a. Review the presented funding strategies and select a preferred financing option for payment of $683,797 to be reimbursed by insurance, for emergency lighting repairs at the Monterey County Jail to Staples Construction Company under the Monterey County Public Works, Facilities, and Parks Job Order Contract, Job Order Number: JF02-21-14-J8552-01; and
b. Adopt a resolution authorizing the Auditor-Controller to make the necessary budget adjustments based upon preferred financing option for payment of $683,797 to be reimbursed by insurance, for payment of emergency lighting repairs at the Monterey County Jail to Staples Construction Company under the Monterey County Public Works, Facilities, and Parks Job Order Contract, Job Order Number: JF02-24-14-J8552-01 (4/5ths vote required).
Report
RECOMMENDATION:
a. Review the presented funding strategies and select a preferred financing option for payment of $683,797 to be reimbursed by insurance, for emergency lighting repairs at the Monterey County Jail to Staples Construction Company under the Monterey County Public Works, Facilities, and Parks Job Order Contract, Job Order Number: JF02-21-14-J8552-01; and
b. Adopt a resolution authorizing the Auditor-Controller to make the necessary budget adjustments based upon preferred financing option for payment of $683,797 to be reimbursed by insurance, for payment of emergency lighting repairs at the Monterey County Jail to Staples Construction Company under the Monterey County Public Works, Facilities, and Parks Job Order Contract, Job Order Number: JF02-24-14-J8552-01 (4/5ths vote required).
SUMMARY:
The Monterey County Sheriff’s Office (MCSO) is requesting an increase in appropriations to repair Jail’s emergency lighting system. MCSO went to the Budget Committee on August 26, 2026 and the Capital Improvement Committee on September 14, 2026.
DISCUSSION:
The Monterey County Sheriff’s Office operates the Monterey County Jail which has an average daily population of over 800 incarcerated persons. The Jail operates 24 hours a day, seven days a week. The Jail is strictly governed by California Code of Regulations Title 15 and Title 24 which require functional emergency lighting at all times.
On July 15, 2025, a catastrophic electrical event damaged portions of the jail's emergency lighting system. Due to this event, the county jail has been functioning without a large portion of its emergency lighting operational. Reliable emergency lighting is essential to maintaining the safety and security of Sheriff's Office personnel, contractors, visitors, and the incarcerated population. Failure of these systems during an emergency could significantly impair facility operations and increase the risk of injury to occupants and responders.
Replacement of the damaged emergency lighting components is necessary to restore system reliability, reduce operational risk, and ensure compliance with applicable detention facility safety standards. It is also imperative that the County maintain compliance with future inspections conducted by the California Board of State and Community Corrections (BSCC) and continue to meet obligations established under the Hernandez Settlement Agreement. Functional emergency lighting is a critical component of life-safety infrastructure and supports the County's ongoing commitment to providing a safe, secure, and constitutionally compliant detention environment.
Expedited completion of this project will support regulatory compliance, and help ensure the continued safety of staff, contractors, visitors, and the incarcerated population during power outages and other critical incidents.
Once the repairs have been completed, Risk Management can submit the project to the insurer for reimbursement under the open claim for this incident.
OTHER AGENCY INVOLVEMENT/COMMITTEE ACTIONS:
The Department of Public Works, Facilities & Parks supports this project. The Office of County Counsel has reviewed and advised on this Agreement as to legal form. The Auditor-Controller has reviewed and approved the Agreement as to fiscal provisions. This report was presented to the Budget Committee on August 26, 2026 and the Capital Improvement Committee on September 14, 2026.
FINANCING:
Option 1: The Sheriff’s Office fund the project using allocations from its FY 2026-2027 Adopted Budget. The Sheriff's Office budget will be reimbursed for the amount expended to complete this project once funds have been received from the insurance carrier. If the claim has not been paid by the insurer by March 31, 2027, the Sheriff’s Office can return to the Board to seek augmentation to its FY 2026-2027 Adopted Budget, for the amount expended to complete this project.
Option 2: The project be funded by the Building Improvement and Replacement Fund 478. The Building Improvement and Replacement Fund 478 will be reimbursed once funds have been received from the insurance carrier.
Option 3: The project be funded by contingencies. Contingencies will be reimbursed once funds have been received from the insurance carrier.
Option 4: The board to authorize the project but direct the project to be absorbed within the Sheriff’s Office FY27 budget at this time
The Sheriff’s Office is requesting the Board of Supervisors increase appropriations in the Adopted Budget for FY 2026-27 in the amount of $683,797 financed by contingencies to be reimbursed by insurance. The CAO reviewed funding options, and if the Sheriff’s Office is not able to absorb the cost of the project within its FY 2026-27 Adopted Budget, recommends contingencies be used due to numerous competing projects and insufficient funds in Building Improvement and Replacement Fund 478. Once insurance reimburses the claim, contingencies would partially be replenished.
BOARD OF SUPERVISORS STRATEGIC PLAN GOALS:
The proposed recommended action demonstrates the County’s commitment to provide public safety in the County of Monterey.
X Well-Being and Quality of Life
X Sustainable Infrastructure for the Present and Future
X Safe and Resilient Communities
__ Diverse and Thriving Economy
__ Dynamic Organization and Employer of Choice
Prepared by: Renee Hankla, Administrative Operations Manager, Ext#3736
Reviewed by: Timothy Lanquist, Chief Deputy, Ext#3887
Reviewed by: Keith Boyd, Undersheriff, Ext#3859
Approved by: Tina M. Nieto, Sheriff/Coroner, Ext#3750
Attachments:
Job Order Control #JF02-24-14-J8552-01
Proposed Project Budget Part 2