Title: Adopt a Resolution to: a. Authorize and direct the Auditor-Controller to amend the Fiscal Year (FY) 2024-25 Adopted Budget for the General Fund Contingencies 001, Appropriation Unit CAO020, to increase appropriations and operating transfer out by $966,434 for the 1200 Aguajito Monterey HVAC Repairs and Replacement Project (4/5ths vote required); b. Authorize and direct the Auditor-Controller to amend the FY 2024-25 Adopted Budget for the Capital Project Fund 404, Appropriation Unit PFP057, to increase appropriations and operating transfer in by $966,434, for the 1200 Aguajito Road, Monterey, HVAC Repair and Replacement Project (4/5ths vote required); and c. Authorize and direct the Auditor-Controller to transfer $966,434 for the FY 2024-25 from the General Fund Contingencies 001, Appropriation Unit CAO020, to Capital Project Fund 404, Appropriation Unit PFP057 (4/5ths vote required).
Attachments: 1. Board Report, 2. Attachment A - Project Budget, 3. Attachment B - Proposed Resolution, 4. Completed Board Order Item No. 63, 5. Completed Resolution Item No. 63
Title
Adopt a Resolution to:
a. Authorize and direct the Auditor-Controller to amend the Fiscal Year (FY) 2024-25 Adopted Budget for the General Fund Contingencies 001, Appropriation Unit CAO020, to increase appropriations and operating transfer out by $966,434 for the 1200 Aguajito Monterey HVAC Repairs and Replacement Project (4/5ths vote required);
b. Authorize and direct the Auditor-Controller to amend the FY 2024-25 Adopted Budget for the Capital Project Fund 404, Appropriation Unit PFP057, to increase appropriations and operating transfer in by $966,434, for the 1200 Aguajito Road, Monterey, HVAC Repair and Replacement Project (4/5ths vote required); and
c. Authorize and direct the Auditor-Controller to transfer $966,434 for the FY 2024-25 from the General Fund Contingencies 001, Appropriation Unit CAO020, to Capital Project Fund 404, Appropriation Unit PFP057 (4/5ths vote required).
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors adopt a resolution to:
a. Authorize and direct the Auditor-Controller to amend the Fiscal Year (FY) 2024-25 Adopted Budget for the General Fund Contingencies 001, Appropriation Unit CAO020, to increase appropriations and operating transfer out by $966,434 for the 1200 Aguajito Monterey HVAC Repairs and Replacement Project (4/5ths vote required);
b. Authorize and direct the Auditor-Controller to amend the FY 2024-25 Adopted Budget for the Capital Project Fund 404, Appropriation Unit PFP057, to increase appropriations and operating transfer in by $966,434, for the 1200 Aguajito Road, Monterey, HVAC Repair and Replacement Project (4/5ths vote required); and
c. Authorize and direct the Auditor-Controller to transfer $966,434 for the FY 2024-25 from the General Fund Contingencies 001, Appropriation Unit CAO020, to Capital Project Fund 404, Appropriation Unit PFP057 (4/5ths vote required).

SUMMARY/DISCUSSION:
Public Works, Facilities and Parks (PWFP) engaged The Paul Davis Partnership, LLC (Consultant) from it’...