File #: BC 25-087    Name: Key Capital Improvement Projects Status Q1 & Q2
Type: Budget Committee Status: Agenda Ready
File created: 9/4/2025 In control: Budget Committee
On agenda: 9/24/2025 Final action:
Title: Receive a report on Key Capital Improvement Projects managed by the Public Works, Facilities and Parks Department (PWFP) for the period of July 1, 2024 through December 31, 2024 (Fiscal Year 2024-25, Quarters 1 and 2).
Attachments: 1. BC Report, 2. Attachment A - PWFP CIP Status FY 2024-25 Q1 & Q2, 3. Attachment B - Public Works Projects, 4. Attachment C - Facilities Projects
Date Action ByActionResultAction DetailsSearchable Meeting DetailsVideo
No records to display.
Title
Receive a report on Key Capital Improvement Projects managed by the Public Works, Facilities and Parks Department (PWFP) for the period of July 1, 2024 through December 31, 2024 (Fiscal Year 2024-25, Quarters 1 and 2).
Report
RECOMMENDATION:
It is recommended the Budget Committee receive a report on Key Capital Improvement Projects managed by the Public Works, Facilities and Parks Department (PWFP) for the period of July 1, 2024 through December 31, 2024 (Fiscal Year 2024-25, Quarters 1 and 2).
 
SUMMARY:
This report provides a status update of key capital improvement projects managed by PWFP for the first and second quarters of Fiscal Year (FY) 2024-25.  During this period, there were active capital projects totaling $594.8 million:  29 Public Works (Road and Bridge) projects at $296.6 million and 29 Facilities projects at $298.2 million.  This report provides an update on key Facilities and Public Works projects that were completed and those with significant activity during the second half of FY 2024-25.
 
DISCUSSION:
Capital improvement projects are non-reoccurring, exceed $100,000 and have an estimated useful life of at least five years to provide long-term assets to the County of Monterey.   Active capital improvement projects being managed by PWFP are summarized in Attachment A.  Additional detail is provided in Attachments B & C for selected completed projects and those with significant activity during the first quarter (Q1) and second quarter (Q2) of FY 2024-25. 
 
OTHER KEY PROJECTS
In addition to the key capital projects discussed above, PWFP is implementing many water and sewer infrastructure projects using American Rescue Plan Act (ARPA) funds.  Updates on the status of these projects are provided via a separate report.  Also, PWFP is managing construction of the first phase of the Carmel River Flood plain Restoration and Environmental Enhancement Project (CRFREE), but the Housing and Community Development Department (HCD) manages the over...