Title: Support adopting a resolution to amend the Water Resources Agency's FY 2019-20 Adopted Budget for Fund 134 - Salinas River Diversion Facility Operations Fund (134-9300-8497-WRA028) by increasing appropriations in the amount of $110,000 financed by Unassigned Fund Balance.
Attachments: 1. Budget Committee Report, 2. Budget Amendment 1 Summary
Date Action ByActionResultAction DetailsSearchable Meeting DetailsVideo
No records to display.
Title
Support adopting a resolution to amend the Water Resources Agency's FY 2019-20 Adopted Budget for Fund 134 - Salinas River Diversion Facility Operations Fund (134-9300-8497-WRA028) by increasing appropriations in the amount of $110,000 financed by Unassigned Fund Balance.
Report
RECOMMENDATION:
It is recommended that the Budget Committee:

Support adopting a resolution to amend the Water Resources Agency's FY 2019-20 Adopted Budget for Fund 134 - Salinas River Diversion Facility Operations Fund (134-9300-8497-WRA028) by increasing appropriations in the amount of $110,000 financed by Unassigned Fund Balance.

SUMMARY/DISCUSSION:
The Monterey County Water Resources Agency (MCWRA) and Monterey One Water (M1W), formerly known as Monterey Regional Water Pollution Control Agency (MRWPCA), entered into an Amended and Restated Water Recycling Agreement (Agreement), which included terms for ownership, operation, maintenance, payments for the Castroville Seawater Intrusion Project (CSIP), Salinas Valley Reclamation Project (SVRP), and Salinas River Diversion Facility (SRDF). Section 7.06 of the Agreement requires annual budgets and modifications to be approved by the M1W Board of Directors, MCWRA Board of Directors and MCWRA Board of Supervisors.

Section 7.06 of the Agreement specifies the procedure and deadlines for adoption of annual budgets for the three projects. During FY 2019-20 budget preparation, both agencies were not able to adhere to the deadlines and agreed to submit a budget similar to FY 2018-19's budget with the understanding that both agencies would continue to work on developing a comprehensive FY 2019-20 budget. After months of collaboration, both agencies have agreed on final figures which resulted in increases to all three projects as follows:

Program Approved Revised Change
SVRP 2,788,000 2,999,254 211,254
CSIP 1,567,000 2,130,525 563,525
SRDF 604,000 845,2...