Title
Approve and authorize the Contracts/Purchasing Officer to sign Amendment No. 1 to the professional services agreement with Kennedy/Jenks Consultants (Lake San Antonio Resort/Marina Site), extending the agreement term by one year to January 31, 2016, for required work needed to support Lake San Antonio environmental remediation and properly address the State Regional Water Board's current site clean-up concerns and recommendations, in an amount not to exceed $212,000 for a total compensation amount not to exceed $231,700.
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors approve and authorize the Contracts/Purchasing Officer to sign Amendment No. 1 to professional services agreement with Kennedy/Jenks Consultants (Lake San Antonio Resort/Marina Site), extending the agreement term by one year to January 31, 2016, for required work needed to support Lake San Antonio environmental remediation and properly address the State Regional Water Board's current site clean-up concerns and recommendations, in an amount not to exceed $212,000 for a total compensation amount not to exceed $231,700.
SUMMARY/DISCUSSION:
The CAO-Budget and Analysis Division requested County Counsel-Risk Management Division to assume responsibility for the payment and tracking of the fuel spill costs on behalf of the County. County Counsel-Risk Management Division requested and received support from the Board of Supervisors to authorize the transfer of General Fund Contingency funds last fiscal year for $1,018,685 to the newly created Lakes Fuel Spill Budget Unit 8429 for remediation costs related to the San Antonio and Nacimiento Lakes Fuel Spill. The transfer was approved by the Board of Supervisors on June 11, 2013. As indicated within our board report, (#13-0644, on June 25, 2013) County Counsel-Risk Management Division is utilizing the services of a licensed engineering and geological firm (Kennedy/Jenks) for the required work. Working toward full remedia...
Click here for full text