File #: 14-1188    Name: Approve addition of Castroville Blvd Overlay to Work Plan FY14-15
Type: General Agenda Item Status: Passed
File created: 10/17/2014 In control: Board of Supervisors
On agenda: 11/4/2014 Final action: 11/4/2014
Title: a. Approve the addition of the Castroville Boulevard Overlay, Project No. 14-157165, to the approved Work Plan for Fiscal Year 2014-15; b. Approve an increase in appropriations in the amount of $1,553,841 in the FY 2014-15 Road Fund, Fund 002-3000-8195-RMA012 for the Castroville Boulevard Overlay (4/5th vote required); c. Authorize the use of uncommitted fund balance, in the amount of $1,553,841, as the financing source; and d. Authorize the Auditor-Controller to incorporate the approved modification in the FY 2014-15 Budget.
Sponsors: Public Works / RMA
Attachments: 1. Board Report, 2. Project Budget, 3. Location Map, 4. Completed Board Order
Title
a. Approve the addition of the Castroville Boulevard Overlay, Project No. 14-157165, to the approved Work Plan for Fiscal Year 2014-15;
b. Approve an increase in appropriations in the amount of $1,553,841 in the FY 2014-15 Road Fund, Fund 002-3000-8195-RMA012 for the Castroville Boulevard Overlay (4/5th vote required);
c. Authorize the use of uncommitted fund balance, in the amount of $1,553,841, as the financing source; and
d. Authorize the Auditor-Controller to incorporate the approved modification in the FY 2014-15 Budget.

Report
RECOMMENDATION:
It is recommended that the Board of Supervisors:

a. Approve the addition of the Castroville Boulevard Overlay, Project No. 14-157165, to the approved Work Plan for Fiscal Year 2014-15;

b. Approve an increase in appropriations in the amount of $1,553,841 in the FY 2014-15 Road Fund, Fund 002-3000-8195-RMA012 for the Castroville Boulevard Overlay (4/5th vote required);

c. Authorize the use of uncommitted fund balance, in the amount of $1,553,841, as the financing source; and

d. Authorize the Auditor-Controller to incorporate the approved modification in the FY 2014-15 Budget.

SUMMARY/DISCUSSION:
The Castroville Boulevard Overlay project is to pave Castroville Boulevard with hot-mix-asphalt from State Route 156 to San Miguel Canyon Road. The project is being constructed concurrently with a safety improvement pavement delineation project along the same road, within the same limits. The project was included in the Fiscal Year 2013-14 Work Plan and was anticipated to be complete in the same year. However, the project was awarded on June 3, 2014 to The Don Chapin Company, Inc; and is still currently in construction. Therefore, the Resource Management Agency-Public Works requests the project be included in the FY 2014-15 Work Plan and Adopted Budget.

The Board of Supervisors adopted the Plans and Special Provisions for the project on February 25, 2014 and authorized the Director of Publ...

Click here for full text