File #: A 25-134    Name: Approve a 30% Contingency for the Las Lomas Drive Bicycle Lane and Pedestrian Project
Type: BoS Agreement Status: Public Works, Facilities & Parks - Consent
File created: 4/18/2025 In control: Board of Supervisors
On agenda: 5/6/2025 Final action:
Title: a. Authorize an additional contingency of 10% or $347,710 in contract amount with the Don Chapin Company Inc., for the Las Lomas Drive Bicycle Lane and Pedestrian Project, Project No. 8867, (Federal Project No. 5944 (135)) in the total amount of $3,471,000 and b. Authorize the Director of Public Works, Facilities, and Parks (PWFP) to execute contract change orders where the overall all total value of change orders does not exceed the original contract amount plus approved contingency funding, and do not significantly change the scope of work.
Attachments: 1. Board Report, 2. Attachment A - Location Map, 3. Attachment B - Project Budget
Date Action ByActionResultAction DetailsSearchable Meeting DetailsVideo
No records to display.
Title
a. Authorize an additional contingency of 10% or $347,710 in contract amount with the Don Chapin Company Inc., for the Las Lomas Drive Bicycle Lane and Pedestrian Project, Project No. 8867, (Federal Project No. 5944 (135)) in the total amount of $3,471,000 and
b. Authorize the Director of Public Works, Facilities, and Parks (PWFP) to execute contract change orders where the overall all total value of change orders does not exceed the original contract amount plus approved contingency funding, and do not significantly change the scope of work.
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors:
a. Authorize an additional contingency of 10% or $347,710 in contract amount with the Don Chapin Company Inc., for the Las Lomas Drive Bicycle Lane and Pedestrian Project, Project No. 8867, (Federal Project No. 5944 (135)) in the total amount of $3,471,000 and
b. Authorize the Director of Public Works, Facilities, and Parks (PWFP) to execute contract change orders where the overall all total value of change orders does not exceed the original contract amount plus approved contingency funding, and do not significantly change the scope of work.

DISCUSSION:
The Las Lomas Drive Bicycle Lane and Pedestrian Project, Project No. 8867 (the Project) consists of constructing approximately 1,320 linear feet of sidewalks between Sill Road and Las Lomas Drive, Class II (striped) bike lanes, curb, gutter, road widening, driveway conforms, retaining wall and bioretention facility in the community of Las Lomas. A Location Map is presented in Attachment A. The County was awarded a combined State and Federal Active Transportation Program (ATP) grant of $2,431,000 for construction of the Project.

On September 17, 2024, the Board of Supervisors authorized PWFP to award a contract to the Don Chapin Company Inc., the lowest responsible bidder to construct the Project in the total amount of $3,471,000; authorized a contingency of $347,100, to provide funding ...