File #: A 23-462    Name: Award Contract to Teichert Const Harkins Hunter Proj
Type: BoS Agreement Status: Passed
File created: 9/14/2023 In control: Board of Supervisors
On agenda: 9/26/2023 Final action: 9/26/2023
Title: a. Award a contract to Teichert Construction, the lowest responsible bidder for the Harkins Road and Hunter Lane Rehabilitation, Project No. 1172, in the total amount of $5,655,350; b. Approve the Performance and Payment Bonds executed and provided by Teichert Construction; c. Authorize a contingency, not to exceed 10% of the contract amount or $565,535, to provide funding for approved contract change orders; d. Authorize the Director of Public Works, Facilities and Parks to execute the contract subject to the provisions of the Public Contract Code and Board Policies as applicable, approve change orders to the contract that do not exceed 10% of the original contract amount ($565,535), do not significantly change the scope of work, not to exceed the maximum contract amount of $6,220,885; and e. Authorize the Director of Public Works, Facilities and Parks to execute a Certificate of Completion and record a Notice of Completion with the County Recorder when the Director determines that th...
Attachments: 1. Board Report, 2. Attachment A - Contract Bonds Insur, 3. Attachment B - Project Budget, 4. Attachment C - Bid Summary, 5. Attachment D - Location Map, 6. Completed Board Order Item No. 36
Title
a. Award a contract to Teichert Construction, the lowest responsible bidder for the Harkins Road and Hunter Lane Rehabilitation, Project No. 1172, in the total amount of $5,655,350;
b. Approve the Performance and Payment Bonds executed and provided by Teichert Construction;
c. Authorize a contingency, not to exceed 10% of the contract amount or $565,535, to provide funding for approved contract change orders;
d. Authorize the Director of Public Works, Facilities and Parks to execute the contract subject to the provisions of the Public Contract Code and Board Policies as applicable, approve change orders to the contract that do not exceed 10% of the original contract amount ($565,535), do not significantly change the scope of work, not to exceed the maximum contract amount of $6,220,885; and
e. Authorize the Director of Public Works, Facilities and Parks to execute a Certificate of Completion and record a Notice of Completion with the County Recorder when the Director determines that the contract is complete in all respects in accordance with the Plans and Special Provisions for the construction of Harkins Road and Hunter Lane Rehabilitation, Project No. 1172.
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors:
a. Award a contract to Teichert Construction, the lowest responsible bidder for the Harkins Road and Hunter Lane Rehabilitation, Project No. 1172, in the total amount of $5,655,350;
b. Approve the Performance and Payment Bonds executed and provided by Teichert Construction;
c. Authorize a contingency, not to exceed 10% of the contract amount or $565,535, to provide funding for approved contract change orders;
d. Authorize the Director of Public Works, Facilities and Parks to execute the contract subject to the provisions of the Public Contract Code and Board Policies as applicable, approve change orders to the contract that do not exceed 10% of the original contract amount ($565,535), do not significantly change the scope of ...