File #: RES 12-0105    Name: NOC Tombleson Inc Jail Restroom Renovation 8546
Type: BoS Resolution Status: Passed
File created: 10/16/2012 In control: Board of Supervisors
On agenda: 11/6/2012 Final action: 11/6/2012
Title: Adopt a Resolution: a. Accepting the Certificate of Completion for construction of the Jail Restroom Renovation-1410 Natividad Rd, Project No. 8546, Bid Package No. 10345, performed by Tombleson, Inc.; and b. Authorizing the Director of Public Works to execute and record the Notice of Completion for the Jail Restroom Renovation-1410 Natividad Rd, Project No. 8546, Bid Package No. 10345, performed by Tombleson, Inc.
Sponsors: Public Works / RMA
Attachments: 1. Resolution, 2. Project Budget, 3. Certificate of Completion, 4. Notice of Completion, 5. Location Map, 6. Completed Board Order & Resolution, 7. Executed Certificates of Completion
Title
Adopt a Resolution:
a. Accepting the Certificate of Completion for construction of the Jail Restroom Renovation-1410 Natividad Rd, Project No. 8546, Bid Package No. 10345, performed by Tombleson, Inc.; and
b. Authorizing the Director of Public Works to execute and record the Notice of Completion for the Jail Restroom Renovation-1410 Natividad Rd, Project No. 8546, Bid Package No. 10345, performed by Tombleson, Inc.

Report
RECOMMENDATIONS:
It is recommended that the Board of Supervisors adopt a Resolution:

a. Accepting the Certificate of Completion for construction of the Jail Restroom Renovation-1410 Natividad Rd, Project No. 8546, Bid Package No. 10345, performed by Tombleson, Inc.; and

b. Authorizing the Director of Public Works to execute and record the Notice of Completion for the Jail Restroom Renovation-1410 Natividad Rd, Project No. 8546, Bid Package No. 10345, performed by Tombleson, Inc.

SUMMARY/DISCUSSION:
On May 1, 2012, the Board of Supervisors awarded a contract to Tombleson, Inc., for construction of the Jail Restroom Renovation-1410 Natividad Rd, Project No. 8546, Bid Package No. 10345, (Project) in the total amount of $61,875 at the Adult Detention Facility. In June 2012, construction began to install new floor, wall and ceiling finishes, repair or replacement of stainless steel access covers, selective demolition of masonry, and related tasks. The County approved multiple changes in the contract work, mostly to correct for water damage and to address high moisture content in the existing subfloor. On September 25, 2012, the Board approved Change Order No. 03 to Agreement No. A-12209 with Tombleson for a total contract value of $72,161. The contract is now complete in all respects in accordance with the Plans and Special Provisions. The work is ready to be accepted by the Board.

OTHER AGENCY INVOLVEMENT:
The Sheriff’s office concurs with the recommendation.

FINANCING:
There is no impact to the General Fund. On September 25, 2012...