Title
Approve and authorize the Director of Public Works, Facilities and Parks (PWFP) to execute Amendment No. 1 to Agreement No. A-17868 between the County of Monterey (County) and Avila Brothers Inc., doing business as Avila Construction Company for the 65650 Bradley Street, Bradley-New Bradley Library and Resiliency Center Project No. 8821, Bid Package No. 10966 (Project), to update contract schedule, with no increase to the total contract amount.
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors approve and authorize the Director of Public Works, Facilities and Parks (PWFP) to execute Amendment No. 1 to Agreement No. A-17868 between the County of Monterey (County) and Avila Brothers Inc., doing business as Avila Construction Company for the 65650 Bradley Street, Bradley-New Bradley Library and Resiliency Center Project No. 8821, Bid Package No. 10966 (Project), to update contract schedule, with no increase to the total contract amount.
SUMMARY:
Staff is recommending that the Board of Supervisors (Board) approve and authorize the Director of Public Works, Facilities and Parks (PWFP) to execute Amendment No. 1 to Agreement No. 17868 (sometimes referred to as “construction contract” or “contract”) between the County and Avila Brothers Inc., doing business as (dba) Avila Construction Company. Proposed Amendment No. 1 to the construction contract between the County and Avila Construction Company will update the contract schedule from calendar days to working days to align with the requirements provided in Addendum No. 3, Pre-Bid Request for Information (RFI) No. 15.
DISCUSSION:
On July 7, 2026, the Board approved and awarded Agreement No. 17868, consisting of a construction contract to Avila Brothers Inc., dba Avila Construction Company, for the Bradley Library Replacement Project in the amount of $3,474,386. The Project includes construction of a new 2,500-square-foot library building, associated site improvements, utility extensions, ...
Click here for full text