the 11 th day of April 2011 before me personally appeared George W. Thompson, who acknowledged
himself to be the Senior Vice President of Farmington Casualty Company, Fidelity and Guaranty Insurance Company, Fidelity and Guaranty Insurance Underwriters,
Inc., St. Paul Fire and Marine Insurance Company, St. Paul Guardian Insurance Company, St. Paul Mercury Insurance Company, Travelers Casualty and Surety
Company, Travelers Casualty and Surety Company of America, and United States Fidelity and Guaranty Company, and that he, as such, being authorized so to do,
executed the foregoing instrument for the purposes therein contained by signing on behalf of the corporations by himself as a duly authorized officer.
In Witness Whereof, I hereunto set my hand and official seal.
My Commission expires the 30th day of June, 2011.
58440-4-09 Printed in U.S.A.
can C
Marie C. Tetreault, Notary Public
WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm
�A
CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT
State of California
County of Sacramento
On April 28, 2011 before me, Christine Golden, Notary Public
Date
personally appeared Edmundo A. Puchi
Here Insert Name and Title of the Officer
Name(s) of Signer(s)
Place Notary Seal Above
who proved to me on the basis of satisfactory evidence to
be the person(s) whose name(s) is/are-subscribed to the
within instrument and acknowledged to me that
ho/che hoy executed the same in his/hor/thoir authorized
capacity(ies), and that by his/hortheir signature(s)-on the
instrument the person(s)1 or the entity upon behalf of
which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws
of the State of California that the foregoing paragraph Is
true and correct.
WITNESS y and anid official seal.
Signature
OPTIONAL
Though the information below Is not required by law, it may prove valuable to persons relying on the document
and could prevent fraudulent removal and reattachment of this form to another document.
Description of Attached Document
Title or Type of Document: Performance Bond
Document Date: April 27, 2011
Signer(s) Other Than Named Above: None
Capacity(ies) Claimed by Signer(s)
Signer's Name: Edmundo A. Puchi
Individual
Number of Pages: 2
Signer's Name:
Individual
0 Corporate Officer Title(s): reasurer
Corporate Officer Title(s):
Partner Limited El General Recd rr l Ilur,1BFF IrJT Partner Limited General
Attorney in Fact OF SIGNER Attorney in Fact
Top of thumb here Top of thumb here
Trustee Trustee
Guardian or Conservator Guardian or Conservator
Other: Other:
Signer Is Representing: Signer Is Representing:
MCM Construction, Inc.
T
02007 National Notary Association 935.,0 De Soto Ave., P0. Box 2402 Chatsworth, CA 91313.2402� www.NasonalNolarxorg Item #6907 Reorder: CallTdl-Free 1-800-878-6827
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm�COUNTY OF MONTEREY
PAYMENT BOND
Civil Code Section 3249)
BOND #105471528
Premium: Incl. in
Performance Bond
WHEREAS, the County of Monterey has awarded to Principal, as Contractor, a
contract for the following project:
LONOAK ROAD BRIDGE
AT LEWIS CREEK
COUNTY BRIDGE NO. 402, STATE BRIDGE NO.44C-0158
PROJECT NO. 11-220565
STATE PROJECT NO. EA 05-927094L
FEDERAL AID PROJECT NO. BRLOZB-5944 035)
AND WHEREAS, Principal, as Contractor, is required to furnish a bond in connection
with said contract, to secure the payment of claims of laborers, mechanics, materialmen, and
other persons furnishing labor and materials on the project, as provided by law.
NOW, THEREFORE, we M.C.M. Construction, Inc. as
Principal, and Travelers Casualty and Surety Company of America
as Surety, are held and firmly
bound unto the County of Monterey, a political subdivision of the State of California hereinafter
called County"), and to the persons named in California Civil Code section 3181 in the penal
One Nli lion Four Hundred Ninety Nine Thousand Nine Hundred for the
sum of Ninety Nin~/100s--=(1.499.999.00)
payment of which sum in lawful money of the United States, well and truly to be made, we bind
ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally,
firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT:
If the Principal, or any of Principal's heirs, executors, administrators, successors,
assigns, or Subcontractors, 1) fails to pay in full all of the persons named in Civil Code Section
3181 with respect to any labor or materials furnished by said persons on the project described
above, or 2) fails to pay in full all amounts due under the California Unemployment Insurance
Code with respect to work or labor performed on the project described above, or 3) fails to pay
for any amounts required to be deducted, withheld, and paid over to the Employment
Development Department from the wages of employees of the Principal and Subcontractors
pursuant to Unemployment Insurance Code section 13020 with respect to such work and labor,
then the Surety shall pay for the same.
Surety hereby stipulates and agrees that no change, extension of time, alteration or
addition to the terms of the contract on the call for bids, or to the work to be performed there
under, or the specifications accompanying the same, shall in any way affect its obligation under
this bond, and it does hereby waive notice of any such change, extension of time, alteration or
addition to the terms of said contract or the call for bids, or to the work, or to the specifications.
LONOAK ROAD BRIDGE
CONTRACT NO. 11-220565
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm�If suit is brought upon this bond by the County and judgment is recovered, the Surety
shall pay all litigation expenses incurred by the County in such suit, including attorney's fees,
court costs, expert witness fees and investigation expenses.
This bond inures to the benefit of any of the persons named in Civil Code section 318 1,
and such persons or their assigns shall have a right of action in any suit brought upon this bond,
subject to any limitations set forth in Civil Code sections 3247 et seq. Civil Code, Division 3,
Part 4, Title 15, Chapter 7: Payment Bond for Public Works).
IN WITNESS WHERE OF the above-bounden parties have executed this instrument
under their several seals this 27th day of April 20 11 the name and corporate
seal of each corporate party being hereto affixed and these presents duly signed by its
undersigned representative, pursuant to authority of its governing body.
Corporate Seal)
Corporate Seal)
M.C.M. Construction, Inc.
EDMUNDO A. PUCHI, TREASURER
Name and Title
Surety
Travelers Casualty and Surety Company of America
Attorney-in-Fact
Attach notary acknowledgment for all signatures and attorney-in-fact certificate for signature by surety's
representative)
LONOAK ROAD BRIDGE 2
CONTRACT NO. 11-220565
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm�ACKNOWLEDGMENT
State of California
County of Santa Clara
On April 27, 2011 before me, Erin Bautista, Notary Public
insert name and title of the officer)
personally appeared Jean L. Neu
who proved to me on the basis of satisfactory evidence to be the person(a) whose name(a) is/auax
subscribed to the within instrument and acknowledged to me that sheflbe executed the same in
his/her/M* authorized capacity(, and that by his/her/ft j signature(;) on the instrument the
person(J, or the entity upon behalf of which the person(a) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal.
Signature l1 Seal)
ERIN BAUTISTA
Commission # 1884542
z d Notary Public California Z
Z c--.- n-_..
My Comm. Expires Apr 25. 2014
7
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm�WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
TRAVELERS
POWER OF ATTORNEY
Farmington Casualty Company St. Paul Mercury Insurance Company
Fidelity and Guaranty Insurance Company Travelers Casualty and Surety Company
Fidelity and Guaranty Insurance Underwriters, Inc. Travelers Casualty and Surety Company of America
St. Paul Fire and Marine Insurance Company United States Fidelity and Guaranty Company
St. Paul Guardian Insurance Company
Attorney-In Fact No. 223488
Farmington Casualty Company
Fidelity and Guaranty Insurance Company
Fidelity and Guaranty Insurance Underwriters, Inc.
St. Paul Fire and Marine Insurance Company
St. Paul Guardian Insurance Company
KNOW ALL MEN BY THESE PRESENTS: That St. Paul Fire and Marine Insurance Company, St. Paul Guardian Insurance Company and St. Paul Mercury Insurance
Company are corporations duly organized under the laws of the State of Minnesota, that Farmington Casualty Company, Travelers Casualty and Surety Company, and
Travelers Casualty and Surety Company of America are corporations duly organized under the laws of the State of Connecticut, that United States Fidelity and Guaranty
Company is a corporation duly organized under the laws of the State of Maryland, that Fidelity and Guaranty Insurance Company is a corporation duly organized under
the laws of the State of Iowa, and that Fidelity and Guaranty Insurance Underwriters, Inc., is a corporation duly organized under the laws of the State of Wisconsin
herein collectively called the Companies"), and that the Companies do hereby make, constitute and appoint
Bryan D. Martin, Bradley N. Wright, Jean L. Neu, Erin Bautista, and Frances Murphy
of the City of San Jose State of California their true and lawful Attorney(s)-in-Fact,
each in their separate capacity if more than one is named above, to sign, execute, seal and acknowledge any and all bonds, recognizances, conditional undertakings and
other writings obligatory in the nature thereof on behalf of the Companies in their business of guaranteeing the fidelity of persons, guaranteeing the performance of
contracts and executing or guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by law.
11th
IN WITNESS WHEREOF, the Comp tze have caused this instrument to be signed and their-corporate seals to be hereto affixed, this
day of April Lll1J 1
State of Connecticut
City of Hartford as.
By:
Certificate No.004157517
St. Paul Mercury Insurance Company
Travelers Casualty and Surety Company
Travelers Casualty and Surety Company of America
United States Fidelity and Guaranty Company
On this the 11th da April 2011
Y of before me personally appeared George W. Thompson, who acknowledged
himself to be the Senior Vice President of Farmington Casualty Company, Fidelity and Guaranty Insurance Company, Fidelity and Guaranty Insurance Underwriters,
Inc., St. Paul Fire and Marine Insurance Company, St. Paul Guardian Insurance Company, St. Paul Mercury Insurance Company, Travelers Casualty and Surety
Company, Travelers Casualty and Surety Company of America, and United States Fidelity and Guaranty Company, and that he, as such, being authorized so to do,
executed the foregoing instrument for the purposes therein contained by signing on behalf of the corporations by himself as a duly authorized officer.
In Witness Whereof, I hereunto set my hand and official seal.
My Commission expires the 30th day of June, 2011.
58440-4-09 Printed in U.S.A.
t'n can C
Marie C. Tetreault, Notary Public
WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
REVISED COMPLETED BOARD ORDERm�CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT
State of California
County of Sacramento
on April 28, 2011 before me, Christine Golden, Notary Public
Date Here Insert Name and Title of the Officer
personally appeared Edmundo A. Puchi
Name(s) of Signer(s)
who proved to me on the basis of satisfactory evidence to
be the person(s) whose name(s) is/acs-subscribed to the
within instrument and acknowledged to me that
he/she/they executed the same in his/her eir authorized
capacity(ies), and that by his/her leir signature(s)-on the
instrument the person(s)1 or the entity upon behalf of
which the person(s) acted, executed the instrument.
CHRISTINE GOLDEN
Commission # 1895518
Notary Public California
Sacramento County
My Comm. Expires Aug 9, 2014
Place Notary Seal Above
I certify under PENALTY OF PERJURY under the laws
of the State of California that the foregoing paragraph is
true and correct.
WITNESS and ar1d official
Signature INVA AiL
Si
P
bfi
N
gnature
otary
u
c
OPTIONAL
Though the Information below Is not required by law, it may prove valuable to persons relying on the document
and could prevent fraudulent removal and reattachment of this form to another document.
Description of Attached Document
Title or Type of Document: Payment Bond
Document Date: April 27, 2011 Number of Pages: 2
Signer(s) Other Than Named Above: None
Capacity(ies) Claimed by Signer(s)
Signer's Name: Edmundo A. Puchi
0 Individual
Corporate Officer Title(s): Treasurer
Partner 0 Limited General
Attorney in Fact
0 Trustee
Guardian or Conservator
Other:
Signer Is Representing:
MCM Construction. Inc.
RIG, I I Ii:~F,1BFriIIIT
OF SIGNER
Top of thumb here
Signer's Name:
Individual
Corporate Officer Title(s):
Partner Limited General
Attorney in Fact
Trustee
Guardian or Conservator
Other:
Signer Is Representing:
RIC T T! IUh.1B i,mrI1
OF SIG'JER
Top of thumb here
02007 National Notary AssociatIon 9350 Do Solo Ave R.0. Box 2402 Chatsworth, CA 91313-2402� www NatlonaP4otarxorg Item 116907 Reorder. CaIIT7ll-Free 1-800-876-6927
BIB]
40732-U01
REVISED-U02
COMPLETED-U02
BOARD-U02
ORDER-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO103975-U03
C15-U03
COMPLETED-U03
BOARD-U03
ORDER-U03
7/8/2011-U04
MARCELLAC-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��CONTRACT FOR PUBLIC WORK
COUNTY OF MONTEREY
STATE OF CALIFORNIA
CONTRACT NO. 11-220565
THIS AGREEMENT, made in triplicate by and between the COUNTY OF MONTEREY, a
political subdivision of the State of California, hereinafter called the County," and
MCM CONSTRUCTION, INC., hereinafter called the Contractor,"
WITNESSETH:
1) THE WORK
The Contractor shall do all the work and furnish all the materials, except such as
are mentioned in any of the contract documents to be furnished by the County, necessary to
construct and complete in a good, workmanlike and substantial manner and to the satisfaction of
the County, the following public work:
LONOAK ROAD BRIDGE
AT LEWIS CREEK
COUNTY BRIDGE NO. 402, STATE BRIDGE NO.44C-0158
PROJECT NO. 11-220565
STATE PROJECT NO. NO. EA 05-927094L
FEDERAL AID PROJECT NO. BRLOZB-5944 035)
in accordance with this agreement and with all of the following additional contract documents
which are incorporated into and made a part of this agreement:
a) The Standard Specifications, dated July 2002 and the Standard Specifications
dated May 2006 with Amendments issue date 11-30-10 were referenced; and
the Standard Plans, dated July 2002 and May 2006 of the State of California,
Department of Transportation.
b) A set of plans and cross sections when applicable) entitled:
LONOAK ROAD BRIDGE AT LEWIS CREEK,
STATE BRIDGE NO. 44C-0158) 44C-0179, COUNTY BR. NO. 402
FEDERAL-AID PROJECT NO. BRLOZB-5944 035)
PROJECT NO. 11-220565
c) The Special Provisions for the work.
d) The Notice to Bidders calling for bids.
e) The Payment and Performance bonds required.
LONOAK ROAD BRIDGE
CONTRACT NO. 11-220565
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��f)
Local Agency Bidder DBE information, Exhibit 15-G(2)
g) Certificate of Insurance.
h) The accepted bid/proposal including the following:
1) List of Subcontractors
2) Equal Employment Opportunity Certification
3) Public Contract Code
Section 10285.1 Statement
Section 10162 Questionnaire
Section 10232 Statement
4) Non-Collusion Affidavit
5) Debarment and Suspension Certification
6) Non-Lobbying Certification for Federal Aid Contracts
7) Disclosure of Lobbying Activities
8) Statement Concerning Employment of Undocumented Aliens
9) Contractor's Certificate as to Worker's Compensation
10) List of Satisfied Public Agencies
11) Bidder's Bond
12) Bidder's List
13) Local Agency Bidder UDBE Commitment, Exhibit 15-G(1)
14) UDBE Information Good Faith Efforts, Exhibit 15-H
All contract documents are intended to cooperate, so that any work called for in one and
not mentioned in another is to be executed the same as if mentioned in all. However, should
there be any conflict between the terms of this instrument and the Contractor's bid or proposal,
then this instrument shall control.
2. WORKERS' COMPENSATION
In accordance with the provisions of Section 3700 of the Labor Code, the Contractor
and every Subcontractor will be required to secure the payment of compensation to his
employees.
3. CONTRACT PRICE
The County shall pay the Contractor the following prices for the performance of this
contract:
LONOAK ROAD BRIDGE
AT LEWIS CREEK
COUNTY BRIDGE NO. 402, STATE BRIDGE NO.44C-0158
PROJECT NO. 11-220565
STATE PROJECT NO. EA 05-927094L
FEDERAL AID PROJECT NO. BRLOZB-5944 035)
ITEM UNIT OF ESTIMATE UNIT PRICE ITEM TOTAL
NO ITEM CODE ITEM DESCRIPTION MEASURE QUANTITY In Figures) In Figures)
1 066072 Maintain Detour LS 1 $5,000.00 $5,000.00
LONOAK ROAD BRIDGE 2
CONTRACT NO. 11-220565
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��ITEM ITEM CODE ITEM DESCRIPTION UNIT OF ESTIMATE UNIT PRICE ITEM TOTAL
NO MEASURE QUANTITY In Figures) In Figures)
2 066105 Resident Engineer's Office LS 1 $35,000.00 $35,000.00
Project Schedule
3 070010 Critical Path Method) LS 1 $5,000.00 $5,000.00
Temporary Fence
4 071302 Type BW) m 200 $25.00 $5,000.00
Temporary Fence
5 071325 Type ESA) m 75 $20.00 $1,500.00
6 073031 900 mm Temporary Culvert m 100 $100.00 $10,000.00
900 mm Temporary
7 073031A Flared End Section EA 8 $400.00 $3,200.00
Prepare Storm Water Pollution
8 074019 Prevention Proram S) LS 1 $1,200.00 $1,200.00
9 074020 Water Pollution Control LS 1 $10,000.00 $10,000.00
10 120090 Construction Area Signs LS 1 $3,000.00 $3,000.00
11 120100 Traffic Control System LS 1 $12,000.00 $12,000.00
12 129000 Temporary Railing Type K) m 50 $150.00 $7,500.00
13 129100 Temporary Crash Cushion
Module EA 22 $350.00 $7,700.00
14 150605 Remove Fence m 325 $8.00 $2,600.00
Install Salvaged) Gate with
15 151554 Posts EA 3 $1,4 00.00 $4,200.00
16 152386 Relocate Roadside
Sign One Post EA 2 $250.00 $500.00
17 152423 Adjust Monument to Grade EA 2 $600.00 $1,200.00
18 153103 Cold Plane AC Pavement
60 mm) m2 15 $250.00 $3,750.00
19 157550 Bridge Removal LS 1 $45,000.00 $45,000.00
20 160101 Clearing and Grubbing LS 1 $10,000.00 $10,000.00
21 170101 Develop Water Supply LS 1 $10,000.00 $10,000.00
22 190101 Roadway Excavation F) m3 850 $25.00 $21,250.00
23 190136 Roadway Excavation
Detour) F) m3 315 $85.00 $26,775.00
24 192003 Structure Excavation m3 207
Bridge) F) $50.00 $10,350.00
25 192020 Structure Excavation
Type D) F) m3 7 $120.00 $840.00
Structure Backfill
26 193003 Bridge) F) m3 115 $125.00 $14,375.00
27 198001 Import Borrow Detour) m3 440 $85.00 $37,400.00
LONOAK ROAD BRIDGE 3
CONTRACT NO. 11-220565
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��ITEM ITEM CODE ITEM DESCRIPTION UNIT OF ESTIMATE UNIT PRICE ITEM TOTAL
NO MEASURE QUANTITY In Figures) In Figures)
28 203016A Erosion Control
Type D-Seed Mix #1) S) m2 700 $3.00 $2,100.00
29 203016B Erosion Control
Type D-Seed Mix #2) S) m2 3,300 $3.00 $9,900.00
30 208252A 38 mm Plastic Pipe
PR 200) Supply Line) m 30 $120.00 $3,6 00.00
31 208751A 102 mm Galvanized Steel
Pipe Conduit m 15 $150.00 $2,250.00
32 220101 Finish Roadway
LS
1
$5,000.00
$5,000.00
33 260200A Detour Baserock
m3
460
$85.00
$39,100.00
34 260201 Aggregate Base Class 2)
M3
910
$70.00
$63,700.00
35 390102 Hot Mix Asphalt Type A)
to
610
$140.00
$85,400.00
36 393001 Pavement Reinforcing
Fabric m2 13 $25.00 $325.00
37 490663 1.5 m Cast-In-Drilled Hole
Concrete Piling S) m 30 $4,900.00 $147,000.00
38 490696 Furnish Piling Class
900) P) m 360 $165.00 $59,400.00
39 490697 Drive Pile Class 900)
EA
24
$2,200.00
$52,800.00
40 500001 Prestressing Cast-In-Place
Concrete S) LS 1 $25,000.00 $25,000.00
41 510051 Structural Concrete,
Bridge Footing m3 26 $430.00 $11,180.00
42 510053 Structural Concrete,
Bridge m3 280 $1,167.00 $326,760.00
43 519129A Joint Seal Assembly
Type B MR=50 mm) m 21 $250.00 $5,250.00
44 520102 Bar Reinforcing Steel
Bridge) P)(S) kg 63,000 $1.80 $113,400.00
45 566011 Roadside Sign-One Post
EA
8
$400.00
$3,200.00
46 721007 RSP 220 kg 1/4 Ton)
Method B) m3 125 $93.00 $11,625.00
47 729010 Rock Slope Protection
Fabric m2 250 $2.00 $500.00
48 731507 Minor Concrete
Gutter Depression) m3 1.6 $2,200.00 $3,520.00
49 750501 Miscellaneous Metal
Bridge) kg 66 $20.00 $1,320.00
50 800002 Fence Type BW, Wood
Post) m 270 $33.00 $8,910.00
51 800701 Reconstruct Pipe Fence
m
20
$330.00
$6,600.00
52 810110 Survey Monument EA 2 $1,400.00 $2,800.00
53 820118 Guard Railing Delineator EA 4 $140.00 $560.00
LONOAK ROAD BRIDGE 4
CONTRACT NO. 11-220565
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��ITEM
ITEM CODE
ITEM DESCRIPTION UNIT OF ESTIMATE UNIT PRICE ITEM TOTAL
NO MEASURE QUANTITY In Figures) In Figures)
54 820152 Object Marker
Type L-2 CA) EA 4 $130.00 $520.00
55 832003 Metal Beam Guard Railing
Wood Post) S) m 31 $75.00 $2,325.00
56 839565 Terminal System
Type SRT) S) EA 4 $2,400.00 $9,600.00
57 839720 Concrete Barrier Type 732)
m
112
$340.00
$38,080.00
58 840561 100 nun Thermoplastic
Traffic Stripe S) m 1,414 $2.00 $2,828.00
59 840656 Paint Traffic Stripe 2-Coat)
m
186
$4.00
$744.00
60 850111 Pavement Marker
Retroreflective) S) EA 110 $6.00 $660.00
61 860791A 4) 102 mm Direct Buried
Utility Conduit at&t) m 50 $85.00 $4,250.00
62 860792A 102 mm Utility Conduit in
bridge at&t) m 47 $100.00 $4,700.00
63 994629 Relocate Building Barn) LS 1
$1,000.00
$1,000.00
64 999990 Mobilization 10%) LS 1 $149,752.00 $149,752.00
P) Denotes Partial Pay Item
F) Denotes Final Pay Item TOTAL BID $1,499,999.00
S) Denotes Specialty Item
LONOAK ROAD BRIDGE 5
CONTRACT NO. 11-220565
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��IN WITNESS WHEREOF, the parties hereto have executed this Agreement as of the
dates appearing below their respective signatures.
CONTRACTOR:
MCM CONSTRUCTION, INC.
COUNTY OF MONTEREY:
By:
Name: Yazdan T. Emrani, P.E.
Title: Director of Public Works
Date: n e
APPROVE AS TO FORM
By:
Name:
Title:
Date:
Cynthia L. Hasson
APPROVE AS TO INDEMNITY/
R RIiJAGE
COUNTY OF M ONTERwEY
By: APPROVED S TO IN4DEMN
Name:1N�jiN1NGUAGE
Deputy County Counsel Title: Risk Mana
S d 1 1/ Date: Efate:
LONOAK ROAD BRIDGE 6
CONTRACT NO. 11 220565
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��COUNTY OF MONTEREY
PAYMENT BOND
Civil Code Section 3249)
BOND #105471528
Premium: Incl. in
Performance Bond
WHEREAS, the County of Monterey has awarded to Principal, as Contractor, a
contract for the following project:
LONOAK ROAD BRIDGE
AT LEWIS CREEK
COUNTY BRIDGE NO. 402, STATE BRIDGE NO.44C-0158
PROJECT NO. 11-220565
STATE PROJECT NO. EA 05-927094L
FEDERAL AID PROJECT NO. BRLOZB-5944 035)
AND WHEREAS, Principal, as Contractor, is required to furnish a bond in connection
with said contract, to secure the payment of claims of laborers, mechanics, materialmen, and
other persons furnishing labor and materials on the project, as provided by law.
NOW, THEREFORE, we M.C.M. Construction, Inc. as
Principal, and Travelers Casualty and Surety Company of America
as Surety, are held and firmly
bound unto the County of Monterey, a political subdivision of the State of California hereinafter
called County", and to the persons named in California Civil Code section 3181 in the penal
One Million Four Hundred Ninety Nine Thousand Nine Hundred for the
sum or Ninety Nine & 00/100a--=(81.499.999.00)
payment of which sum in lawful money of the United States, well and truly to be made, we bind
ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally,
firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT:
If the Principal, or any of Principal's heirs, executors, administrators, successors,
assigns, or Subcontractors, 1) fails to pay in full all of the persons named in Civil Code Section
3181 with respect to any labor or materials furnished by said persons on the project described
above, or 2) fails to pay in full all amounts due under the California Unemployment Insurance
Code with respect to work or labor performed on the project described above, or 3) fails to pay
for any amounts required to be deducted, withheld, and paid over to the Employment
Development Department from the wages of employees of the Principal and Subcontractors
pursuant to Unemployment Insurance Code section 13020 with respect to such work and labor,
then the Surety shall pay for the same.
Surety hereby stipulates and agrees that no change, extension of time, alteration or
addition to the terms of the contract on the call for bids, or to the work to be performed there
under, or the specifications accompanying the same, shall in any way affect its obligation under
this bond, and it does hereby waive notice of any such change, extension of time, alteration or
addition to the terms of said contract or the call for bids, or to the work, or to the specifications.
LONOAK ROAD BRIDGE
CONTRACT NO. 11-220565
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��If suit is brought upon this bond by the County and judgment is recovered, the Surety
shall pay all litigation expenses incurred by the County in such suit, including attorney's fees,
court costs, expert witness fees and investigation expenses.
This bond inures to the benefit of any of the persons named in Civil Code section 3181,
and such persons or their assigns shall have a right of action in any suit brought upon this bond,
subject to any limitations set forth in Civil Code sections 3247 et seq. Civil Code, Division 3,
Part 4, Title 15, Chapter 7: Payment Bond for Public Works).
IN WITNESS WHERE OF the above-bounden parties have executed this instrument
under their several seals this 27th day of April 20 11 the name and corporate
seal of each corporate party being hereto affixed and these presents duly signed by its
undersigned representative, pursuant to authority of its governing body.
Corporate Seal)
Corporate Seal)
M.C.M. Construction, Inc.
Surety
Name and Title EDMUNDO A. PUCHI, TREASURER
Travelers Casualty and Surety Company of America
Attorney-in-Fact
Attach notary acknowledgment for all signatures and attorney-in-fact certificate for signature by surety's
representative)
LONOAK ROAD BRIDGE 2
CONTRACTNO, 11-220565
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em� �ACKNOWLEDGMENT
State of California
County of Santa Clara
On April 27, 2011 before me, Erin Bautista, Notary Public
insert name and title of the officer)
personally appeared Jean L. Neu
who proved to me on the basis of satisfactory evidence to be the person() whose name() is/aix
subscribed to the within instrument and acknowledged to me that kadsheAtmy executed the same in
its/her/1 i'F-authorized capacityb and that by kWher/kt@k signature(;e) on the instrument the
person(), or the entity upon behalf of which the person() acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal.
Signature
Seal)
ERIN BAUTISTA
Commission # 1884542 Z
Notary Public California
D
Z Santa Clara County
My Comm. Expires Apr 25, 2014
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em�
�TRAVELERS
WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
POWER OF ATTORNEY
Farmington Casualty Company St. Paul Mercury Insurance Company
Fidelity and Guaranty Insurance Company Travelers Casualty and Surety Company
Fidelity and Guaranty Insurance Underwriters, Inc. Travelers Casualty and Surety Company of America
St. Paul Fire and Marine Insurance Company United States Fidelity and Guaranty Company
St. Paul Guardian Insurance Company
Attorney-In Fact No. 223488
Certificate No. V lJ Y 57 s.,! 1 5
KNOW ALL MEN BY THESE PRESENTS: That St. Paul Fire and Marine Insurance Company, St. Paul Guardian Insurance Company and St. Paul Mercury Insurance
Company are corporations duly organized under the laws of the State of Minnesota, that Farmington Casualty Company, Travelers Casualty and Surety Company, and
Travelers Casualty and Surety Company of America are corporations duly organized under the laws of the State of Connecticut, that United States Fidelity and Guaranty
Company is a corporation duly organized under the laws of the State of Maryland, that Fidelity and Guaranty Insurance Company is a corporation duly organized under
the laws of the State of Iowa, and that Fidelity and Guaranty Insurance Underwriters, Inc., is a corporation duly organized under the laws of the State of Wisconsin
herein collectively called the Companies"), and that the Companies do hereby make, constitute and appoint
Bryan D. Martin, Bradley N. Wright, Jean L. Neu, Erin Bautista, and Frances Murphy
of the City of San Jose State of California their true and lawful Attomey(s)-in-Fact,
each in their separate capacity if more than one is named above, to sign, execute, seal and acknowledge any and all bonds, recognizances, conditional undertakings and
other writings obligatory in the nature thereof on behalf of the Companies in their-business of guaranteeing the fidelity of persons, guaranteeing the performance of
contracts and executing or guaranteeing bonds and undertakings required or permitted in any actions or-proceedings allowed by law.
1 1 th
IN WITNESS HEREOF, the CompaLIIJJ pjep have caused this instrument to be signed and their corporate seals to be hereto affixed, this
l
day of April
Farmington Casualty Company
Fidelity and Guaranty Insurance Company
Fidelity and Guaranty Insurance Underwriters, Inc.
St. Paul Fire and Marine Insurance Company
St. Paul Guardian Insurance Company
State of Connecticut
City of Hartford ss.
By:
St. Paul Mercury Insurance Company
Travelers Casualty and Surety Company
Travelers Casualty and Surety Company of America
United States Fidelity and Guaranty Company
11th April 2011
On this the day of before me personally appeared George W. Thompson, who acknowledged
himself to be the Senior Vice President of Farmington Casualty Company, Fidelity and Guaranty Insurance Company, Fidelity and Guaranty Insurance Underwriters,
Inc., St. Paul Fire and Marine Insurance Company, St. Paul Guardian Insurance Company, St. Paul Mercury Insurance Company, Travelers Casualty and Surety
Company, Travelers Casualty and Surety Company of America, and United States Fidelity and Guaranty Company, and that he, as such, being authorized so to do,
executed the foregoing instrument for the purposes therein contained by signing on behalf of the corporations by himself as a duly authorized officer.
In Witness Whereof, I hereunto set my hand and official seal.
My Commission expires the 30th day of June, 2011.
58440-4-09 Printed in U.S.A.
Marie C. Tetreault, Notary Public
WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em�
�WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of Farmington Casualty Company, Fidelity
and Guaranty Insurance Company, Fidelity and Guaranty Insurance Underwriters, Inc., St. Paul Fire and Marine Insurance Company, St. Paul Guardian Insurance
Company, St. Paul Mercury Insurance Company, Travelers Casualty and Surety Company, Travelers Casualty and Surety Company of America, and United States
Fidelity and Guaranty Company, which resolutions are now in full force and effect, reading as follows:
RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President, any Vice President, any Second Vice
President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint Attorneys-in-Fact and Agents to act for and on behalf
of the Company and may give such appointee such authority as his or her certificate of authority may prescribe to sign with the Company's name and seal with the
Company's seal bonds, recognizances, contracts of indemnity, and other writings obligatory in the nature of a bond, recognizance, or conditional undertaking, and any
of said officers or the Board of Directors at any time may remove any such appointee and revoke the power given him or her; and it is
FURTHER RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice President may
delegate all or any part of the foregoing authority to one or more officers or employees of this Company, provided that each such delegation is in writing and a copy
thereof is filed in the office of the Secretary; and it is
FURTHER RESOLVED, that any bond, recognizance, contract of indemnity, or writing obligatory in the nature of a bond, recognizance, or conditional undertaking
shall be valid and binding upon the Company when a) signed by the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice
President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary and duly attested and sealed with the
Company's seal by a Secretary or Assistant Secretary; or b) duly executed under seal, if required) by one or more Attorneys-in-Fact and Agents pursuant to the power
prescribed in his or her certificate or their certificates of authority or by one or more Company officers pursuant to a written delegation of authority; and it is
FURTHER RESOLVED, that the signature of each of the following officers: President, any Executive Vice President, any Senior Vice President, any Vice President,
any Assistant Vice President, any Secretary, any Assistant Secretary, and the seal of the Company may be affixed by facsimile to any Power of Attorney or to any
certificate relating thereto appointing Resident Vice Presidents, Resident Assistant Secretaries or Attorneys-in-Fact for purposes only of executing and attesting bonds
and undertakings and other writings obligatory in the nature thereof, and any such Power of Attorney or certificate bearing such facsimile signature or facsimile seal
shall be valid and binding upon the Company and any such power so executed and certified by such facsimile signature and facsimile seal shall be valid and binding on
the Company in the future with respect to any bond or understanding to which it is attached.
1, Kori M. Johanson, the undersigned, Assistant Secretary, of Farmington Casualty Company, Fidelity and Guaranty Insurance Company, Fidelity and Guaranty Insurance
Underwriters, Inc., St. Paul Fire and Marine Insurance Company, St. Paul Guardian Insurance Company, St. Paul Mercury Insurance Company, Travelers Casualty and
Surety Company, Travelers Casualty and Surety Company of America, and United'States Fidelity and Guaranty Company do hereby certify that the above and foregoing
is a true and correct copy of the Power of Attorney executed by said Compnies which is in full force and effect and has not been revoked.
IN TESTIMONY WHEREOF, I have hereunto set my hand and affixed the seals of saidFCompanies this 2 7th day of April 2011
j/~OPPONq)f'~H /`OORPONgrf: jn:
cut tml tf; n~
t? SEAL%bn: J. i~t
Kori M. Johans Assistant Secretary
To verify the authenticity of this Power of Attorney, call 1-800-421-3880 or contact us at www.travelersbond.com. Please refer to the Attorney-In-Fact number, the
above-named individuals and the details of the bond to which the power is attached.
WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em�
�CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT
State of California
County of Sacramento
on April 28, 2011 before me, Christine Golden, Notary Public
Date
personally appeared Edmundo A. Puchi
Here Insert Name and Title of the Officer
Name(s) of Signer(s)
who proved to me on the basis of satisfactory evidence to
be the person(s) whose name(s) isIac subscribed to the
within instrument and acknowledged to me that
her/sheAhey executed the same in his/horltheir authorized
capacity(ies), and that by his/her/their signature(s)-on the
instrument the person(s); or the entity upon behalf of
which the persons) acted, executed the instrument.
CHRISTINE GOLDEN
Commission # 1895518
Notary Public California
My Comm. Expires Al c 9 2014
Sacramento County
Place Notary Seal Above
I certify under PENALTY OF PERJURY under the laws
of the State of California that the foregoing paragraph is
true and correct.
Signatur
OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document
and could prevent fraudulent removal and reattachment of this form to another document.
Description of Attached Document
Title or Type of Document: Payment Bond
Document Date: April 27, 2011 Number of Pages: 2
Signer(s) Other Than Named Above: None
Capacity(ies) Claimed by Signer(s)
Signer's Name: Edmundo A. Puchi
Individual
V
Treasurer
Corporate Officer Title(s):
Partner Limited General
Attorney in Fact
Trustee
Guardian or Conservator
Other:
Signer Is Representing:
MCM Construction, Inc.
a
RIGI Ir1I IUMBPRINT
OF SIGNER
Top of thumb here
Signer's Name:
Individual
Corporate Officer Title(s):
Partner Limited General
Attorney in Fact
Trustee
Guardian or Conservator
Other:
Signer Is Representing:
RIGIIT TI IUMBPRINI'
OF SIGNER
Top of thumb here
02007 National Notary Association- 9350 De Solo Ave., P.O. Box 2402 Chatsworth, CA 91313-2402� www.NationaiNotaryorg Item 56907 Reorder: CallToll-Free 1.800.876-6827
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em�
�COUNTY OF MONTEREY
PERFORMANCE BOND
WHEREAS, the County of Monterey has awarded to Principal, M M. C M M. Construction, Inc.
as Contractor, a contract for the following project:
LONOAK ROAD BRIDGE
AT LEWIS CREEK
COUNTY BRIDGE NO. 402, STATE BRIDGE NO.44C-0158
PROJECT NO. 11-220565
STATE PROJECT NO. EA 05-927094L
FEDERAL AID PROJECT NO. BRLOZB-5944 035)
BOND #105471528
Premium: $6,750.00
WHEREAS, Principal, as Contractor, is required to furnish a bond in connection with said
contract, to secure the faithful performance of said contract.
NOW, THEREFORE, we M C M Construction, Inc. as Principal,
and Travelers Casualty and Surety Company of America
as Surety, are held and firmly
bound unto the County of Monterey, a political subdivision of the State of California hereinafter
called County"), in the anal sum of None Million & Four Hundred Ninety Nine ThousanioTNinet,Heundred
p /5-- csti 499.999.00) 1 I1]]
payment of which sum in lawful money of the United States, well and truly to be made, we bind
ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally,
firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT:
If the Principal, as Contractor, or Principal's heirs, executors, administrators, successors,
or assigns, 1) shall in all things stand to and abide by and well and truly keep and perform the
covenants, conditions, and agreements in said contract and any alteration thereof made as therein
provided, on Principal's part to be kept and performed, at the time and in the manner therein
specified and in all respects according to their true intent and meaning, and 2) shall defend,
indemnify and save harmless the County, the members of its board of supervisors, and its
officers, agents and employees as therein stipulated, then this obligation shall become null and
void; otherwise, it shall be and remain in full force and virtue.
Surety hereby stipulates and agrees that no change, extension of time, alteration, or addition
to the terms of the contract or the call for bids, or to the work to be performed thereunder, or the
specifications accompanying the same, shall in any way affect its obligation under this bond, and
it does hereby waive notice of any such change, extension of time, alteration or addition to the
terms of said contract or the call for bids, or to the work, or to the specifications.
Whenever the Principal, as Contractor, is in default, and is declared in default, under the
contract by the County of Monterey, the County of Monterey having performed its obligation
under the contract, Surety may promptly remedy the default, or shall promptly:
1) Complete the contract in accordance with its terms or conditions, or
LONOAK ROAD BRIDGE 3
CONTRACT NO. 11 220565
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��2) Obtain a bid or bids for submission to County of Monterey for completing the
contract in accordance with its terms or conditions, and upon determination by
County of Monterey and Surety of the lowest responsible and responsive bidder,
arrange for a contract between such bidder and County of Monterey, and make
available as work progresses even though there should be a default or a
succession of defaults under the contract or contracts of completion arranged
under this paragraph) sufficient funds to pay the cost of completion less the
balance of contract price.
If suit is brought upon this bond by the County and judgment is recovered, the Surety shall
pay all litigation expenses incurred by the County in such suit, including attorney's fees, court
costs, expert witness fees and investigation expenses.
IN WITNESS WHEREOF, the above-bounden parties have executed this instrument under
their several seals this 27th day of Aril 20 11 the name and
corporate seal of each corporate party being hereto affixed and these presents duly signed by its
undersigned representative, pursuant to authority of its governing body.
Corporate Seal)
Corporate Seal)
M.C.M. Construction, Inc.
Name and Title EDMUNDO A. PUCHI, TREASURER
Surety
Travelers Casualty and Surety Company of America
Attorney-in-Fact
Attach notary acknowledgment for all signatures and attorney-in-fact certificate for signature by surety's
representative)
LONOAK ROAD BRIDGE 4
CONTRACT NO. 11-220565
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��ACKNOWLEDGMENT
State of California
County of Santa Clara
April 27, 2011 before me, Erin Bautista, Notary Public
insert name and title of the officer)
personally appeared Jean L. Neu
who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/arx
subscribed to the within instrument and acknowledged to me that iWshc/lbe~z executed the same in
iais/her/ft authorized capacity(e,t, and that by i /her/wit signature() on the instrument the
person(, or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing
paragraph is true and correct.
WITNESS my hand and official seal.
Signature
Seal)
ERIN BAUTISTA I
Commission # 1884542
Z W Notary Public California D
Z Santa Clara County
My Comm. Expires Apr 25, 2014
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
TRAVELERS
POWER OF ATTORNEY
Farmington Casualty Company St. Paul Mercury Insurance Company
Fidelity and Guaranty Insurance Company Travelers Casualty and Surety Company
Fidelity and Guaranty Insurance Underwriters, Inc. Travelers Casualty and Surety Company of America
St. Paul Fire and Marine Insurance Company United States Fidelity and Guaranty Company
St. Paul Guardian Insurance Company
Attorney-In Fact No. 223488 Certificate No. 0 0 4 153 7 5 14
KNOW ALL MEN BY THESE PRESENTS: That St. Paul Fire and Marine Insurance Company, St. Paul Guardian Insurance Company and St. Paul Mercury Insurance
Company are corporations duly organized under the laws of the State of Minnesota, that Farmington Casualty Company, Travelers Casualty and Surety Company, and
Travelers Casualty and Surety Company of America are corporations duly organized under the laws of the State of Connecticut, that United States Fidelity and Guaranty
Company is a corporation duly organized under the laws of the State of Maryland, that Fidelity and Guaranty Insurance Company is a corporation duly organized under
the laws of the State of Iowa, and that Fidelity and Guaranty Insurance Underwriters, Inc., is a corporation duly organized under the laws of the State of Wisconsin
herein collectively called the Companies"), and that the Companies do hereby make, constitute and appoint
Bryan D. Martin, Bradley N. Wright, Jean L. Neu, Erin Bautista, and Frances Murphy
of the City of San Jose State of California their true and lawful Attorney(s)-in-Fact,
each in their separate capacity if more than one is named above, to sign, execute, seal and acknowledge any and all bonds, recognizances, conditional undertakings and
other writings obligatory in the nature thereof on behalf of the Companies in their business of guaranteeing the fidelity of persons, guaranteeing the performance of
contracts and executing or guaranteeing bonds and undertakings required or permitted in any'actions or proceedings allowed by law.
11th
IN WITNESS WHEREOF, the Companies have caused this instrument to be signed and their corporate seals to be hereto affixed, this
day of April 2011
Farmington Casualty Company
Fidelity and Guaranty Insurance Company
Fidelity and Guaranty Insurance Underwriters, Inc.
St. Paul Fire and Marine Insurance Company
St. Paul Guardian Insurance Company
State of Connecticut
City of Hartford ss.
By:
St. Paul Mercury Insurance Company
Travelers Casualty and Surety Company
Travelers Casualty and Surety Company of America
United States Fidelity and Guaranty Company
11th April 2011
On this the day of before me personally appeared George W. Thompson, who acknowledged
himself to be the Senior Vice President of Farmington Casualty Company, Fidelity and Guaranty Insurance Company, Fidelity and Guaranty Insurance Underwriters,
Inc., St. Paul Fire and Marine Insurance Company, St. Paul Guardian Insurance Company, St. Paul Mercury Insurance Company, Travelers Casualty and Surety
Company, Travelers Casualty and Surety Company of America, and United States Fidelity and Guaranty Company, and that he, as such, being authorized so to do,
executed the foregoing instrument for the purposes therein contained by signing on behalf of the corporations by himself as a duly authorized officer.
In Witness Whereof, I hereunto set my hand and official seal.
My Commission expires the 30th day of June, 2011.
58440-4-09 Printed in U.S.A.
can C
Marie C. Tetreault, Notary Public
WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of Farmington Casualty Company, Fidelity
and Guaranty Insurance Company, Fidelity and Guaranty Insurance Underwriters, Inc., St. Paul Fire and Marine Insurance Company, St. Paul Guardian Insurance
Company, St. Paul Mercury Insurance Company, Travelers Casualty and Surety Company, Travelers Casualty and Surety Company of America, and United States
Fidelity and Guaranty Company, which resolutions are now in full force and effect, reading as follows:
RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President, any Vice President, any Second Vice
President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint Attorneys-in-Fact and Agents to act for and on behalf
of the Company and may give such appointee such authority as his or her certificate of authority may prescribe to sign with the Company's name and seal with the
Company's seal bonds, recognizances, contracts of indemnity, and other writings obligatory in the nature of a bond, recognizance, or conditional undertaking, and any
of said officers or the Board of Directors at any time may remove any such appointee and revoke the power given him or her; and it is
FURTHER RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice President may
delegate all or any part of the foregoing authority to one or more officers or employees of this Company, provided that each such delegation is in writing and a copy
thereof is filed in the office of the Secretary; and it is
FURTHER RESOLVED, that any bond, recognizance, contract of indemnity, or writing obligatory in the nature of % bond, recognizance, or conditional undertaking
shall be valid and binding upon the Company when a) signed by the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice
President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary and duly attested and sealed with the
Company's seal by a Secretary or Assistant Secretary; or b) duly executed under seal, if required) by one or more Attorneys-in-Fact and Agents pursuant to the power
prescribed in his or her certificate or their certificates of authority or by one or more Company officers pursuant to a written delegation of authority; and it is
FURTHER RESOLVED, that the signature of each of the following officers: President, any Executive Vice President, any Senior Vice President, any Vice President,
any Assistant Vice President, any Secretary, any Assistant Secretary, and the seal of the Company may be affixed by facsimile to any Power of Attorney or to any
certificate relating thereto appointing Resident Vice Presidents, Resident Assistant Secretaries or Attorneys-in-Fact for purposes only of executing and attesting bonds
and undertakings and other writings obligatory in the nature thereof, and any such Power of Attorney or certificate bearing such facsimile signature or facsimile seal
shall be valid and binding upon the Company and any such power so executed and certified by such facsimile signature and facsimile seal shall be valid and binding on
the Company in the future with respect to any bond or understanding to which it is attached.
I, Kori M. Johanson, the undersigned, Assistant Secretary, of Farmington Casualty Company, Fidelity and Guaranty Insurance Company, Fidelity and Guaranty Insurance
Underwriters, Inc., St. Paul Fire and Marine Insurance Company, St. Paul Guardian Insurance Company, St. Paul Mercury Insurance Company, Travelers Casualty and
Surety Company, Travelers Casualty and Surety Company of America, and United'States Fidelity-and Guaranty Company do hereby certify that the above and foregoing
is a true and correct copy of the Power of Attorney executed by said Companieg,,which-is in full force and effect and has not been revoked.
IN TESTIMONY HEREOF, I have hereunto set my hand and affixed the-seals of said,. Companies this 2 7th
+coxroaatm
1951
day of April 2011
To verify the authenticity of this Power of Attorney, call 1-800-421-3880 or contact us at www.travelersbond.com. Please refer to the Attorney-In-Fact number, the
above-named individuals and the details of the bond to which the power is attached.
WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT
State of California
County of Sacramento
On April 28, 2011
Date
before me, Christine Golden, Notary Public
Here Insert Name and Title of the Officer
personally appeared Edmundo A. Puchi
CHRISTINE GOLDEN
Commission # 1895518
Notary Public California
Sacramento County
My Comm. Expires Aug 9, 2014
Name(s) of Signer(s)
who proved to me on the basis of satisfactory evidence to
be the person(s) whose name(s) is/ace-subscribed to the
within instrument and acknowledged to me that
he/she/t executed the same in his/hor/heir authorized
capacity{ies), and that by his/#her eir signature(s)-on the
instrument the person(s) or the entity upon behalf of
which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws
of the State of California that the foregoing paragraph is
true and correct.
WITNESS 1hand_arrd official se
Place Notary Seal Above
Signature
Signature o otary Public
OPTIONAL
Though the Information below is not required by law, it may prove valuable to persons relying on the document
and could prevent fraudulent removal and reattachment of this form to another document.
Description of Attached Document
Title or Type of Document: Performance Bond
Document Date: April 27, 2011
Signer(s) Other Than Named Above: None
Capacity(ies) Claimed by Signer(s)
Signer's Name: Edmundo A. Puchi
Individual
Corporate Officer Title(s): Treasurer
Partner Limited El General
Attorney In Fact
Trustee
Guardian or Conservator
Other:
Signer Is Representing:
MCM Construction, Inc.
RIGNt'111UMBPRINT
OF SIGNER
Top of thumb here
Number of Pages: 2
Signer's Name:
El Individual
Corporate Officer Title(s):
Partner Limited General
Attorney in Fact
Trustee
Guardian or Conservator
Other:
Signer Is Representing:
RIGIITTI-IUPIBPRINT
OF SIGNER
Top of thumb here
02007 National Notary Association 9350 De Soto Ave., P.O. Box 2402 Chatsworth, CA 91313-2402� www.NatlonalNoiaryorg Item 116907 Reorder: CaIIToll-Free 1-800.876-6827
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��AR CERTIFICATE OF LIABILITY INSURANCE rIXATE MWDDNYM
Pag@ 1 of 2 04/28/2011
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS
CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES
BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED
REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.
IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies)must be endorsed. If SUBROGATION IS WAIVED, subject to
the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the
certificate holder in lieu of such endorsement(s).
PRODUCER CONTACT
NAM
Willis Insurance Services of California, Inc. P
HONE
FAx
One Bush Street A/C Igo ExT).
877-945-7378
888-467-2378
AIC NO)
9th Floor E-MAIL C@rtlf cates�wili16 coin A S.
San Francisco, CA 94104
INSURER(S)AFFORDING COVERAGE NAIL #
INSURERA:Zurich American Insurance Company 16535-100
INSURED
Inc
MCM Co
struction
INSURERS: American Guarantee and Liability Insuranc
26247-100
n
P. 0. Box 620 INSURERC:Zurich American Insurance Company 19356-900
North Highlands, CA 95660
INSURERD:Great American Assurance Company
26344-001
INSURER E:
INSURER F:
COVERAGES
CERTIFICATE NUMBER: 15879070
REVISION NUMBER:See Remarks
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN. THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSR
LTJL TYPE OF INSURANCE DD' SUB POLICY NUMBER POLICY EFF POLICY EXP LIMRS
A GENERAL LIABILITY Y GL0475607600 3/1/2011 3/1/2012 EA
OCCURRENCE
H
CC $ 1,750,000
X COMMERCIAL GENERAL LIABILITY M
Aq
pp
FIR ISESOEa oocurenoe $ 100,000
CLAIMS-MADE OCCUR MED EXP Any one person) $ 5 0 0 0
X SIR:$250,000 per occ PERSONAL&ADVINJURY $ 1,750,000
X XCU GENERAL AGGREGATE $ 4,000,000
GEN'L AGGREGATE LIMIT APPLIES PER: PRODUCTS-COMP/OPAGG $ 4, 000 00,000
POLICY X PRO X LOC $
A AUTOMOBILE LIABILITY Y BAP475607500 /1/2011 3/1/2012 COMBINED SINGLE LIMIT
Ea accident)
$ 2,000,000
X ANY AUTO BODILYINJURY(Perperson) $
ALL OWNED
AUTOS SCHEDULED
AUTOS
BODILY INJURY(Peraccident)
$
HIRED AUTOS NON-OWNED
AUTOS PROPER DA AG
Per accident)
$
B X UMBRELLAUAB X OCCUR AUC475616100 3/1/2011 3/1/2012 EACH OCCURRENCE $ 5,000,000
EXCESS LIAB CLAIMS-MADE AGGREGATE $ 5 000 000
DED RETENTION $ $
C WORKERS COMPENSATION EWS475607800 3/1/2011 3/1/2012 X
AND EMPLOYERS' LIABILITY
Y
ANYPROPRIETOR/PARTNER/EXECUTIVE N/A E.L. EACH ACCIDENT $ 11000,000
OFFICER/MEMBER EXCLUDED?
Mandatory in NH)
E.L. DISEASE EA EMPLOYEE I
s 1,000,000
1f yes, describe under
DESCRIPTIONOFOPERATIONS below
E.L. DISEASE POLICY LIMIT
$ 1,000,000
D EXC2098802 3/1/2011 3/1/2012
Excess Liability $8,000,000. Each Occurrence
$8,000,000. Policy Aggregate
DESCRIPTION OF OPERATIONS I LOCATIONS /VEHICLES Attach Acord 101, Additonal Remarks Schedule, if more space Is required)
THIS VOIDS AND REPLACES PREVIOUSLY ISSUED CERTIFICATE DATED: 4/27/2011 WITH ID: 15875936
Re: MCM Job #347 Lonoak Road Bridge at Lewis Creek, King City, Monterey County
Excess Workers Compensation:
Excess of $500,000 Self-Insured Retention
The n Monterey, its officers. and employees Additional insureds as respects
CERTIFICATE HOLDER
CANCELLATION
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE
THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN
ACCORDANCE WITH THE POLICY PROVISIONS.
County of Monterey AUTHORIZED REPRESENTATIVE
Contracts/Purchasing Department
168 W Alisal Street, 3rd Floor
CA 93901
Salinas
Coll:3342940 Tpl:1257137 Cert:15879070 1988-2010ACORDCORPORATION. All rights reserved.
ACORD 25 2010/05) The ACORD name and logo are registered marks of ACORD
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��AGENCY CUSTOMER ID: 401000
LOC#:
ACO OR
ADDITIONAL REMARKS SCHEDULE
Page_ of 2
AGENCY NAMED INSURED
MCM Construction, Inc.
Willis Insurance Services of California, Inc. P. 0. Box 620
POLICY NUMBER North Highlands, CA 9 5 6 6 0
See First Page
CARRIER NAIC CODE
See First Page EFFECTIVE DATE: See First Page
ADDITIONAL REMARKS
THIS ADDITIONAL REMARKS FORM IS A SCHEDULE TO ACORD FORM,
FORM NUMBER: 25 FORM TITLE: CERTIFICATE OF LIABILITY INSURANCE
General Liability and Automobile Liability if required by written contract but only as respects to
operations of the Named Insured.
ACORD 101 2008/01) Coll:3342940 Tpl:1257137 Cert:15879070 2008ACORD CORPORATION. All rights reserved.
The ACORD name and logo are registered marks of ACORD
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��Additional Insured Automatic Owners, Lessees Or
0
ZURICH
Contractors
Policy No. Exp. Date of Pol. Eff. Date of End. Agency No. Addl. Prem. Return Prem.
GL0475607600 3/1/2012 3/1/2011
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
Named Insured: MCM Construction, Inc.
Address including ZIP Code): P. 0. Box 620
North Highlands, CA 95660
This endorsement modifies insurance provided under the:
Commercial General Liability Coverage Part
A. Section II Who Is An Insured is amended to include as an insured any person or organization who you are re-
quired to add as an additional insured on this policy under a written contract or written agreement.
B. The insurance provided to the additional insured person or organization applies only to bodily injury", property
damage" or personal and advertising injury" covered under SECTION I Coverage A Bodily Injury And Prop-
erty Damage Liability and Section I Coverage B Personal And Advertising Injury Liability, but only with
respect to liability for bodily injury", property damage" or personal and advertising injury" caused, in whole or in
part, by:
1. Your acts or omissions; or
2. The acts or omissions of those acting on your behalf; and resulting directly from:
a. Your ongoing operations performed for the additional insured, which is the subject of the written contract or
written agreement; or
b. Your work" completed as included in the products-completed operations hazard", performed for the addi-
tional insured, which is the subject of the written contract or written agreement.
C. However, regardless of the provisions of paragraphs A. and B. above:
1. We will not extend any insurance coverage to any additional insured person or organization:
a.
b. That is not provided to you in this policy; or
That is any broader coverage than you are required to provide to the additional insured person or organiza-
tion in the written contract or written agreement; and
2. We will not provide Limits of Insurance to any additional insured person or organization that exceed the lower
of:
a. The Limits of Insurance provided to you in this policy; or
Includes copyrighted material of Insurance Services Office, Inc., with its permission. U-GL-1 175-B CW 3/2007)
Page 1 o172
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��b. The Limits of Insurance you are required to provide in the written contract or written agreement.
D. The insurance provided to the additional insured person or organization does not apply to:
Bodily injury", property damage" or personal and advertising injury" arising out of the rendering or failure to
render any professional architectural, engineering or surveying services including:
1. The preparing, approving or failing to prepare or approve maps, shop drawings, opinions, reports, surveys, field
orders, change orders or drawings and specifications; and
2. Supervisory, inspection, architectural or engineering activities.
E. The additional insured must see to it that:
1. We are notified as soon as practicable of an occurrence" or offense that may result in a claim;
2. We receive written notice of a claim or suit" as soon as practicable; and
3. A request for defense and indemnity of the claim or suit" will promptly be brought against any policy issued by
another insurer under which the additional insured may be an insured in any capacity. This provision does not
apply to insurance on which the additional insured is a Named Insured, if the written contract or written agree-
ment requires that this coverage be primary and non-contributory.
F. For the coverage provided by this endorsement:
1. The following paragraph is added to Paragraph 4.a. of the Other Insurance Condition of Section IV Com-
mercial General Liability Conditions:
This insurance is primary insurance as respects our coverage to the additional insured person or organization,
where the written contract or written agreement requires that this insurance be primary and non-contributory. In
that event, we will not seek contribution from any other insurance policy available to the additional insured on
which the additional insured person or organization is a Named Insured.
2. The following paragraph is added to Paragraph 4.b. of the Other Insurance Condition of Section IV Com-
mercial General Liability Conditions:
This insurance is excess over:
Any of the other insurance, whether primary, excess, contingent or on any other basis, available to an additional
insured, in which the additional insured on our policy is also covered as an additional insured by attachment of
an endorsement to another policy providing coverage for the same occurrence", claim or suit". This provision
does not apply to any policy in which the additional insured is a Named Insured on such other policy and where
our policy is required by written contract or written agreement to provide coverage to the additional insured on a
primary and non-contributory basis.
G. This endorsement does not apply to an additional insured which has been added to this policy by an endorsement
showing the additional insured in a Schedule of additional insureds, and which endorsement applies specifically to
that identified additional insured.
Any provisions in this Coverage Part not changed by the terms and conditions of this endorsement continue to apply as
written.
Includes copyrighted material of Insurance Services Office, Inc., with its permission. U-GL-1175 B CW 3/2007)
Page 2 of 2
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��POLICY NUMBER: BAP475607500
COMMERCIAL AUTO
CA 20 48 02 99
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
DESIGNATED INSURED
This endorsement modifies insurance provided under the following:
BUSINESS AUTO COVERAGE FORM
GARAGE COVERAGE FORM
MOTOR CARRIER COVERAGE FORM
TRUCKERS COVERAGE FORM
With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless
modified by this endorsement.
This endorsement identifies person(s) or organization(s) who are insureds" under the Who Is An Insured Provision
of the Coverage Form. This endorsement does not alter coverage provided in the Coverage Form.
This endorsement changes the policy effective on the inception date of the policy unless another date is indicated
below.
Endorsement Effective: Countersigned By:
Named Insured: MCM Construction, Inc.
Authorized Representative)
SCHEDULE
Name of Person(s) or Organization(s):
The County of Monterey, its officers, agents and employees
If no entry appears above, information required to complete this endorsement will be shown in the Declarations as
applicable to the endorsement.)
Each person or organization shown in the Schedule is an insured" for Liability Coverage, but only to the extent that
person or organization qualifies as an insured" under the Who Is An Insured Provision contained in Section 11 of
the Coverage Form.
CA 983 2-99)
CA 20 48 02 99 Copyright, Insurance Services Office, Inc., 1998 Page 1 of I
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��POLICY NUMBER: BAP 4756075-00
B. General Conditions
1. Bank uptcy
Bankruptcy or insolvency of the insured" or
the insured's" estate will not relieve us of any
obligations under this coverage form.
2. Concealment, Misrepresentation Or Fraud
This coverage form is void in any case of fraud
by you at any time as it relates to this coverage
form. It is also void if you or any other in-
sured", at any time, intentionally conceal or
misrepresent a material fact concerning:
a. This coverage form;
b. The covered auto";
c. Your interest in the covered auto"; or
d. A claim under this coverage form.
3. Liberalization
If we revise this coverage form to provide more
coverage without additional premium charge,
your policy will automatically provide the addi-
tional coverage as of the day the revision is ef-
fective in your state.
4. No Benefit To Bailee Physical Damage
Coverages
We will not recognize any assignment or grant
any coverage for the benefit of any person or
organization holding, storing or transporting
property for a fee regardless of any other pro-
vision of this coverage form.
5. Other Insurance
a. For any covered auto" you own, this cov-
erage form provides primary insurance. For
any covered auto" you don't own, the in-
surance provided by this coverage form is
excess over any other collectible insurance.
However, while a covered auto" which is a
trailer" is connected to another vehicle, the
Liability Coverage this coverage form pro-
vides for the trailer" is:
1) Excess while it is connected to a motor
vehicle you do not own.
2) Primary while it is connected to a cov-
ered auto" you own.
b. For Hired Auto Physical Damage Coverage,
any covered auto" you lease, hire, rent or
borrow is deemed to be a covered auto"
you own. However, any auto" that is
leased, hired, rented or borrowed with a
driver is not a covered auto".
c. Regardless of the provisions of Paragraph
a. above, this coverage form's Liability
Coverage is primary for any liability as-
sumed under an insured contract".
d. When this coverage form and any other
coverage form or policy covers on the same
basis, either excess or primary, we will pay
only our share. Our share is the proportion
that the Limit of Insurance of our coverage
form bears to the total of the limits of all the
coverage forms and policies covering on
the same basis.
6. Premium Audit
a. The estimated premium for this coverage
form is based on the exposures you told us
you would have when this policy began. We
will compute the final premium due when we
determine your actual exposures. The
estimated total premium will be credited
against the final premium due and the first
Named Insured will be billed for the bal-
ance, if any. The due date for the final pre-
mium or retrospective premium is the date
shown as the due date on the bill- If the es-
timated total premium exceeds the final
premium due, the first Named Insured will
get a refund.
b. If this policy is issued for more than one
year, the premium for this coverage form
will be computed annually based on our
rates or premiums in effect at the beginning
of each year of the policy.
7. Policy Period, Coverage Territory
Under this coverage form, we cover accidents"
and losses" occurring:
a. During the policy period shown in the Dec-
larations; and
b. Within the coverage territory.
The coverage territory is:
1) The United States of America;
2) The territories and possessions of the Unit-
ed States of America;
3) Puerto Rico;
4) Canada; and
5) Anywhere in the world if:
a) A covered auto" of the private passen-
ger type is leased, hired, rented or bor-
rowed without a driver for a period of 30
days or less; and
b) The insured's" responsibility to pay
damages is determined in a suit" on the
merits, in the United States of America,
the territories and possessions of the
United States of America, Puerto Rico or
Canada or in a settlement we agree to.
CA 00 0103 10 Insurance Services Office, Inc., 2009
Page 9 of 12 11
Insured Copy
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��WAIVER OF TRANSFER OF RIGHTS OF RECOVERY AGAINST OTHERS TO US
POLICY NO.
BAP 4756075-00
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
EFF. DATE OF POL.
3/1/2011
EXP- DATE OF POL.
3/1/2012
Named Insured MCM Construction, Inc.
Address including ZIP Code)
EFF. DATE OF END.
3/1/2011
AGENCY NO.
This endorsement modifies insurance provided by the following:
Business Auto Coverage Part
Truckers Coverage Part
Garage Coverage Part
SCHEDULE
Name of Person or Organization:
ADD'L. PREM.
RETURN PREM.
ALL PERSONS AND/OR ORGANIZATIONS THAT ARE REQUIRED BY WRITTEN
CONTRACT OR AGREEMENT WITH THE INSURED, EXECUTED PRIOR TO THE
ACCIDENT OR LOSS, THAT WAIVER OF SUBROGATION BE PROVIDED UNDER THIS
POLICY.
We waive any right of recovery we may have against the designated person or organization shown in the schedule because of
payments we make for injury or damage caused by an accident" or loss' resulting from the ownership, maintenance, or use of a
covered auto" for which a Waiver of Subrogation is required in conjunction with work performed by you for the designated
person or organization. The waiver applies only to the designated person or organization shown in the schedule.
Countersigned
Authorized Representative
U-CA-320-A CW) 4/92)
insured Copy
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
NOTICE OF CANCELLATION CERTIFICATE HOLDERS
SPECIFIED DAYS)
The person(s) or organization(s) listed or described in the Schedule below have requested that they
receive written notice of cancellation when this policy is cancelled by us. We will mail or deliver to the
Person(s) or Organization(s) listed or described in the Schedule a copy of the written notice of
cancellation that we sent to you. If possible, such copies of the notice will be mailed at least 60 days,
except for cancellation for non-payment of premium which will be mailed 10 days, prior to the effective
date of the cancellation, to the address or addresses of certificate holders as provided by your broker or
agent.
Schedule
Person(s) or Organization(s) including mailing address:
County of Monterey
Contracts/Purchasing Department
168 W Alisal Street, 3rd Floor
Salinas, CA 93901
This notification of cancellation of the policy is intended as a courtesy only. Our failure to provide such
notification to the person(s) or organization(s) shown in the Schedule will not extend any policy
cancellation date nor impact or negate any cancellation of the policy. This endorsement does not entitle
the person(s) or organization(s) listed or described in the Schedule above to any benefit, rights or
protection under this policy.
Any provision of this endorsement that is in conflict with a statute or rule is hereby amended to conform to
that statute or rule.
All other terms and conditions of this policy remain unchanged.
Endorsement Number:
Policy Number: BAP475607500
Named Insured: MCM Construction, Inc.
This endorsement is effective on the inception date of this Policy unless otherwise stated herein:
Endorsement Effective Date:
00 ML0087 00 11 10 Page 1 of 1
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em��THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
NOTICE OF CANCELLATION CERTIFICATE HOLDERS
SPECIFIED DAYS)
The person(s) or organization(s) listed or described in the Schedule below have requested that they
receive written notice of cancellation when this policy is cancelled by us. We will mail or deliver to the
Person(s) or Organization(s) listed or described in the Schedule a copy of the written notice of
cancellation that we sent to you. If possible, such copies of the notice will be mailed at least 60 days,
except for cancellation for non-payment of premium which will be mailed 10 days, prior to the effective
date of the cancellation, to the address or addresses of certificate holders as provided by your broker or
agent.
Schedule
Person(s) or Organization(s) including mailing address:
County of Monterey
Contracts/Purchasing Department
168 W Alisal Street, 3rd Floor
Salinas, CA 93901
This notification of cancellation of the policy is intended as a courtesy only. Our failure to provide such
notification to the person(s) or organization(s) shown in the Schedule will not extend any policy
cancellation date nor impact or negate any cancellation of the policy. This endorsement does not entitle
the person(s) or organization(s) listed or described in the Schedule above to any benefit, rights or
protection under this policy.
Any provision of this endorsement that is in conflict with a statute or rule is hereby amended to conform to
that statute or rule.
All other terms and conditions of this policy remain unchanged.
Endorsement Number:
Policy Number: GL0475607600
Named Insured: MCM Construction, Inc.
This endorsement is effective on the inception date of this Policy unless otherwise stated herein:
Endorsement Effective Date:
00 ML0087 00 11 10 Page 1 of 1
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012
EXECUTED AGREEMENT"�|Em�� NOTEXTPAGE
BIB]
40956-U01
EXECUTED-U02
AGREEMENT-U02
LI21329-U03
FO96183-U03
FO96184-U03
FO99828-U03
MG99866-U03
AS99892-U03
AS99899-U03
AI102934-U03
DO109659-U03
C5-U03
AGREEMENTS-U03
2/13/2012-U04
BOYDA-U04
16667-U05
2-U06
A.-U07
AWARD-U07
A-U07
CONTRACT-U07
TO-U07
MCM-U07
CONSTRUCTION,-U07
INC.,-U07
THE-U07
LOWEST-U07
RESPONSIBLE-U07
BASE-U07
BIDDER,-U07
THE-U07
LONOAK-U07
ROAD-U07
BRIDGE-U07
AT-U07
300-PUBLIC-U08
WORKS-U08
ESTRADA-U09
IRMA-U09
ESTRADAI-U10
6/6/2011-U011
LEWIS-U012
CREEK-U012
REPLACEMENT-U012
PROJECT,-U012
BRIDGE-U012
NO.-U012
402,-U012
FEDERAL-U012
AID-U012
PROJECT-U012
NO.-U012
BRLOZB-5944(035),-U012
PROJECT-U012
NO.-U012
11-220565;-U012
IN-U012
THE-U012
TOTAL-U012
AMOUNT-U012
OF-U012
$1,499,999;-U012
B.-U012
APPROVE-U012
THE-U012
PERFORMANCE-U012
PAYMENT-U012
BONDS-U012
EXECUTED-U012
PROVIDED-U012
BY-U012
MCM-U012
CONSTRUCTION,-U012
INC.;-U012
C.-U012
AUTHORIZE-U012
A-U012
CONTINGENCY,-U012
TO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
CONTRACT-U012
AMOUNT,-U012
TO-U012
PROVIDE-U012
FUNDING-U012
APPROVED-U012
CONTRACT-U012
CHANGE-U012
ORDERS;-U012
D.-U012
AUTHORIZE-U012
THE-U012
DIRECTOR-U012
OF-U012
PUBLIC-U012
WORKS-U012
TO-U012
EXECUTE-U012
THE-U012
CONTRACT-U012
SUBJECT-U012
TO-U012
THE-U012
TERMS-U012
OF-U012
THE-U012
PUBLIC-U012
CONTRACT-U012
CODE,-U012
APPROVE-U012
CHANGE-U012
ORDERS-U012
TO-U012
THE-U012
CONTRACT-U012
DO-U012
EXCEED-U012
TEN-U012
PERCENT-U012
10%)-U012
OF-U012
THE-U012
ORIGINAL-U012
CONTRACT-U012
AMOUNT-U012
DO-U012
SIGNIFICANTLY-U012
CHANGE-U012
THE-U012
SCOPE-U012
OF-U012
WORK.-U012