File #: A 12-076    Name: Reel Grobman (Seismic Compliance) Amendment #3
Type: BoS Agreement Status: Passed
File created: 5/9/2012 In control: Board of Supervisors
On agenda: 6/12/2012 Final action: 6/12/2012
Title: Authorize the Purchasing Manager for Natividad Medical Center (NMC) to execute Amendment No. 3 to the Agreement (A-11873) with Reel Grobman & Associates for Seismic Compliance Architectural Design Services at NMC, extending the Agreement to June 30, 2013 for a total Agreement amount not to exceed $170,535 (no change to the previously approved amount).
Attachments: 1. Reel Grobman (Seismic Compliance), 2. Completed Board Order Item 48
Title
Authorize the Purchasing Manager for Natividad Medical Center (NMC) to execute Amendment No. 3 to the Agreement (A-11873) with Reel Grobman & Associates for Seismic Compliance Architectural Design Services at NMC, extending the Agreement to June 30, 2013 for a total Agreement amount not to exceed $170,535 (no change to the previously approved amount).

Body
RECOMMENDATION:

It is recommended the Board of Supervisors authorize the Purchasing Manager for Natividad Medical Center (NMC) to execute Amendment No. 3 to the Agreement (A-11873) with Reel Grobman & Associates for Seismic Compliance Architectural Design Services at NMC, extending the Agreement to June 30, 2013 for a total Agreement amount not to exceed $170,535 (no change to the previously approved amount).

SUMMARY/DISCUSSION:

Natividad Medical Center desires to continue its established relationship with Reel Grobman & Associates architectural firm for the Seismic Compliance Project. This project was not completed during Fiscal Year 2012, and therefore, the hospital would like to extend the term date of this agreement to June 30, 2013, which will allow for the hospital to complete the project. There will be no increase of dollars from the amounts that were previously approved by the Board of Supervisors.

In October 2010 the Board of Supervisors approved the Seismic Compliance Project. The total amount approved for this project was $170,535. To date, we have completed 72% of the approved scope of work and have paid $123,014.

OTHER AGENCY INVOLVEMENT:

County Counsel has reviewed and approved this Amendment as to legal form and risk provisions. Auditor-Controller has reviewed and approved this Amendment as to fiscal provisions. The Amendment has also been reviewed and approved by Natividad Medical Center’s Board of Trustees.

FINANCING:

There are no additional costs to this “term extension only” Amendment. The previously approved cost for this Agreement was $170,535. The remaining amount ($...

Click here for full text