Legislation Details

File #: JBL 26-019    Name: SA Spillway Update-JBL Sept
Type: Joint Board Leadership Status: Agenda Ready
File created: 9/11/2026 In control: Joint Water Resources/Board of Supervisors Leadership Committee
On agenda: 9/17/2026 Final action:
Title: Receive an Update on the San Antonio Dam Spillway Replacement Project.
Attachments: 1. Board Report
Date Action ByActionResultAction DetailsSearchable Meeting DetailsVideo
No records to display.

Title

Receive an Update on the San Antonio Dam Spillway Replacement Project.

Report

SUMMARY/DISCUSSION:

Following the Oroville Dam Spillway failure in 2017, the California Department of Water Resources, Division of Safety of Dams (DSOD) required the Agency perform a condition assessment of the San Antonio Dam Spillway.  Ultimately, DSOD mandated the spillway be replaced.  The Agency has until December 2031 to complete that replacement project. 

 

The Agency contracted with McMillen Inc. in October 2024 to provide engineering design services for the San Antonio Dam Spillway Replacement Project.  The initial tasks included the

Probable Maximum Flood Study and Alternatives Analysis Report to inform the design.  Those reports were approved by DSOD in May 2026.  McMillen then prepared the 30% Design Drawings and Documentation Report.  These were submitted to DSOD in September 2026 with an anticipated 90-day review period.

 

The Agency contracted with GEI Consultants in September 2026 to perform environmental consulting services.  The project kickoff meeting will be held in early October and the activities will closely align with the design work.

 

The Spillway Replacement Project is on schedule.  Key milestones include:

                     Fall 2026: Begin CEQA process

                     Winter 2027: Construct and test a physical model of the spillway

                     Winter 2027: Complete 60% Design Documentation

                     Spring 2027: DSOD Review

                     Summer 2027: Draft CEQA documentation for public review

                     Summer 2027: Complete 90% Design Documentation

                     Fall 2027: DSOD Review

                     Fall 2027: Final CEQA documentation

                     Fall 2027: 100% Design Documentation

                     TBD: Final Permitting

                     TBD: Construction

 

OTHER AGENCY INVOLVEMENT:

California Department of Water Resources

 

FINANCING:

May of 2024, the Agency secured approximately $16.15 million in funds under SB104 for use toward dam safety projects through a funding agreement with the California Department of Water Resources.  An estimated three (3) million dollars has been allocated toward the final design of the San Antonio Spillway Replacement Project.  This a reimbursable funding agreement and so Agency funds will be utilized to support the project until the reimbursements are received. 

 

Prepared by:                                          Shaunna Murray, Deputy General Manager, (831) 755-4860

 

Approved by:                                          Ara Azhderian, General Manager, (831) 755-4860