File #: ZA 24-054    Name: PLN210091 - SANTA ROSA MOTEL CO.
Type: General Agenda Item Status: Agenda Ready
File created: 11/8/2024 In control: County of Monterey Zoning Administrator
On agenda: 4/23/2024 Final action:
Title: PLN210091 - SANTA ROSA MOTEL CO. Public hearing to consider demolition and rebuild of nine structures and site renovations to the existing Portofino Inn and removal of two protected oak trees (one landmark). Project Location: 10 Country Club Way, Carmel Valley, Carmel Valley Master Plan Proposed CEQA action: Find the project Categorically Exempt pursuant to Section 15302 of the CEQA Guidelines
Attachments: 1. Staff Report, 2. Exhibit A - Draft Resolution, 3. Arborist Report and Tree Protection Plan (combined documents LIB230177 and LIB230178), 4. Exhibit C - Carmel Valley LUAC Minutes (May 16, 2022), 5. Exhibit D - Vicinity Map
Title

PLN210091 - SANTA ROSA MOTEL CO.

Public hearing to consider demolition and rebuild of nine structures and site renovations to the existing Portofino Inn and removal of two protected oak trees (one landmark).

Project Location: 10 Country Club Way, Carmel Valley, Carmel Valley Master Plan

Proposed CEQA action: Find the project Categorically Exempt pursuant to Section 15302 of the CEQA Guidelines

Body

RECOMMENDATION:

It is recommended that the Zoning Administrator approve a Resolution allowing the following:

1)                     Find the project categorically exempt from environmental review pursuant to Section 15302 of the CEQA Guidelines and there are no exceptions pursuant to Section 15300.2 of the CEQA guidelines; and

2)                     Approve an Administrative Permit and Design Approval to allow facility renovations to the Portofino Inn consisting of the demolition & rebuild of nine existing buildings:  Building A, 1,709 sq. ft. caretaker residence proposed to be reduced by demolition of a 578 sq. ft. attached shed, with a new building entry adding 57 sq. ft. and an approximately 480 sq. ft. portochere; Building B, 2,411 sq. ft. barn proposed to be rebuilt as 2,444 sq. ft. and with a new 120 sq. ft. covered patio;  Building C, 5,974 sq. ft. clubhouse proposed to be rebuilt as 6,006 sq. ft., associated new covered patio approximately 455 sq. ft.;  Building D, 410 sq. ft. pool house proposed to be rebuilt in same footprint as a guest exercise room with a basement; existing cabins E1.A (1,720 sq. ft.), E1.B (1,720 sq. ft.), E2.A  (1,149 sq. ft.), E2.B (1,149 sq. ft.) and E3 (577 sq. ft.) full remodel; demolition/relocation of the pool from 2,322 sq. ft. to 420 sq. ft. and spa from 60 sq. ft. to 301 sq. ft. and construction of new patios. Project includes onsite wastewater treatment system upgrade, rehabilitation of flatwork (walkways, parking areas & hardscape), landscape rehabilitation, and removal of two Oak trees: one single tr...

Click here for full text