File #: 16-724    Name:
Type: General Agenda Item Status: Passed
File created: 6/2/2016 In control: Board of Supervisors
On agenda: 6/14/2016 Final action: 6/14/2016
Title: a. Adopt the Plans and Specifications for the 855 E. Laurel, Bldg A-Equipment and Stormwater Management-Canopy Project No. 8569, Bid Package No.10570; and b. Authorize the Interim Director of Public Works and Facilities to advertise for bids in the Monterey County Weekly.
Sponsors: Public Works / RMA
Attachments: 1. Board Report, 2. Notice to Bidders Inviting Formal Bids_6-14-2016_DDSca51615, 3. Project Budget, 4. 855 Stormwater Canopy Project No. 8569_Project Manual, 5. Site Map 855 Laurel Bldg A, 6. 855 Stormwater Canopy Project 8569_Plans, 7. Completed Board Order, 8. Updated Board Order

Title

a.  Adopt the Plans and Specifications for the 855 E. Laurel, Bldg A-Equipment and Stormwater Management-Canopy Project No. 8569, Bid Package No.10570; and

b.  Authorize the Interim Director of Public Works and Facilities to advertise for bids in the Monterey County Weekly.

 

Report

RECOMMENDATION:

It is recommended that the Board of Supervisors:

a. Adopt the Plans and Specifications for the 855 E. Laurel, Bldg A-Equipment and Stormwater Management-Canopy Project No. 8569, Bid Package No.10570; and

b. Authorize the Interim Director of Public Works and Facilities to advertise for bids in the Monterey County Weekly.

 

SUMMARY/DISCUSSION:

Staff is seeking adoption of the Plans and Specifications and authorization to advertise for bids for the 855 E. Laurel, Bldg A-Equipment and Stormwater Management-Canopy Project No. 8569, Bid Package No.10570 (Project).  The bid opening is set for Thursday, August 4, 2016, at 2:00 p.m., in the Board of Supervisors’ Conference Room 1032, Monterey County Government Center, 168 West Alisal Street 1st Floor, Salinas, California 93901.  The recommended action authorizes staff to proceed with the advertisement and bid selection for the construction phase of the Project.

 

A 4000-square foot canopy will be built on the concrete apron immediately adjacent to the Fleet Maintenance facility to shed stormwater over and away from contaminants on the concrete work surface below.  Additionally, the new canopy will provide high-clearance overhead protection from the weather for fleet maintenance workers and County equipment.  Construction is scheduled to begin in November 2016, with completion anticipated in March 2017.  A “Notice to Bidders” will be duly advertised in a newspaper of general circulation per California Public Contract Code Section 20150.8.

 

This project advances County strategic initiatives by promoting best environmental practices for County facilities and operations, protecting regional water quality, and improving County facilities and working conditions for County workers.

 

OTHER AGENCY INVOLVEMENT:

RMA coordinated with the County Administrative Office’s Fleet Management Division to develop the Project Plans and Specifications.  Offices of the County Counsel, Auditor-Controller, and Risk Management have reviewed and approved the Specifications as to form and legality, fiscal terms, and insurance provisions, respectively.

 

FINANCING:

Total estimated project cost is $436,960.  The Project is fully funded in Facilities Maintenance Projects Fund 401.

 

Prepared by: Dave Pratt, Project Manager II, (831) 796-6091

 

Approved by: Benny J. Young, Interim Director of Public Works & Facilities

 

Approved by: Carl P. Holm, AICP, RMA Director

 