Legislation Details

File #: JBL 26-020    Name: Plunge Pool-JBL Sept
Type: Joint Board Leadership Status: Agenda Ready
File created: 9/11/2026 In control: Joint Water Resources/Board of Supervisors Leadership Committee
On agenda: 9/17/2026 Final action:
Title: Receive an Update on the Nacimiento Dam Spillway Plunge Pool Erosion Protection Project.
Attachments: 1. Board Report
Date Action ByActionResultAction DetailsSearchable Meeting DetailsVideo
No records to display.

Title

Receive an Update on the Nacimiento Dam Spillway Plunge Pool Erosion Protection Project.

Report

SUMMARY/DISCUSSION:

The Nacimiento Dam Spillway Plunge Pool Erosion Protection Project is a dam safety initiative to address ongoing erosion concerns caused by high velocity spillway flows entering the plunge pool. Past spill events have eroded the left and right banks, displaced riprap, and exposed weak underlying rock formations. Recent hydraulic modeling, a geotechnical investigation and report, and the 30% design have been completed by AECOM Technical Services, to construct a roller compacted concrete (RCC) erosion protection system to ensure spillway and dam safety during large flood events, including the Probable Maximum Flood (PMF).

 

The Agency contracted with GEI Consultants in September 2026 to perform environmental consulting services.  The project kickoff meeting will be held in early October, and the activities will closely align with the design work. Environmental permitting and regulatory coordination with DSOD, FERC, RWQCB, CDFW, and the U.S. Army Corps of Engineers will continue as the design advances.

 

The Spillway Plunge Pool Erosion Protection Project is on schedule.  Key milestones include:

Completed Milestones

                     Topographic & bathymetric surveys: Jan 2024

                     Geotechnical investigations & borings: Nov 2024 - Jul 2025

                     Alternatives hydraulic modeling: 2025 - Feb 2026

                     Selection of preferred alternative (Alt. 1): Feb 19, 2026

                     30% Design Report completed: Aug 28, 2026

                     30% Design Report Submission to DSOD for review: Sept 14, 2026

Upcoming Milestones

                     Begin 60% design development: Nov 2026

                     Complete 60% design package: Jan 2027

                     Regulatory review of 60% design: Mar - May 2027

                     Complete 90% design package: Jul 2027

                     Final design completion: Nov 2027

                     Bid package preparation: Feb - Mar 2028

                     Advertise for construction bids: Mar 2028

                     Issue Notice to Proceed: Jun 2028

 

Construction is subject to permitting, funding, and contractor procurement.

 

OTHER AGENCY INVOLVEMENT:

California Department of Water Resources

Federal Energy Regulatory Commission

 

FINANCING:

May of 2023, the Agency secured approximately $6.1 million in funds under Funding Agreement No. 4600015276 for use toward dam safety projects at Nacimiento Dam through a funding agreement with the California Department of Water Resources.  $1.67 million dollars has been allocated toward the design of the Nacimiento Dam Spillway Plunge Pool Erosion Protection Project.  The Agency is in possession of funds for this agreement.

 

Additional funding for environmental permitting and construction has been identified under SB104 for use toward dam safety projects through a reimbursable funding agreement with the California Department of Water Resources.

 

Prepared by:                                          Mark Foxworthy, Senior Water Resources Engineer, (831) 788-3454

 

Approved by:                                          Ara Azhderian, General Manager, (831) 755-4860