Title
Adoption of a Resolution to:
a. Approve the Scope, Cost and Schedule for the New Juvenile Hall Project and submittal to the Board of State and Community Corrections for Project Establishment with the State; and
b. Support authorizing and directing the County Administrative Officer Resource Management Agency Director, and Chief Probation Officer to take such other further actions as may be necessary or appropriate to move the Project forward to meet State milestone requirements for design submissions as defined under the SB 81 2007 Youthful Offender Rehabilitative Facility Construction Funding Program.
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors adopt a Resolution to:
a. Approve the Scope, Cost, and Schedule for the New Juvenile Hall Project and submittal to the Board of State and Community Corrections for Project Establishment with the State; and
b. Authorize and direct the County Administrative Officer, Resource Management Agency Director, and Chief Probation Officer to take such other further actions as may be necessary or appropriate to move the Project forward to meet State milestone requirements for design submissions as defined under the SB 81 2007 Youthful Offender Rehabilitative Facility Construction Funding Program.
SUMMARY/DISCUSSION:
Support of the recommended actions provide for the required documents for project establishment and authorizes the County Administrative Officer (CAO), Resource Management (RMA) Director, and Chief Probation Officer to take other further actions as may be necessary or appropriate to move the Project forward to meet State milestone requirements for design submissions as defined under the Senate Bill 81 (SB 81) 2007 Youthful Offender Rehabilitative Facility Construction Funding Program.
On April 22, 2014, the Board of Supervisors authorized the Chief Probation Officer to submit the revised Project Scope, Cost, and Schedule to the Board of State and Community Corrections ...
Click here for full text