File #: 15-0381    Name: jail housing status report
Type: General Agenda Item Status: Agenda Ready
File created: 4/15/2015 In control: Budget Committee
On agenda: 4/29/2015 Final action:
Title: Receive a Quarterly Budget and Schedule Status Report on the Jail Housing Addition, Project 8819 (Project), for the period ending March 31, 2015.
Sponsors: Public Works / RMA
Attachments: 1. board report, 2. Project Budget, 3. PROJECT MILESTONE SCHEDULE
Title
Receive a Quarterly Budget and Schedule Status Report on the Jail Housing Addition, Project 8819 (Project), for the period ending March 31, 2015.

Report
RECOMMENDATION:
It is recommended that the Budget Committee receive a Quarterly Budget and Schedule Status Report on the Jail Housing Addition, Project 8819 (Project), for the period ending March 31, 2015.

SUMMARY/ DISCUSSION:

Key schedule components and budget status are summarized below.

Budget and Schedule: The Project is on budget. The Schematic Design was delayed by two months due to resubmittals by the Design Team. We have been able to make up fifteen of the forty days lost during Schematic Design phase. We anticipate making up the balance during the Construction Document phase. The Preliminary Plan (Design Development) documents have been submitted for review to the Board of State and Community Corrections (BSCC) on April 13, 2015 for approval from the State Public Works Board in July 2015. Construction will start in summer 2016.

State Milestones: The County's next submittal to the State Public Works Board is for Preliminary Plan Review in mid-July 2015.

CEQA Process: EMC Planning Group is progressing with the Final Environmental Impact Report and CEQA findings to be submitted to the Board of Supervisors in June 2015.

Real Estate Due Diligence: Final document revisions were submitted and approved by the State Department of General Services.

OTHER AGENCY INVOLVEMENT:
The Resource Management Agency - Public Works and the Office of the Sheriff continue to work jointly with the BSCC to meet all State requirements to maintain the conditional award by moving the project forward in design.

FINANCING:
Total estimated Project cost is $88,900,000, of which $8,900,000 was approved by the Board of Supervisors as the County's match. To-date expenditures total $3,280,417, including current year expenditures estimated at $1,294,267. The remaining County match balance of $5,...