File #: A 15-094    Name: Award Granite Rock Company River Rd Overlay
Type: BoS Agreement Status: Passed
File created: 4/29/2015 In control: Board of Supervisors
On agenda: 5/12/2015 Final action: 5/12/2015
Title: a. Award a contract to Granite Rock Company, the lowest responsible bidder, for the construction of the River Road Overlay project, Project No. 1724, with the bid amount of $1,469,668; b. Approve the Performance and Payment Bonds executed and provided by Granite Rock Company; c. Authorize a contingency (not to exceed 10% of the contract amount) to provide funding for approved contract change orders; d. Authorize the Director of Public Works to execute the contract and, subject to the terms of the Public Contract Code, approve change orders to the contract that do not exceed the 10% of the original contract amount, and do not significantly change the scope of work; and e. Authorize the Director of Public Works to execute a Certificate of Completion and record a Notice of Completion with the County Recorder when he determines that the contract is complete in all respects in accordance with the Plans and Special Provisions for the construction of the River Road Overlay project, Projec...
Sponsors: Public Works / RMA
Attachments: 1. Board Report, 2. Project Budget, 3. Bid Summary, 4. Contract for Public Work, 5. Performance Bond, 6. Payment Bond, 7. Location Map, 8. Completed Board Order
Title
a. Award a contract to Granite Rock Company, the lowest responsible bidder, for the construction of the River Road Overlay project, Project No. 1724, with the bid amount of $1,469,668;
b. Approve the Performance and Payment Bonds executed and provided by Granite Rock Company;
c. Authorize a contingency (not to exceed 10% of the contract amount) to provide funding for approved contract change orders;
d. Authorize the Director of Public Works to execute the contract and, subject to the terms of the Public Contract Code, approve change orders to the contract that do not exceed the 10% of the original contract amount, and do not significantly change the scope of work; and
e. Authorize the Director of Public Works to execute a Certificate of Completion and record a Notice of Completion with the County Recorder when he determines that the contract is complete in all respects in accordance with the Plans and Special Provisions for the construction of the River Road Overlay project, Project No. 1724, performed by Granite Rock Company.
Report

RECOMMENDATION:
It is recommended that the Board of Supervisors:

a. Award a contract to Granite Rock Company, the lowest responsible bidder, for the construction of the River Road Overlay project, Project No. 1724, with the bid amount of $1,469,668;

b. Approve the Performance and Payment Bonds executed and provided by Granite Rock Company;

c. Authorize a contingency (not to exceed 10% of the contract amount) to provide funding for approved contract change orders;

d. Authorize the Director of Public Works to execute the contract and, subject to the terms of the Public Contract Code, approve change orders to the contract that do not exceed the 10% of the original contract amount, and do not significantly change the scope of work; and

e. Authorize the Director of Public Works to execute a Certificate of Completion and record a Notice of Completion with the County Recorder when he determines that the cont...