Title: Adopt Resolution to: a. Approve the change in Scope, Cost, and Schedule for the New Juvenile Hall Project, Project 8811 (Project), to reduce the Project from a 150 medium-security-bed Juvenile Hall complex to a 120 medium-security-bed facility with essential administrative and support space improvements based on the State of California conditional award of $35 million, total project cost of $52,791,824, and project completion date of September 2019; b. Authorize the Chief of Probation to submit the revised project Scope, Cost, and Schedule to the Board of State and Community Corrections for approval; c. Contingent upon approval of the change in scope by BSCC, authorizing and directing the County Administrative Officer, Director of Public Works, and Chief of Probation to take such other further actions as authorized by the Board of Supervisors, as may be necessary or appropriate to move the Project forward to meet State milestone requirements for design submissions as defined under ...
Attachments: 1. Resolution, 2. Letter from Probation Department 3-20-14, 3. Project Budget, 4. Location_Map, 5. Completed Board Order & Resolution
Title
Adopt Resolution to:
a. Approve the change in Scope, Cost, and Schedule for the New Juvenile Hall Project, Project 8811 (Project), to reduce the Project from a 150 medium-security-bed Juvenile Hall complex to a 120 medium-security-bed facility with essential administrative and support space improvements based on the State of California conditional award of $35 million, total project cost of $52,791,824, and project completion date of September 2019;
b. Authorize the Chief of Probation to submit the revised project Scope, Cost, and Schedule to the Board of State and Community Corrections for approval;
c. Contingent upon approval of the change in scope by BSCC, authorizing and directing the County Administrative Officer, Director of Public Works, and Chief of Probation to take such other further actions as authorized by the Board of Supervisors, as may be necessary or appropriate to move the Project forward to meet State milestone requirements for design submissions as defined under the SB 81 2007 Youthful Offender Rehabilitative Facility Construction Funding Program.
report
RECOMMENDATION:
It is recommended that the Board of Supervisors adopt a Resolution to:

a. Approve the change in Scope, Cost, and Schedule for the New Juvenile Hall Project, Project 8811 (Project), to reduce the Project from a 150 medium-security-bed Juvenile Hall complex to a 120 medium-security-bed facility with essential administrative and support space improvements based on the State of California conditional award of $35 million, total project cost of $52,791,824, and project completion date of September 2019;

b. Authorize the Chief of Probation to submit the revised project Scope, Cost, and Schedule to the Board of State and Community Corrections for approval;

c. Contingent upon approval of the change in scope by BSCC, authorizing and directing the County Administrative Officer, Director of Public Works, and Chief of Probation to take such other further actions as a...