File #: 17-0323    Name: Adopt Plans and Special Provisions-Bridge Preventive Maintenance Project No. 1143
Type: General Agenda Item Status: Passed
File created: 3/31/2017 In control: Board of Supervisors
On agenda: 4/18/2017 Final action: 4/18/2017
Title: a. Adopt Plans and Special Provisions for the Bridge Preventive Maintenance Project (Methacrylate & Polyester Overlay), Project No. 1143, Federal Aid Project No: BPMPL-5944(122); and b. Authorize the Resource Management Agency Director to advertise the "Notice to Bidders" in the Monterey County Weekly.
Sponsors: Public Works / RMA
Attachments: 1. Board Report, 2. Attachment 1 - Project Budget, 3. Attachment 2 - Notice to Bidders, 4. Attachment 3 - Book One -Notice to Bidders, 5. Attachment 4 - Book Two -Bid Form, 6. Attachment 5 - Location Map, 7. Completed Board Order
Title
a. Adopt Plans and Special Provisions for the Bridge Preventive Maintenance Project (Methacrylate & Polyester Overlay), Project No. 1143, Federal Aid Project No: BPMPL-5944(122); and
b. Authorize the Resource Management Agency Director to advertise the "Notice to Bidders" in the Monterey County Weekly.
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors:

a. Adopt Plans and Special Provisions for the Bridge Preventive Maintenance Project (Methacrylate & Polyester Overlay), Project No. 1143, Federal Aid Project No: BPMPL-5944(122); and

b. Authorize the Resource Management Agency Director to advertise the "Notice to Bidders" in the Monterey County Weekly.

SUMMARY:
Adoption of the Plans and Special Provisions to the Standard Specifications will authorize the Resource Management Agency to proceed with advertising of the Bridge Preventive Maintenance Project (Methacrylate & Polyester Overlay), Federal Aid Project No: BPMPL-5944(122), Project No. 1143.

DISCUSSION:
The work to be done, in general, consists of bridge deck treatment for 5 bridges with polyester concrete overlay and bridge deck treatment for 11 bridges with a high molecular weight methacrylate; including but not limited to traffic control, repairing of bridge joint seals, paving bridge approaches with hot-mix-asphalt, and pavement delineation. The bid opening is set for May 12, 2017 at 3:00 p.m., in the Board of Supervisors' Conference Room 1032, Monterey County Government Center, 168 West Alisal Street, 1st Floor, Salinas, CA 93901. Project construction is scheduled to begin in August 2017.

The project has been determined to be categorically exempt (Class 1) from the California Environmental Quality Act (CEQA) because it is to be perform repair and maintenance of existing streets and similar facilities, which involves no expansion of an existing use (See CCR ? 15301 Existing Facilities).




OTHER AGENCY INVOLVEMENT:
The Office of the County Counsel, Auditor-Controlle...