File #: WRAFIN 25-029    Name: Amend No. 4 GEI
Type: WRA FInance Item Status: Agenda Ready
File created: 2/28/2025 In control: Water Resources Agency Finance Committee
On agenda: 3/7/2025 Final action:
Title: Approve Amendment No.4 of the agreement for Professional Services with GEI Consultants, Inc., to extend the term length to June 30, 2027, for engineering design & project management services for storm damage repair design and implementation of the Nacimiento Dam Hydro-Plant’s South Access Road; and authorize the General Manager to execute the amendment. (Staff Presenting: Guillermo Alvarez)
Attachments: 1. Board Report, 2. Amendment No. 4, 3. Amendments Nos. 1 thru 3

Title

Approve Amendment No.4 of the agreement for Professional Services with GEI Consultants, Inc., to extend the term length to June 30, 2027, for engineering design & project management services for storm damage repair design and implementation of the Nacimiento Dam Hydro-Plant’s South Access Road; and authorize the General Manager to execute the amendment. (Staff Presenting: Guillermo Alvarez)                     

Report

RECOMMENDATION:

It is recommended that the Monterey County Water Resources Agency Finance Committee:

 

Recommend that the Board of Directors of the Monterey County Resources Agency approve Amendment No.4 of the agreement for Professional Services with GEI Consultants, Inc., to extend the term length to June 30, 2027, for engineering design & project management services for storm damage repair design and implementation of the Nacimiento Dam Hydro-Plant’s South Access Road; and authorize the General Manager to execute the amendment.

 

SUMMARY/DISCUSSION:

During the winter storms of January 2023, Nacimiento Dam suffered erosion damage at the Spillway’s Plunge Pool and at multiple locations along the Nacimiento Dam Hydro-Plant’s South Access Road at multiple locations. An Agreement for Professional Services with GEI Consultants Inc. to perform emergency repair and protection of the Nacimiento Dam spillway plunge pool banks, was approved by the Board of Directors on February 2, 2023, in an amount not to exceed $200,000.

 

Amendment No. 1 to the services agreement was approved by the Board of Directors on May 15, 2023, to increase the amount payable on contract $170,000, for total contract amount of $370,000. The Board of Directors approved Amendment No. 2 to the services agreement with GEI Inc., increased the amount payable on contract by $70,000, for a contract not-to-exceed amount of $440,000. The Board of Directors approved Amendment No.3 to the services agreement with GEI will increase the value of the contract by $156,000, and adjust the contract’s Fee Schedule, increasing the hourly labor rates according to the Direct Labor Rate schedule.

 

FEMA has authorized $1.1 mil for repair of damages at the South Access Road. The Agency intends to release the RFP for construction in May 2025. Construction of repairs is estimated at $450,000. The Agency will be reimbursed for all costs associated with design, construction management, and construction of the repairs per the FEMA authorization.

 

Amendment No. 4 of the agreement for Professional Services with GEI Consultants, Inc., will extend the term of the contract to June 30, 2027, allowing GEI to provide engineering services through completion of the planned repairs to theNacimiento Dam Hydro-Plant’s South Access Road.

 

OTHER AGENCY INVOLVEMENT:

FEMA (reimbursement and contracting requirements).

County of San Luis Obispo-Building and Planning (grading permit)

 

FINANCING:

Fund 116-Nacimiento (FEMA reimbursement authorized)

 

Prepared by:    Guillermo Alvarez, Water Resources Engineer (831) 279-6144

Approved by:  Ara Azhderian, General Manager, (831)755-4860

                                                     

Attachments:

1. Amendment No. 4

2. Amendment Nos. 1 thru 3