a. Authorizing the Monterey County Water Resources Agency to proceed with the Interlake Tunnel Project, including spillway modifications as a key component of the Interlake Tunnel Project;
b. Authorizing the General Manager of the Monterey County Water Resources Agency to prepare and issue Requests for Proposal for geotechnical and final design engineering; permitting and environmental approval; and, financing plan preparation and implementation;
c. Requesting the Monterey County Board of Supervisors to authorize proceeding with negotiation of a funding agreement between Monterey County and the Monterey County Water Resources Agency for an amount not to exceed $2.5 million to perform geotechnical and final design engineering; permitting and environmental approval; financing plan preparation and implementation; and, program management services, all for the Interlake Tunnel Project, said funds to be reimbursed to Monterey County if the Project is financed; and,
d. Authorizing the Monterey County Water Resources Agency to negotiate a Project Labor Agreement to be utilized by the contractors selected to construct the Interlake Tunnel Project.
Report
RECOMMENDATION:
It is recommended that the Monterey County Water Resources Agency Board of Supervisors:
a. Authorize the Monterey County Water Resources Agency to proceed with the Interlake Tunnel Project, including spillway modifications as a key component of the Interlake Tunnel Project;
b. Authorize the General Manager of the Monterey County Water Resources Agency to prepare and issue Requests for Proposal for geotechnical and final design engineering; permitting and environmental approval; and, financing plan preparation and implementation;
c. Request the Monterey County Board of Supervisors to authorize proceeding with negotiation of a funding agreement between Monterey County and the Monterey County Water Resources Agency for an amount not to exceed $2.5 million to perform geotechnica...