File #: 15-1006    Name: East West Wing Renovation Space Plans
Type: General Agenda Item Status: Passed
File created: 9/14/2015 In control: Board of Supervisors
On agenda: 9/29/2015 Final action: 9/29/2015
Title: Receive a presentation on the East-West Wing Renovation Project.
Sponsors: Public Works / RMA
Attachments: 1. Board Report, 2. East-West Wing Renovation Programming & Space Plans, 3. Completed Board Order

Title

Receive a presentation on the East-West Wing Renovation Project.

 

Report

RECOMMENDATION:

It is recommended that the Board of Supervisors receive a presentation on the East-West Wing Renovation Project.

 

SUMMARY:

Although the East-West Wing Renovation Project (Project) was a component of the overall Facilities Master Plan approved by the Board of Supervisors in August 2001, and construction documents were produced and finalized in 2006, the Project was not publicly bid.  Project funding was redirected and the Project was put on hold.  In October 2010, the remaining tenants of the East-West Wing Building (E/W) moved to their assigned locations in the North Wing of the Courthouse.  Since that time the E/W has remained vacant.  Funding issues and competing capital project priorities since 2009 prevented the Project from moving forward until now.

 

DISCUSSION:

On January 15, 2013, the Board of Supervisors approved the Fund 404 Financing Plan which included the Project.  In September 2013, the Budget and Capital Improvement Committees supported moving forward with securing architectural programming and pre-design services to assist with determining how future tenants could be accommodated in the building.  In 2014, architectural firm Wald, Ruhnke, and Dost (WRD) was hired to produce a design layout showing how the District Attorney, Law Library, Human Resources’ Learning & Development Center, and a Snack Shop could be accommodated in the E/W.  Concurrent efforts were also underway for acquisition of Schilling Place.  Once the decision to purchase Schilling Place was made, the Project was put on hold while the ramifications of the new acquisition were clarified.

 

On November 4, 2014, the Board of Supervisors approved funding to finance the Facility Utilization Program (FUP) for master planning Schilling Place, the E/W, and the Monterey County Government Center Administration Building.  FUP’s effort concluded that the Project is necessary for housing the District Attorney, and ultimately, removing the modular buildings from the Salinas Government Center campus.  With the Resource Management Agency as one of the major tenants moving to Schilling Place, FUP further established that the second floor of the Administration Building would be backfilled by the Public Defender and Human Resources Department, which includes the Learning & Development Center unit.  A modification was required to WRD’s June 2014 design layout for the E/W to be concurrent (consistent) with FUP’s master planning.  Tenants for the E/W include the District Attorney occupying all three floors in the West Wing and the second floor of the East Wing; a Snack Shop; Law Library; Grand Jury; auxiliary office for the Second District Supervisor; and some still unassigned space on the first floor of the East Wing.  Creating the District office opens space in the Administrative Building for District 5, which currently has no office space. 

 

The presentation (attached) provides proposed organizational diagrams, floor plans, and square-foot allocation per tenant relocating to the E/W.

 

On May 5, 2015, the Board of Supervisors supported the Project and granted the Auditor-Controller the authority to execute documents to facilitate the issuance of Certificates of Participation (COP) in the amount of $52 Million to include tenant improvements for this Project with a project cost of $36 Million and $16 Million in project costs for Schilling Place Tenant Improvements.  The difference between the building’s fair market appraised value of $12 Million and the required Project Total funded through the COP is an investment in the County’s historic landmark building.

 

In 2009, the E/W was placed on the National Register of Historic Places, which required that a Supplemental Environmental Impact Report (SEIR) be prepared.  On May 12, 2015, the Board of Supervisors certified the SEIR and on May 14, 2015, the required Notice of Determination was filed with the State.

 

The Project is scheduled to start in the first quarter of FY 2015-16, with completion anticipated in fall 2018. 

 

OTHER AGENCY INVOLVEMENT:

Resource Management Agency-Public Works (RMA-PW) continues to work closely with the Auditor-Controller, Board of Supervisors - District 2, County Administrative Office, District Attorney, the Office of the County Counsel, and Superior Court of California - Grand Jury Office to advance this project.  This report was presented to the Capital Improvement Committee and to the Budget Committee on August 19, 2015 and September 2, 2015, respectively.

 

FINANCING:

On July 7, 2015, the Board of Supervisors adopted a Capital Improvement Program Five Year Plan, which included the Project.  Per the financing plan, the Project is anticipated to be funded with the issuance of $16 Million in COP for Schilling Place Tenant Improvements and $36 Million in COP for this Project.  The exact amount of annual debt service obligation cannot be determined until final pricing and documents are executed in the first quarter of FY 2015-16.  Sufficient appropriations exist in the FY 2015-16 Adopted Budget for Fund 404-3000-8174-RMA015 for the anticipated costs to be incurred in FY15-16.

 

Prepared by: Don Searle, Architectural Services Manager, (831) 755-5061

 

Approved by:  Robert K. Murdoch, P.E., Director of Public Works

 

Approved by:  Carl P. Holm, AICP, RMA Director

 

Date:  September 21, 2015

 

Attachment:  East-West Wing Renovation Programming & Space Plans