File #: 14-949    Name: Feasibility Study for State Hwy 1 at Dolan Rd Safety & Operational Improvements
Type: General Agenda Item Status: Agenda Ready
File created: 8/20/2014 In control: Budget Committee
On agenda: 8/27/2014 Final action:
Title: a. Receive a report on the Feasibility Study for the State Highway 1 at Dolan Road Safety and Operational Improvements; b. Support approval of alternatives 2, 3 and 4 combined as the short term improvement project at State Highway 1 at Dolan Road; c. Support authorizing and directing the Resource Management Agency - Public Works to work with Caltrans and the Transportation Agency for Monterey County to seek funding for alternative 2, 3 and 4 combined; d. Support approval of the addition of the State Highway 1 at Dolan Road Project, Project 1372 to the approved Work Plan for Fiscal Year 2014-15; e. Support approval of an increase in appropriations in the amount of $28,261 in the FY 2014-15 Road Fund, Fund 002-3000-8195-RMA012, for the State Highway 1 at Dolan Road Project, Project 1372; and g. Support authorization of the Auditor-Controller to incorporate the approved modification in the FY 2014-15 Budget.
Sponsors: Public Works / RMA
Attachments: 1. Attachment 1 Feasibility Study & Appendix A, 2. Attachment 2 Location Map and Conceptual Plans of each Alternative
Title
a. Receive a report on the Feasibility Study for the State Highway 1 at Dolan Road Safety and Operational Improvements;
b. Support approval of alternatives 2, 3 and 4 combined as the short term improvement project at State Highway 1 at Dolan Road;
c. Support authorizing and directing the Resource Management Agency - Public Works to work with Caltrans and the Transportation Agency for Monterey County to seek funding for alternative 2, 3 and 4 combined;
d. Support approval of the addition of the State Highway 1 at Dolan Road Project, Project 1372 to the approved Work Plan for Fiscal Year 2014-15;
e. Support approval of an increase in appropriations in the amount of $28,261 in the FY 2014-15 Road Fund, Fund 002-3000-8195-RMA012, for the State Highway 1 at Dolan Road Project, Project 1372; and
g. Support authorization of the Auditor-Controller to incorporate the approved modification in the FY 2014-15 Budget.
Report

RECOMMENDATION:
It is recommended that the Budget Committee:

a. Receive a report on the Feasibility Study for the State Highway 1 at Dolan Road Safety and Operational Improvements;

b. Support approval of alternatives 2, 3 and 4 combined as the short term improvement project at State Highway 1 at Dolan Road;

c. Support authorizing and directing the Resource Management Agency - Public Works to work with Caltrans and the Transportation Agency for Monterey County to seek funding for alternative 2, 3 and 4 combined;

d. Support approval of the addition of the State Highway 1 at Dolan Road Project, Project 1372 to the approved Work Plan for Fiscal Year 2014-15;

e. Support approval of an increase in appropriations in the amount of $28,261 in the FY 2014-15 Road Fund, Fund 002-3000-8195-RMA012, for the State Highway 1 at Dolan Road Project, Project 1372; and

g. Support authorization of the Auditor-Controller to incorporate the approved modification in the FY 2014-15 Budget.

SUMMARY/DISCUSSION:
In February 2012, the Co...

Click here for full text