a. Receive a report on the Feasibility Study for the State Highway 1 at Dolan Road Safety and Operational Improvements;
b. Approve Improvement Alternatives 2, 3, and 4, combined as the short term improvement project at State Highway 1 at Dolan Road;
c. Authorize and direct the Resource Management Agency - Public Works to work with Caltrans and the Transportation Agency for Monterey County to seek funding for Improvement Alternatives 2, 3, and 4, combined;
d. Approve addition of the State Highway 1 at Dolan Road Project, Project 1372, to the approved Work Plan for FY 2014-15;
e. Approve an increase in appropriations in the amount of $28,261 in the FY 2014-15 Road Fund, Fund 002-3000-8195-RMA012, for the State Highway 1 at Dolan Road Project, Project 1372 (4/5th vote required); and
f. Authorize the Auditor-Controller to incorporate the approved modification in the FY 2014-15 Budget.
Report
RECOMMENDATIONS:
It is recommended that the Board of Supervisors:
a. Receive a report on the Feasibility Study for the State Highway 1 at Dolan Road Safety and Operational Improvements;
b. Approve Improvement Alternatives 2, 3, and 4, combined as the short term improvement project at State Highway 1 at Dolan Road;
c. Authorize and direct the Resource Management Agency - Public Works to work with Caltrans and the Transportation Agency for Monterey County to seek funding for Improvement Alternatives 2, 3, and 4, combined;
d. Approve addition of the State Highway 1 at Dolan Road Project, Project 1372, to the approved Work Plan for FY 2014-15;
e. Approve an increase in appropriations in the amount of $28,261 in the FY 2014-15 Road Fund, Fund 002-3000-8195-RMA012, for the State Highway 1 at Dolan Road Project, Project 1372 (4/5th vote required); and
f. Authorize the Auditor-Controller to incorporate the approved modification in the FY 2014-15 Budget.
SUMMARY/DISCUSSION:
In February 2012, the County hired Hatch Mott MacDonald, LLC to prepar...