File #: RES 12-0101    Name: NOC MPE Blanco Rd Class II Bikeway Proj
Type: BoS Resolution Status: Passed
File created: 10/2/2012 In control: Board of Supervisors
On agenda: 10/16/2012 Final action: 10/16/2012
Title: Adopt a Resolution: a. Accepting the Certificate of Completion for construction of the Blanco Rd Class II Bikeway Project, Project No. 11-869365, State Project EA 05-4A2794L, Federal Aid Project No. RPSTPLE-5944(106) performed by Monterey Peninsula Engineering; and b. Authorizing the Director of Public Works to execute and record the Notice of Completion for the Blanco Rd Class II Bikeway Project, Project No. 11-869365, State Project EA 05-4A2794L, Federal Aid Project No. RPSTPLE-5944(106) performed by Monterey Peninsula Engineering.
Sponsors: Public Works / RMA
Attachments: 1. Resolution, 2. Project Budget, 3. Certificate of Completion, 4. Notice of Completion, 5. Location Map, 6. Completed Board Order & Resolution, 7. Recorded Page & Certificate of Completion
Title
Adopt a Resolution:
a. Accepting the Certificate of Completion for construction of the Blanco Rd Class II Bikeway Project, Project No. 11-869365, State Project EA 05-4A2794L, Federal Aid Project No. RPSTPLE-5944(106) performed by Monterey Peninsula Engineering; and
b. Authorizing the Director of Public Works to execute and record the Notice of Completion for the Blanco Rd Class II Bikeway Project, Project No. 11-869365, State Project EA 05-4A2794L, Federal Aid Project No. RPSTPLE-5944(106) performed by Monterey Peninsula Engineering.

Report
RECOMMENDATIONS:
It is recommended that the Board of Supervisors adopt a Resolution:
a. Accepting the Certificate of Completion for construction of the Blanco Rd Class II Bikeway Project, Project No. 11-869365, State Project EA 05-4A2794L, Federal Aid Project No. RPSTPLE-5944(106) performed by Monterey Peninsula Engineering; and
b. Authorizing the Director of Public Works to execute and record the Notice of Completion for the Blanco Rd Class II Bikeway Project, Project No. 11-869365, State Project EA 05-4A2794L, Federal Aid Project No. RPSTPLE-5944(106) performed by Monterey Peninsula Engineering.

SUMMARY/DISCUSSION:
On December 13, 2011, the Board of Supervisors awarded a contract to Monterey Peninsula Engineering for construction of the Blanco Rd Class II Bikeway Project, Project No. 11-869365, State Project EA 05-4A2794L, Federal Aid Project No. RPSTPLE-5944(106) (Project). The Project consisted of replacing the existing 4” white edgeline with a 6” white edgeline on Blanco Road, from Research Drive by the City of Marina to Luther Way by the City of Salinas, approximately 5.14 miles. The Project also included the installation of Bike Lane signs and pavement markings.

The contract is complete in all respects in accordance with the Plans and Special Provisions. The work is ready to be accepted by the Board of Supervisors.

OTHER AGENCY INVOLVEMENT:
None.

FINANCING:
There is no impact to the General Fund. The tot...