File #: WRAG 14-038    Name: WRA Quarterly Report - Budget committee
Type: WRA General Status: Agenda Ready
File created: 8/20/2014 In control: Budget Committee
On agenda: 8/27/2014 Final action:
Title: Receive and accept the Monterey County Water Resources Agency (MCWRA) Quarterly Financial Status Report through June 2014.
Attachments: 1. Summary of Fund 111 & Status Report

Title

Receive and accept the Monterey County Water Resources Agency (MCWRA) Quarterly Financial Status Report through June 2014.

 

Report

RECOMMENDATION:

It is recommended that the Budget Committee:

 

Receive and accept the Monterey County Water Resources Agency (MCWRA) Quarterly Financial Status Report through June 2014.

 

SUMMARY/DISCUSSION:

 

Revenues for most Agency funds are projected to meet budget estimates and in some cases exceed expectations due to additional receipts from Ad Valorem taxes, assessments fees, RDA AB/129 distributions, boat dock fees, and grants. Fund 112, the Pajaro River Levee, received 65% of anticipated revenues due Santa Cruz County proceeding with a construction contractor at a cost less than originally forecasted.  

 

A Budget amendment in September of 2013 authorized the Agency to transfer of $810,805 from the Fund 111 Hydro Stabilization Reserve due to less than expected flow releases from Nacimiento as a result of continued drought conditions and delays in insurance reimbursements for Fund 130 emergency repairs at the hydroelectric plant that occurred in 2012. The Agency anticipates approximately $570,000 in business interruption insurance to be received in FY 2014-15. On a consolidated basis the Agency financial performance is projected as follows:

 

                     FY 2013-14 Actual beginning fund balance                                                                   $ 14,246,180

                     FY 2013-14 Preliminary Revenues                                                                        20,842,820

                     Total FY 2013-14 Available funds                                                                     $ 35,089,000

                     Less: 2013-14 Preliminary expenditures                                               (18,735,889)

            FY 2013-14 Projected Ending Fund Balance                                $ 16,353,111                     

 

OTHER AGENCY INVOLVEMENT:

 

The Agency’s Finance Committee and Board of Directors have been involved in the development of the Budget; but, the Board of Directors will formally approve this report during the Regular Board of Directors meeting on August 25, 2014.

 

FINANCING:

 

There is no financial impact in receiving this report.

 

Prepared by:                                                                                                                                                                                                                  

                                          Cathy Paladini, Finance Manager, (831) 755-4861

 

Approved by:                                                                                                                                                                                                                  

                                          David E. Chardavoyne, General Manager, (831) 755-4860

 

Attachments:  Summary of Administration Fund 111 & Status Report