Administrative hearing to consider construction of a 636-square-foot addition to an existing single-family dwelling and development within 750 feet of known archaeological resources
Project Location: 3215 Macomber Dr, Pebble Beach
Proposed CEQA action: Find that the project qualifies for a Class 1 Categorical Exemption pursuant to CEQA Guidelines section 15301, and that no exceptions pursuant to section 15300.2 apply
Body
RECOMMENDATIONS
It is recommended that the HCD Chief of Planning adopt a resolution to:
a. Find that the project qualifies for a Class 1 Categorical Exemption pursuant to CEQA Guidelines section 15301, and that no exceptions pursuant to section 15300.2 apply; and
b. Approve a Coastal Administrative Permit and Design Approval to allow construction of a 636-square-foot addition to an existing single-family dwelling and a Coastal Administrative Permit to allow development within 750 feet of known archaeological resources.
The attached draft resolution includes findings and evidence for consideration (Exhibit A). Staff recommends approval subject to 6 conditions of approval.
PROJECT INFORMATION
Agent: Amy Denney
Property Owner: Sergio Alvarez
APN: 008-162-015-000
Parcel Size: 2.93 acres
Zoning: LDR/B-8-D(CZ)
Plan Area: Del Monte Forest Land Use Plan
Flagged and Staked: Yes
Project Planner: Joseph Alamenda, Assistant Planner
alamedaj@countyofmontery.gov, (831)783-7079
SUMMARY
Staff is recommending approval of two Coastal Administrative Permits and a Design Approval subject to the findings and evidence in the attached Resolution (see Exhibit A), and subject to the conditions of approval attached to the Resolution. Please read these carefully and contact the planner if you have any questions. Unless otherwise noted in the conditions, the applicant will be required to satisfy all permit conditions prior to the issuance of a building/grading permits and/or commencement of the approved use.
On November 6, 2024, an administrative decision will be made. A public notice has been distributed for this project. The deadline for submittal of written comments in opposition to the project, its findings, or conditions, based on a substantive issue, is 5:00 p.m. on Tuesday, November 5, 2024. The permit will be administratively approved the following day if we do not receive any written comments by the deadline.You will receive a copy of your approved permit in the mail. We will notify you as soon as possible in the event that we receive correspondence in opposition to your project or if the application is referred to a public hearing.
Note: This project will be referred to the Monterey County Zoning Administrator if a public hearing is necessary. The decision on this project is appealable to Board of Supervisors and the California Coastal Commission.
OTHER AGENCY INVOLVEMENT
The following agencies have reviewed the project, have comments, and/or have recommended conditions:
HCD-Engineering Services
Environmental Health Bureau
HCD-Environmental Services
Pebble Beach Community Services District
Prepared by: Joseph Alameda, Assistant Planner, x7079
Reviewed and Approved by: Fionna Jensen, Senior Planner
The following attachments are on file with HCD:
Exhibit A - Draft Resolution including:
• Recommended Conditions of Approval
• Site Plans, Floor Plans & Elevations
• Colors and Materials
Exhibit B - Vicinity Map
cc: Front Counter Copy; Pebble Beach Community Services District; HCD-Environmental Services; HCD-Engineering Services; Environmental Health Bureau; Joseph Alameda, Projet Planner; Fionna Jensen, Senior Planner; Sergio Alvarez, Property Owners; Amy Denney, Agent; The Open Monterey Project; LandWatch (Executive Director); Lozeau Drury LLP; Christina McGinnis, Keep Big Sur Wild, Planning File PLN240122.