File #: RES 23-203    Name: FY24 NGEN Capital Appropriations Increase
Type: BoS Resolution Status: General Government - Consent
File created: 10/26/2023 In control: Board of Supervisors
On agenda: 11/7/2023 Final action: 11/7/2023
Title: Authorize the Auditor-Controller to amend the NGEN (Next Generation Radio System) Capital Fund Fiscal Year 2023-24 Adopted Budget (405-1520-EME002-8426-7531) to increase appropriations by $722,000 financed with fund balance to pay for NGEN projects which were not completed in FY2022-23 (4/5th vote required).
Attachments: 1. Board Report, 2. Resolution, 3. Resolution, 4. Completed Board Order No. 58, 5. Completed Resolution No. 58, 6. Revised Completed Resolution No. 58
Title
Authorize the Auditor-Controller to amend the NGEN (Next Generation Radio System) Capital Fund Fiscal Year 2023-24 Adopted Budget (405-1520-EME002-8426-7531) to increase appropriations by $722,000 financed with fund balance to pay for NGEN projects which were not completed in FY2022-23 (4/5th vote required).

Report
RECOMMENDATION:
It is recommended that the Board of Supervisors adopt a resolution to:
a. Authorize the Auditor-Controller to amend the NGEN (Next Generation Radio System) Capital Fund Fiscal Year 2023-24 Adopted Budget (405-1520-EME002-8426-7531) to increase appropriations by $722,000 financed with fund balance to pay for NGEN projects which were not completed in FY2022-23 (4/5th vote required).

SUMMARY/DISCUSSION:
In FY 2022-23, the Information Technology Department (ITD) planned to complete an ISSI Gateway project for $275,000 and a NGEN Phase-2 Upgrade for $438,000 for the enhancement of the NGEN Radio System. These projects were budgeted in FY2022-23 but not completed and no budget was submitted for the NGEN Capital Fund in FY2023-24 because at the time of budget creations, it was anticipated that these projects would be completed.

The ISSI Gateway provides interoperability between the NGEN radio system and FirstNet for supported radios. However, the current project scope will not include integration with a foreign system such as Motorola. The NGEN Phase-2 Upgrade doubles channel capacity at all NGEN digital radio sites. These projects are funded by savings from the original buildout of the radio system and from prior years' surplus in the NGEN Operations and Maintenance (O&M) Fund 026 which were transferred into fund 405 in the FY2022-23 budget.

Additionally, $9,000 is needed to reimburse ITD for the relocation of the Roberts Knoll radio site. This site relocation was required because ITD was requested by the new landlord at Roberts Knoll to remove the NGEN shelter and tower. The total cost of the site relocation is $2...