Public hearing to consider a Coastal Development Permit allowing the construction of three roundabouts to replace the existing Castroville Boulevard signalized intersection. Two of the three roundabouts will connect Highway 156 with Castroville Boulevard, just east of the existing intersection, by adding eastbound and westbound off ramps leading to a roundabout (on the north of the highway for westbound traffic and south side of the highway for eastbound traffic). Roundabouts will be connected by a bridge over the highway. The third roundabout will be located near the intersection of Castroville Blvd and Cielo Azul Road. The project will also provide a new Class 1 mixed use bicycle and pedestrian path. The improvements will be located within 100 feet of environmentally sensitive habitat. This hearing was continued from the May 25, 2022, Planning Commission meeting.
Project Location: Highway 156 between Castroville Boulevard (postmile R1.40) and the Moro Cojo Slough Bridge (postmile 1.60).
Proposed CEQA Action: Consider a Final Environmental Impact Report/Environmental Impact Statement (FEIR/EIS) previously certified by the California Department of Transportation for the State Route 156 West Corridor Project on January 31, 2013 (SCH#1999111063).
Report
RECOMMENDATION
It is recommended that the Planning Commission:
a. Receive a report and presentation on the State Route 156 Interchange Roundabouts project;
b. Continue the hearing to the June 29, 2022 Planning Commission hearing; and
c. Direct staff to return with written findings, evidence and conditions of approval, as appropriate.
PROJECT INFORMATION
Owner: California Department of Transportation
Planning File Number: PLN200118
Project Location: Highway 156 between Castroville Boulevard (postmile R1.40) and the Moro Cojo Slough Bridge (postmile 1.60)
APNs: 133-071-010-000, 133-071-011-000, 133-071-012-000, 133-071-013-000, 133-071-021-000, 133-072-034-000, 133-073-001-000, 133-073-002-000, 133-073-003-000, 133-073-004-000, 133-073-005-000, 133-073-006-000, 133-073-007-000, 133-073-008-000, 133-073-009-000 and 133-081-007-000), North County Land Use Plan, Coastal Zone.
Zoning: Coastal Agricultural Preserve (CAP), Resource Conservation (RC), High Density Residential (HDR), and Coastal General Commercial (CGC)
Parcel Size: 43 acres for all parcels
Plan Area: North County Coastal
Flagged and Staked N/A
BACKGROUND:
This Caltrans Combined Development Permit was noticed and originally heard at the May 25, 2022 Planning Commission hearing. In preparation of the hearing documents, County staff worked with Caltrans staff to ensure project impacts and mitigations were appropriately identified in the draft resolution and incorporated as conditions of approval.
Staff has reviewed the project materials and due to the project’s history, it’s modified scope of development and the volume to documents to consider, staff recommends that the Planning Commission first be introduced to the project in more of a workshop format to allow discussion and/or feedback.
Staff also requests that the Planning Commission continue the hearing to June 29, 2022 and direct staff to return with appropriate findings, evidence and conditions of approval.
SUMMARY:
The California Department of Transportation (Caltrans) and the Federal Highway Administration (FHA), in cooperation with the Transportation Agency of Monterey County (TAMC), proposes to replace the existing at grade signalized intersection of Castroville Boulevard State Route 156 West (hereafter “Hwy 156” or “highway”) with a new separated grade intersection containing off ramps, roundabouts, and road relocation. This Castroville Blvd interchange project has been separated out as Phase 1 of Caltrans Hwy 156 corridor safety improvements. The corridor improvements include projects from Highway 101 to Highway 1 along the highway; however, funding for the whole project is not available. The Castroville Blvd interchange project is moving forward as Phase 1 of the corridor improvements with funding form Measure X and because this improvement has been prioritized due to higher-than-average rates of collisions at this intersection. Other phases of the project will be studied when funding is identified. This report focuses on the Castroville Blvd interchange project/phase.
The project is located in the Coastal areas of North Monterey County (North County Land Use Plan area). Zoning designations in the project area include: Coastal Agricultural Preserve (CAP), High Density Residential (HDR), Coastal General Commercial (CGC) and Resource Conservation (RC). Within the project area, the existing land uses are a mix of active farmland properties, urban build environments and undeveloped commercial/residential sites. The improvements would disturb approximately 75 total acres. 43 of those acres will be permanently altered by roadway improvements. Of the 75 acre disturbance area, approximately 55 percent (41 acres) is farmland (mostly south of Hwy 156) and 45 percent (34 acres) is residential/commercial (mostly north of Hwy 156).
Caltrans, as the lead agency, prepared and certified an Environmental Impact Report (EIR) and Environmental Impact Statement (EIS) pursuant to the California Environmental Quality Act (CEQA) and the National Environmental Protection Act (NEPA) for the Highway 156 corridor improvements, which include the Castroville Blvd interchange improvements as a component. Alternative designs for the intersection improvements were studied and Caltrans ultimately choose the roundabout design as the preferred alternative. This design takes into account current and potential future land use and road improvements in the area including the CHISPA Castroville Oaks project, railway alignments, future road widening designs, and other environmental considerations.
The EIR/EIS identified conversion of farmland for the project as a significant and unavoidable impact. Other impacts were found to be less than significant or less than significant with mitigation. Potentially significant but mitigatable impacts included visual/aesthetics, air quality, biology (including impacts to natural communities, wetlands, and special status species like the federally endangered Long-toed salamander), hydrology and water quality, noise, land use, and potential growth inducing effects. Staff has reviewed the EIR/EIS and found it adequate to comply with CEQA/NEPA. Mitigations applicable to the Castroville Blvd interchange portion of the project within the responsibility of the County (to issue a Coastal Development Permit) have been incorporated as conditions of approval of the project.
In this case, although there will be significant impacts as a result of conversion of farmlands, the benefits of the project may override the significant unavoidable impacts. The proposed intersection and driveway improvements will address long-standing safety issues and will help alleviate congestion.
During review of the application, one area of controversy has been identified. California Coastal Commission staff have reviewed the project and are suggesting that the project requires an amendment to the North County Land Use Plan (LUP) in order to be found consistent. Staff and Caltrans have reviewed that letter and disagree. The LUP was amended September 9, 2008 in association with the Salinas Road interchange improvements. That LUP amendment involved similar resource impacts. The proposed Castroville Blvd intersection improvements are consistent with the revised LUP and overall the project, as mitigated, minimizes impacts on coastal resources while providing needed safety improvements.
DISCUSSION:
See Exhibit A for a more detailed discussion of the project.
OTHER AGENCY INVOLVEMENT:
The following agencies have reviewed the project, have comments, and/or have recommended conditions:
California Coastal Commission
Environmental Health Bureau
HCD-Engineering Services
HCD-Environmental Services
North County Fire Protection District
North County Coastal Land Use Advisory Committee
California Department of Transportation, District 5
Prepared by: Fionna Jensen, Associate Planner
Elizabeth Gonzales, Supervising Planner, and
Anna Quenga, AICP, Principal Planner
Reviewed by: Craig Spencer, Chief of Planning
Approved by: Erik Lundquist, AICP, Director HCD
The following attachments are on file with the HCD:
Exhibit A - Detailed Project Discussion
Exhibit B - Local Coastal Plan Consistency Matrix
Exhibit C - NEPA/CEQA Re-Validation Form* (hyperlinked on Exhibit Cover Page)
Attachment 1 - FEIR/EIS* (hyperlinked on Exhibit Cover Page)
Attachment 2 - NES* (hyperlinked on Exhibit Cover Page)
Exhibit D - Project Plans
Exhibits which include an asterisk (*) may also be found at: https://www.co.monterey.ca.us/government/departments-a-h/housing-community-development/planning-services/current-planning/general-info/current-major-projects
cc: Front Counter Copy; California Coastal Commission; Erik Lundquist, HCD Director, Craig Spencer, Chief of Planning; Fionna Jensen, Associate Planner; Elizabeth Gonzales, Supervising Planner; Anna Quenga, AICP, Principal Planer; Mitch Dallas, Caltrans, Applicant/Owner; The Open Monterey Project (Molly Erickson); LandWatch (Executive Director); Project File PLN200118.