Consider receiving an update on implementation of the Interim Operations Plan for San Antonio and Nacimiento Reservoirs and approving continued implementation of the Interim Operations Plan. (Staff: Joey Klein)
Report
RECOMMENDATION:
It is recommended that the Board of Directors:
Receive an update on implementation of the Interim Operations Plan for San Antonio and Nacimiento Reservoirs and approve continued implementation of the Interim Operations Plan.
SUMMARY
On November 21, 2022, the Monterey County Water Resources Agency Board of Directors (BOD) adopted the Interim Operations Plan (IOP) for Nacimiento and San Antonio Reservoirs to address specific conditions where the Flow Prescription did not meet its intended goals over the first 13 years of Salinas Valley Water Project operation. The IOP was implemented beginning in 2023, but natural flows (2023, 2024, and 2026) and Flow Prescription triggered actions (2025) obviated the need for IOP support to meet Flow Prescription passage targets in the first four years of implementation.
In February of 2025, a release action based on Flow Prescription triggers provided an opportunity to test and verify a new steelhead migration flow threshold determined in a recent critical riffle study conducted in support of the development of the Habitat Conservation Plan.
On October 20, 2025, the BOD approved the modification of the flow target at the Salinas River near Chualar USGS gage to 80 cfs.
The IOP has provided supplemental adaptive management to the existing Flow Prescription while the Salinas River Operations Habitat Conservation Plan (HCP) is under development.
Staff finds that the IOP continues to provide a flexible and effective mechanism to address shortcomings of the Flow prescription. Hydrologic conditions have effectively precluded the need for IOP actions since adoption. Staff recommends continuation of IOP implementation with the modified steelhead migration flow target.
The Agency’s Water Reso...