File #: RES 12-0139    Name: NOC Stronger Building Svcs - Old Jail Roof Replacemnt
Type: BoS Resolution Status: Passed
File created: 12/18/2012 In control: Board of Supervisors
On agenda: 1/8/2013 Final action: 1/8/2013
Title: Adopt a Resolution: a. Accepting the Certificate of Completion for construction of 142 W. Alisal St, Salinas, CA-Old Jail-Roof Replacement and Limited Weatherization, Project No. 8820, Bid Package No. 10362, performed by Stronger Building Services; and b. Authorizing the Director of Public Works to execute and record the Notice of Completion for 142 W. Alisal St, Salinas, CA-Old Jail-Roof Replacement and Limited Weatherization, Project No. 8820, Bid Package No. 10362, performed by Stronger Building Services.
Sponsors: Public Works / RMA
Attachments: 1. Resolution, 2. Project Budget, 3. 2005 Adopted Resolution No. 05-019, 4. Certificate of Completion, 5. Notice of Completion, 6. Location Map, 7. Completed Board Order, 8. Resolution No. 13-003, 9. Recorded Page
Title
Adopt a Resolution:
a. Accepting the Certificate of Completion for construction of 142 W. Alisal St, Salinas, CA-Old Jail-Roof Replacement and Limited Weatherization, Project No. 8820, Bid Package No. 10362, performed by Stronger Building Services; and
b. Authorizing the Director of Public Works to execute and record the Notice of Completion for 142 W. Alisal St, Salinas, CA-Old Jail-Roof Replacement and Limited Weatherization, Project No. 8820, Bid Package No. 10362, performed by Stronger Building Services.

StaffReport
RECOMMENDATIONS:
It is recommended that the Board of Supervisors adopt a Resolution:

a. Accepting the Certificate of Completion for construction of 142 W. Alisal St, Salinas, CA-Old Jail-Roof Replacement and Limited Weatherization, Project No. 8820, Bid Package No. 10362, performed by Stronger Building Services; and

b. Authorizing the Director of Public Works to execute and record the Notice of Completion for 142 W. Alisal St, Salinas, CA-Old Jail-Roof Replacement and Limited Weatherization, Project No. 8820, Bid Package No. 10362, performed by Stronger Building Services.

SUMMARY/DISCUSSION:
On October 9, 2012, the Board of Supervisors awarded a contract to Stronger Building Services (SBS), for construction of 142 W. Alisal St, Salinas, CA-Old Jail-Roof Replacement and Limited Weatherization, Project No. 8820, Bid Package No. 10362 (Project), in the total amount of $187,000. On October 18, 2012, SBS mobilized to begin the scoped repairs at the Old Jail consisting of installation of a new roof system as well as removal of scuppers and the exercise yard enclosure. The work was completed on time and at the original contract value of $187,000. This contract is now complete in all respects in accordance with the Plans and Special Provisions. The work is ready to be accepted by the Board.

Phase 1 of the project includes all initial programming activities through FY 2007-08 to develop early alternatives for the future use of the facilit...

Click here for full text