File #: 24-295    Name: PLN220090 - Caltrans/Garrapata Bridge Rails
Type: General Agenda Item Status: Scheduled PM
File created: 4/16/2024 In control: Board of Supervisors
On agenda: 5/7/2024 Final action:
Title: PLN220090 - CALTRANS/GARRAPATA BRIDGE RAILS Public hearing to consider California Department of Transportation's ("Caltrans") appeal of the Garrapata Creek Bridge Rail Replacement Project on Highway 1, Big Sur. Project Location: Garrapata Creek Bridge near post mile 63.0 on HWY 1, Big Sur Land Use Plan. Proposed California Environmental Quality Act ("CEQA") action: Continuing the project would be an administrative activity of government which would not be a project under CEQA.
Attachments: 1. Board Report, 2. Attachment A - Link to HCD Website, 3. Attachment B - Public Comment, 4. Completed Board Order Item No. 16
Title
PLN220090 - CALTRANS/GARRAPATA BRIDGE RAILS
Public hearing to consider California Department of Transportation's ("Caltrans") appeal of the Garrapata Creek Bridge Rail Replacement Project on Highway 1, Big Sur.
Project Location: Garrapata Creek Bridge near post mile 63.0 on HWY 1, Big Sur Land Use Plan.
Proposed California Environmental Quality Act ("CEQA") action: Continuing the project would be an administrative activity of government which would not be a project under CEQA.
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors make a motion to continue the appeal hearing on the Garrapata Creek Bridge Rail Replacement Project to a date certain of June 25, 2024.

PROJECT INFORMATION:
Agent: Peter Hendrix
Project Applicant: California Department of Transportation (Caltrans)
Zoning: WSC/40-D
Plan Area: Big Sur Land Use Plan
Flagged and Staked: No (visual simulations provided)

DISCUSSION:
The California Department of Transportation ("Caltrans") proposes to remove and replace the bridge rails on the Garrapata Creek Bridge, a historic bridge individually eligible for listing on the National Register of Historic Places and California Register of Historic Resources. On December 6, 2023, the Board of Supervisors ("Board") heard an appeal of the Planning Commission denial of this combined development permit. At the hearing, the Board adopted a motion of intent to deny the project and requested that staff return with findings for denial of the permit.

Between December 2023 and January 2024, Caltrans coordinated with County staff and Coastal Commission staff on the next steps and the possibility of submitting additional details and analysis. On January 30, 2024, the Board of Supervisors continued the hearing on the item to March 26, 2024, to provide additional time for Caltrans and County staff to review new materials. Caltrans submitted supplemental packages of information on February 23, 2024, and March 6, 2024, which the Board of Supervisor...