Skip to main content
File #: A 24-464    Name: Amend. 3 Biggs Cardosa Associates, Inc. for the Hartnell Road Bridge Replacement Project (RFP #10804)
Type: BoS Agreement Status: Passed
File created: 9/19/2024 In control: Board of Supervisors
On agenda: 10/8/2024 Final action: 10/8/2024
Title: a. Approve Amendment No. 3 to Professional Services Agreement No. A-15826, Multi-Year Agreement #3200*6415, with Biggs Cardosa Associates, Inc. to continue to provide construction management services for the Hartnell Road Bridge Replacement Project, County Bridge No. 209, Request for Proposals #10804, to increase the not to exceed amount by $75,567 for a total amount not to exceed $955,739 with no extension to the term from June 15, 2022 to June 14, 2025, with the option to extend the term for two additional 1-year period(s); and b. Authorize the Contracts & Purchasing Officer or their designee to execute Amendment No. 3 to Professional Services Agreement No. A-15826 and future amendments to the Agreement where the amendments do not significantly alter the scope of work or increase the approved Agreement amount.
Attachments: 1. Board Report, 2. Attachment A - Proposed A3 to PSA, 3. Attachment B - A2 to PSA, 4. Attachment C - A1 to PSA, 5. Attachment D - PSA, 6. Attachment E - Project Budget, 7. Attachment F - Location Map, 8. Attachment G - Summary of PSA and Annual Expenditures and Balance, 9. Completed Board Order Item No. 26
Title
a. Approve Amendment No. 3 to Professional Services Agreement No. A-15826, Multi-Year Agreement #3200*6415, with Biggs Cardosa Associates, Inc. to continue to provide construction management services for the Hartnell Road Bridge Replacement Project, County Bridge No. 209, Request for Proposals #10804, to increase the not to exceed amount by $75,567 for a total amount not to exceed $955,739 with no extension to the term from June 15, 2022 to June 14, 2025, with the option to extend the term for two additional 1-year period(s); and
b. Authorize the Contracts & Purchasing Officer or their designee to execute Amendment No. 3 to Professional Services Agreement No. A-15826 and future amendments to the Agreement where the amendments do not significantly alter the scope of work or increase the approved Agreement amount.
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors:
a. Approve Amendment No. 3 to Professional Services Agreement No. A-15826, Multi-Year Agreement #3200*6415, with Biggs Cardosa Associates, Inc. to continue to provide construction management services for the Hartnell Road Bridge Replacement Project, County Bridge No. 209, Request for Proposals #10804, to increase the not to exceed amount by $75,567 for a total amount not to exceed $955,739 with no extension to the term from June 15, 2022 to June 14, 2025, with the option to extend the term for two additional 1-year period(s); and
b. Authorize the Contracts & Purchasing Officer or their designee to execute Amendment No. 3 to Professional Services Agreement No. A-15826 and future amendments to the Agreement where the amendments do not significantly alter the scope of work or increase the approved Agreement amount.

SUMMARY/DISCUSSION:
The County of Monterey Department of Public Works, Facilities and Parks (PWFP) is replacing the existing two-lane Hartnell Road Bridge (County Bridge No. 209) over Alisal Creek in Monterey County, California, with a wider bridge, Hartnell Road ...

Click here for full text