File #: 15-0390    Name: Quarterly New Juvenile Hall Project Status Report
Type: General Agenda Item Status: Agenda Ready
File created: 4/16/2015 In control: Budget Committee
On agenda: 4/29/2015 Final action:
Title: Receive a Quarterly Budget and Schedule Status Report on the New Juvenile Hall, Project 8811, for the period ending March 31, 2015
Sponsors: Public Works / RMA
Attachments: 1. board report, 2. Project Budget Sheet, 3. Project Milestone Schedule
Title
Receive a Quarterly Budget and Schedule Status Report on the New Juvenile Hall, Project 8811, for the period ending March 31, 2015
 
.Report
RECOMMENDATION:
It is recommended that the Budget Committee receive a Quarterly Budget and Schedule Status Report on the New Juvenile Hall, Project 8811, for the period ending March 31, 2015.
 
SUMMARY/DISCUSSION:
Key schedule components and budget status are summarized below.
 
Budget and Schedule:  The New Juvenile Hall, Project 8811, (Project) is on budget and on schedule.  Construction is anticipated to start in summer 2016.
 
State Milestones:  The project team has submitted Preliminary Plans (Design Development) to the Board of State and Community Corrections (BSCC) for approval by the State Public Works Board on June 12, 2015.
 
Design:  DLR Group has held multiple meetings with the Probation Department and the Resource Management Agency - Public Works (RMA - PW) to develop Preliminary Plans for each building composing the campus-style New Juvenile Hall.  DLR Group is presently on schedule, with 100 percent of the Preliminary Plan Phase complete. Overall, design is 35 percent complete.
 
CEQA Process:  Staff is proceeding with the California Environmental Quality Act (CEQA) process anticipating a Mitigated Negative Declaration (MND) to comply with CEQA requirements.  The MND is presently out for public review.  We anticipate the public hearing with Board of Supervisors to adopt the MND in June 2015.
 
Real Estate Due Diligence:  The County has submitted the Real Estate Due Diligence to the Department of General Services for review and comment.
 
OTHER AGENCY INVOLVEMENT:
RMA - PW and Probation continue to work jointly with the BSCC to meet all State requirements to maintain the conditional award by moving the project forward in design.
 
FINANCING:
Total estimated Project cost is $52,791,824, of which $17,791,824 was approved by the Board of Supervisors as the County's match.  To-date expenditures total $1,331,969, including current year expenditures estimated at $532,783.  The remaining County match balance of $16,459,855 is available in the General Fund Capital Project Assignment (Account 3127) for the design and construction phases of the Project.
 
Prepared by:  Donald D. Searle, Architectural Services Manager (831) 755-5061
 
Approved by:
 
__________________________________________
Robert K. Murdoch, P.E., Director of Public Works
 
___________________________________
Carl P. Holm, AICP, Acting RMA Director
 
Attachments: Project Budget; Project Milestone Schedule
 
cc: Manuel T. Gonzalez, Assistant CAO; Marcia Parsons, Chief Probation Officer