Title: Receive a status report on the Job Order Contract Program from the Public Works, Facilities and Parks Department supporting Public Works and Facilities projects for the period of October 2024 through March 2025 to capture Fiscal Year (FY) 2024-25 Quarters Two and Three.
Attachments: 1. CIC Report, 2. Attachment A - Project Summary FY25 Q2-Q3
Date Action ByActionResultAction DetailsSearchable Meeting DetailsVideo
No records to display.
Title
Receive a status report on the Job Order Contract Program from the Public Works, Facilities and Parks Department supporting Public Works and Facilities projects for the period of October 2024 through March 2025 to capture Fiscal Year (FY) 2024-25 Quarters Two and Three.
Report
RECOMMENDATION:
It is recommended that the Capital Improvement Committee receive a status report on the Job Order Contract Program from the Public Works, Facilities and Parks Department supporting Public Works and Facilities projects for the period of October 2024 through March 2025 to capture FY 2024-25 Quarters Two and Three.

SUMMARY/DISCUSSION:
The Capital Improvement Committee (CIC) requested to receive quarterly reports on the Job Order Contracting (JOC) program managed by Public Works, Facilities and Parks (PWFP) supporting Public Works and Facilities projects.

October 1, 2024 through March 31, 2025 (FY25) Quarters Two and Three Project Summary:

Facilities
- Project Job Orders: 38
- Construction Contract Value: $5,375,507
- Gordian License Fees (JOC Fees): $268,775
- Gordian Construction Management (JOC Plus Fees): $162,652

Public Works
- Project Job Orders: 52
- Construction Contract Value: $8,042,383
- Gordian License Fees (JOC Fees): $402,119
- Gordian Construction Management (JOC Plus Fees): $55,944

Total
- Project Job Orders: 90
- Construction Contract Value: $13,417,890
- Gordian License Fees (JOC Fees): $670,894
- Gordian Construction Management (JOC Plus Fees): $218,596
- Use of Local Contractor/Employer in Contracts: 50%
- Average Days to Procure: 19

Combined Local Work Force Percentage
Attachment A reports the number of Facilities and Public Works projects issued Notice to Proceed (NTP) in FY 2024-25 Quarters Two and Three.

JOC provides an alternative procurement method for completing public works projects which improves economy and efficiency in completing many public works projects, including urgent and time sensitive projects. The price of an ind...