File #: 23-882    Name: BoS 11-28-2023 Kennedy-Jenks Amendment No. 7
Type: General Agenda Item Status: General Government - Consent
File created: 11/15/2023 In control: Board of Supervisors
On agenda: 11/28/2023 Final action:
Title: Approve and authorize the County Counsel's Office to execute Renewal and Amendment #7, with Kennedy/Jenks Consultants, to extend the agreement for one year with an additional $44,740.53 in funding, for a new full term of March 1, 2016 to September 1, 2024, and a new NTE amount of $743,000 for the construction, testing, reporting and oversight of a bioventing system at the Lake San Antonio Resort/Marina site, required by the California State Water Resources Control Board and Regional Board ("Water Boards") to address fuel spill remediation at the lake, to be funded from County Counsel - Enterprise Risk (001-1210-8429-COU006).
Attachments: 1. Board Report, 2. Proposed Amendment No.pdf, 3. Completed Board Order Item No. 49
Date Action ByActionResultAction DetailsSearchable Meeting DetailsVideo
No records to display.
Title
Approve and authorize the County Counsel's Office to execute Renewal and Amendment #7, with Kennedy/Jenks Consultants, to extend the agreement for one year with an additional $44,740.53 in funding, for a new full term of March 1, 2016 to September 1, 2024, and a new NTE amount of $743,000 for the construction, testing, reporting and oversight of a bioventing system at the Lake San Antonio Resort/Marina site, required by the California State Water Resources Control Board and Regional Board ("Water Boards") to address fuel spill remediation at the lake, to be funded from County Counsel - Enterprise Risk (001-1210-8429-COU006).
Report
RECOMMENDATION:
It is recommended that the Board of Supervisors approve and authorize the County Counsel's Office to execute Renewal and Amendment #7, with Kennedy/Jenks Consultants, to extend the agreement for one year with an additional $44,740.53 in funding, for a new full term of March 1, 2016 to September 1, 2024, and an new NTE amount of $743,000, for the construction, testing, reporting and oversight of a bioventing system at the Lake San Antonio Resort/Marina site, required by the California State Water Resources Control Board and Regional Board ("Water Boards") to address fuel spill remediation at the lake, to be funded from County Counsel - Enterprise Risk (001-1210-8429-COU006).

SUMMARY/DISCUSSION:
County Counsel/Risk Management Division has managed the contracts for the remediation of the fuel spills at the Lakes Resort, including payment and tracking of costs. In 2013, the Board of Supervisors authorized the transfer of General Fund Contingency funds for $1,018,685 to a newly created Lakes Fuel Spill Budget Unit 8429 (now included in the County Budget under "Enterprise Risk Budget Unit 8429") for costs associated with the remediation efforts.

The County initially entered into a contract with Kennedy/Jenks Consultants for work at Lake San Antonio in 2016, and continues utilizing the services of the firm for t...